HomeMy WebLinkAbout22-21-C CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
RMO YARD AREA 8 CHANGE ORDER NO. 01
FENCE RECONSTRUCTION APRIL18, 2023
CONTRACT NO. 22-21-C PAGE 1 OF 2
TO: YUKON FENCE COMPANY, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time.
INCREASE/DECREASE ITEMS AT UNIT BID PRICES:
This change was proposed the engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item
quantities to the actual quantities used.
Decreased Items:
Item Total Total
No. Description Unit Quantity Price Amount (0/6) o�
3 FID Permit Fees $ 170.00 $1.00 $170.00 17.00 17.00
4 Remove and Dispose Existing LF 1,003.00 1.00 1,003.00 54.22 54.22
Fence Along Perimeter
6 Install 6' High Chainlink Fence LF 21.00 28.00 588.00 0.92 0.92
with 3 Strands of Barbed Wire,
Posts on Concrete Foundation
and Appurtenances per Plan
TOTAL DECREASE: $1,761.00
This change did not impact the critical path of the project schedule, therefore, granting additional time was not
warranted.
Contractor We the above signed contractor,have considered the change proposed and hereby agree,if this proposal is
Auditor approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
RMO YARD AREA 8 CHANGE ORDER NO. 01
FENCE RECONSTRUCTION APRIL18, 2023
CONTRACT NO. 22-21-C PAGE 2 OF 2
NET COST THIS CHANGE ORDER: $1,761.00 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
.P�6utyS�escGuc,�.eey
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
YUKON FENCE COMPANY, INC.
Contractor Mandeep S. Sekhon, PE
TOttitttit� slwl�lOhJ Construction Engineer
By Tommy Simi ions(Apr 18,2023 10:59 PDT)
APPROVED BY:
Project Manager }p p White
+p Digitally signed by Steve White
Title Steve ite Date:2023.04.1914:05:33
-07'00'
Apr 18 2023 Steven E. White, Director
Accepted Date: Public Works and Planning
Date:
Contractor We the above signed contractor,have considered the change proposed and hereby agree,if this proposal is
Auditor approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business Office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.