COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AUBERRY ROAD/COPPER AVENUE CHANGE ORDER NO. 05
TRAFFIC SIGNAL INSTALLATION JANUARY 10, 2023
FEDERAL PROJECT NUMBER: HSIPL-5942(241) PAGE 1 OF 5
CONTRACT NO. 19-08-C
TO: AVISON CONSTRUCTION, INC.:
Make the following change(s)to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0)-WORKING DAYS will be added to the contract time. The
revised completion date was October 14,2022.
PART I: INCREASE/DECREASE ITEMS AT UNIT BID PRICES
This change was proposed by the engineer.
Quantities in the Bid Book are estimates only.This part adjusts items to the actual quantities used.
Increased Items:
Item Total
No. Description Unit Quantity Price Amount
23 Remove Roadside Sign EA 4.00 $30.00 $120.00 200.00
25 Install Roadside Sign—One Post EA 1.00 425.00 425.00 9.09
TOTAL INCREASE: $545.00
Decreased Items:
Item Total
No. Description Unit Quantity Unit Price Amount
24 Remove Roadside Sign (Metal Post) EA 1.00 $55.00 $55.00 16.67
42 Paint Pavement Marking SF 3.00 11,00 33.00 37.50
(Retroreflective) Bike Loop Symbol
(2-Coat)
TOTAL DECREASE: $88.00
This change did not impact the critical path for the project,therefore, granting additional contract time was not
warranted.
TOTAL COST PART I: A$457.00 INCREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
_Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
_Auditor this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business orrice noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AUBERRY ROAD/COPPER AVENUE CHANGE ORDER NO. 05
TRAFFIC SIGNAL INSTALLATION JANUARY 10, 2023
FEDERAL PROJECT NUMBER: HSIPL-5942(241) PAGE 2 OF 5
CONTRACT NO. 19-08-C
PART 11: INSTALL STEEL BOLLARDS AT THE EQUIPMENT PAD—EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work,"of the Standard Specifications, install a total of
three (3)4-inch steel bollards on the traffic-side of the equipment pad at the north-west corner, as shown on
the drawing. Install bollards in a 12-inch diameter and 30-inch-deep concrete footing, with a 6-inch concrete
cover at the bottom of the bollards. Utilize minor concrete conforming to the requirements of Section 90-2,
"Minor Concrete,"of the Standard Specifications. Compensation for this work will be made at force account on
time and materials basis, as per Section 9-1.03, "Payment Scope,"of the Special Provisions. Payment for this
work was calculated according to Section 9-1.04, "Force Account," of the Standard Specifications, resulted in
$4,028.51.
This extra work was performed during the contract suspension,therefore, granting additional contract time
was not warranted.
TOTAL COST PART 11: A $4,028.51 INCREASE
TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS
PART III: INSTALL TRAFFIC SENSOR LOOPS PER THE REVISED STRIPING PLAN—EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, install a total of
eight traffic sensor loops (five Type E and three Type D)for the southbound Auberry Road and eastbound
Copper Avenue per the attached revised striping plan. Perform all work according to Section 23,"Traffic
Signals and Street Lighting,"of the City of Fresno Standards (included in the Project Details, in Project
Specifications). Payment for this work will be made as extra work at an agreed lump sum price of$9,889.33
according to Section 9-1.03, "Payment Scope,"of the Special Provisions.This price includes compensation of
all labor, materials, equipment, overhead costs, markups, and incidentals for performing the work.
This extra work was performed during the contract suspension, therefore, granting additional contract time
was not warranted.
TOTAL COST PART III: A $9,889.33 INCREASE
TOTAL TIME EXTENSION PART III: ZERO (0) -WORKING DAYS
PART IV: SPLICE NEW TRAFFIC SENSOR LOOPS— EXTRA WORK
This change was requested by the engineer.
_Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
_Auditor this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
_RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AUBERRY ROAD/COPPER AVENUE CHANGE ORDER NO.05
TRAFFIC SIGNAL INSTALLATION JANUARY 10, 2023
FEDERAL PROJECT NUMBER: HSIPL-5942(241) PAGE 3 OF 5
CONTRACT NO. 19-08-C
In accordance with Section 4-1.05, "Changes and Extra Work,"of the Standard Specifications, splice a total of
eight newly installed traffic sensor loops for the southbound Auberry Road and eastbound Copper Avenue per
the attached revised striping plan. Perform all work according to Section 23, "Traffic Signals and Street
Lighting,"of the City of Fresno Standards(included in the Project Details, in Project Specifications).
Compensation for this work will be made at force account on time and materials basis,as per Section 9-1.03,
"Payment Scope,"of the Special Provisions. Payment for this work was calculated according to Section 9-1.04,
"Force Account,"of the Standard Specifications, resulted in $1,105.19.
This extra work was performed during the contract suspension, therefore, granting additional contract time
was not warranted.
TOTAL COST PART IV: A$1,105.19 INCREASE
TOTAL TIME EXTENSION PART IV: ZERO (0)-WORKING DAYS
PART V: EXTEND MIDWEST GUARDRAIL SYSTEM ALONG COPPER AVENUE—EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work,"of the Standard Specifications, extend the
Midwest Guardrail System by 25 feet along southside of Copper Avenue between sta. 19+70.86 and 19+95.86.
Perform all work according to Section 83-2.02, "Midwest Guardrail Systems,"of the Standard Specifications.
Payment for this work will be made as extra work at an agreed lump sum price of$6,431.65 according to
Section 9-1.03, 'Payment Scope,"of the Special Provisions.This price includes compensation of all labor,
materials, equipment, overhead costs, markups, and incidentals for performing the work.
This extra work was performed during the contract suspension, therefore, granting additional contract time
was not warranted.
TOTAL COST PART V: A $6,431.65 INCREASE
TOTAL TIME EXTENSION PART V: ZERO (0)-WORKING DAYS
PART VI: REMOVE TEMPORARY STRIPING PER THE REVISED STRIPING PLAN—EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work,"of the Standard Specifications, remove
temporary striping per the revised striping plans (attached). Perform all work according to Section 84-9,
"Existing Markings,"of the Standard Specifications. Payment for this work will be made as extra work at an
agreed lump sum price of$3,449.60 according to Section 9-1.03, "Payment Scope,"of the Special Provisions.
This price includes compensation of all labor, materials, equipment, overhead costs, markups, and incidentals
_Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,IF
_Auditor this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_const.Management therefore the prices shown above.
_RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention Is directed to the requirements of the
specifications as to proceeding with the ordered work and riling a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AUBERRY ROAD/COPPER AVENUE CHANGE ORDER NO.05
TRAFFIC SIGNAL INSTALLATION JANUARY 10, 2023
FEDERAL PROJECT NUMBER: HSIPL-5942(241) PAGE 4 OF 5
CONTRACT NO. 19-08-C
for performing the work.
This extra work was performed during the contract suspension,therefore, granting additional contract time
was not warranted.
TOTAL COST PART VI: A $3,449.60 INCREASE
TOTAL TIME EXTENSION PART VI: ZERO (0)-WORKING DAYS
PART VII: INSTALL ADDITIONAL TEMPORARY TRAFFIC CONTROL DEVICES FOR THE SIGNAL TURN-
ON—EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work,"of the Standard Specifications, furnish and
install a total of three (3) portable changeable message signs (PCMS), two(2)"STOP AHEAD"signs,and two
(2) "STOP"signs at the locations determined by the Resident Engineer_The temporary roadside signs are to
be installed on Type III Barricades. These signs and the PCMSs are to be displayed for two weeks and
removed when the newly installed traffic signal is fully functional. Perform all work according to Section 12,
"Temporary Traffic Control,"of the Project Special Provisions and Standard Specifications. Payment for this
work will be made as extra work at an agreed lump sum price of$4,553.12 according to Section 9-1.03,
"Payment Scope,"of the Special Provisions.This price includes compensation of all labor, materials,
equipment, overhead costs, markups, and incidentals for performing the work.
This extra work was performed during the contract suspension, therefore, granting additional contract time
was not warranted.
TOTAL COST PART VII: A $4,553.12 INCREASE
TOTAL TIME EXTENSION PART VII: ZERO (0)-WORKING DAYS
Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
_Auditor this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of supervisors therefore the rites shown above.
_Const.Management p
_RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AUBERRY ROAD/COPPER AVENUE CHANGE ORDER NO.05
TRAFFIC SIGNAL INSTALLATION JANUARY 10,2023
FEDERAL PROJECT NUMBER: HSIPL-5942(241) PAGE 5 OF 5
CONTRACT NO. 19-08-C
NET COST THIS CHANGE ORDER: A$29,914.40 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0)-WORKING DAYS
--,IQLA r'
L1Ru_Guo>s^u Uan 11.2023 03:02115TI
LaRue Goossen, Resident Engineer
APPROVAL RECOMMENDED:
AVISON CONTRUCTION, INC.
J'('0 ,%S.C' �ti_
Contractor Mandeep S. Sekhon, PE
Construction Engineer
_fie R_91 a r
By APPROVED BY:
Steve �� le Da eelly
Title Project Manager Steve signed by Steve While
-0g0 20Z3.01.1808:39:56
Steven E.White, Director
Accepted Date:
Jan 12 2023 Public Works and Planning
Date:
S�i Quintero, Chairman
Boa4of Supervisors
Date: 12
ATTEST:
BERNICE E.SEIDEL
Clerk of the Board of Supervisors
County of Fresno,State of California
By— Deputy
_Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,If
Auditor this proposal Is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board a/Supervisors therefore the prices shown above.
_Const,management
_RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention Is directed to the requirements of the
spedfications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
ACCOUNTING: 45104514 FUND: 0010 SUBCLASS: 11000 ACCOUNT: 7370 PRJ: G13544 ACTIVITY:4750
LETTER OF TRANSMITTAL - C.C.O. NO. 5 JANUARY 10, 2023
TO: SAL QUINTERO, CHAIRMAN AUBERRY ROAD/COPPER AVENUE
BOARD OF SUPERVISORS TRAFFIC SIGNAL INSTALLATION
FEDERAL PROJECT NUMBER: HSIPL-5942(241)
STEVEN E. WHITE, DIRECTOR CONTRACT NO. 19-08-C
PUBLIC WORKS AND PLANNING
ATTN: MANDEEP S. SEHKON
CONSTRUCTION ENGINEER
FROM: -ie Goossen(Jan 11,2023 08:01 PST)
LaRue Goossen, Resident Engineer
STATUS OF FUNDS:
Contract Items $ 786,169.00 Original Allotment $ 837,977.45
Dept. Furnished Materials $ 0.00 Supplemental Allotment $ 79,968.38
Previous CCO's $ 131,775.53 Total Allotment $ 917,945.83
This CCO #5 $ 29,914.40 Obligated Funds $ 947,858.93
Total Obligated Funds $ 947,858.93 Unobligated Balance $ -29,913.10
DIRECTOR'S LIMIT to sign change orders is: 51,808.45
PART I - DESCRIPTION:
Increase/decrease items at unit prices.
WHY:
The item quantities in the Bid Book are estimates only. This reflects the actual quantities used for
construction.
Bid Item No. 23 — Remove Roadside Sign increased by 200 percent, reflects the actual used
quantity in the field. Payment for the increased quantity in excess of 125 percent of the
estimated quantity resulted in an amount of$30. Since the payment for the quantity in excess of
125 percent resulted in less than $5,000, no adjustment to the unit price was made as per
Section 9-1.06, "Changed Quantity Payment Adjustments," of the Standard Specifications; and
the increased quantity was paid at the unit price, resulting in an increase of$120.
Bid Item No. 42 — Paint Pavement Marking (Retroreflective) Bike Loop Symbol (2-Coat)
decreased by 37.75 percent, reflects the actual used quantity in the field. The contractor did
not request a pay adjustment for the quantity decreased more than 25 percent, as referenced
in Section 9-1.06C "Decreases of More Than 25 percent," of the Standard Specifications.
This bid item was decreased by 37.75 percent, resulting in a $33.00 decrease.
All other changes in the bid item quantities are minor and within the normal deviations for this type of
construction.
HOW:
Item quantities were increased or decreased at unit prices per Section 9-1.06, "Changed
LETTER OF TRANSMITTAL - C.C.O. NO. 5 JANUARY 10, 2023
Quantity Payment Adjustments," of the Standard Specifications, resulting in an increase of
$457.00.
COST:
A $457.00 Increase
PART II - DESCRIPTION:
Install steel bollards at the equipment pad —extra work.
WHY:
The PG&E requested installing three (3) 4-inch steel bollards on the traffic-side of the signal
equipment pad. This work was not included in the project; therefore, it was necessary to perform this
work as extra work.
HOW:
The contractor was directed to perform this extra work according to Section 4-1.05, "Changes
and Extra Work," of the Standard Specifications. Compensation for this work will be made at
force account on time and materials basis, per Section 9-1.03, "Payment Scope," of the Special
Provisions. The County staff kept track of labor, equipment, and materials used for this work
and calculated compensation according to Section 9-1.04, "Force Account," of the Standard
Specifications. The total compensation for this work resulted in $4,028.51.
COST:
A $4,028.51 Increase
PART III - DESCRIPTION:
Install traffic sensor loops per the revised striping plan — extra work
WHY:
The original striping plan was revised to accommodate truck turns through the intersection. The
contractor had already installed the traffic sensor loops and the temporary striping per the original
striping plan. The revised striping plan required re-installing a total of eight (8) traffic sensor loops at
the new locations on southbound Auberry Road and eastbound Copper Avenue; this was
considered extra work.
HOW:
The contractor was directed to perform this extra work according to Section 4-1.05, "Changes and
Extra Work," of the Standard Specifications. Compensation for this work will be made at an agreed
lump sum price of$9,889.33 according to Section 9-1.03, "Payment Scope," of the Special
Provisions.
COST:
A $9,889.33 Increase
PART IV - DESCRIPTION:
LETTER OF TRANSMITTAL - C.C.O. NO. 5 JANUARY 10, 2023
Splice new traffic sensor loops —extra work.
WHY:
The new traffic senor loops installed as extra work, included in Part III of this contract change order,
required splicing into the traffic signal components, this work was also considered as extra work.
HOW:
The contractor was directed to perform this extra work according to Section 4-1.05, "Changes
and Extra Work," of the Standard Specifications. Compensation for this work will be made at
force account on time and materials basis, per Section 9-1.03, "Payment Scope," of the Special
Provisions. The County staff kept track of labor, equipment, and materials used for this work
and calculated compensation according to Section 9-1.04, "Force Account," of the Standard
Specifications. The total compensation for this work resulted in $1,105.19.
COST:
A $1,105.19 Increase
PART V - DESCRIPTION:
Extend Midwest Guardrail System along Copper Avenue— extra work.
WHY:
The County staff decided to extend the Midwest Guardrail System along Copper Avenue by 25-feet,
between sta. 19+70.86 and 19+95.86 to protect a traffic signal pole and to enhance public safety.
This work was not included in the project; therefore, it was necessary to perform this work as extra
work.
HOW:
The contractor was directed to perform this extra work according to Section 4-1.05, "Changes and
Extra Work," of the Standard Specifications. Compensation for this work will be made at an agreed
lump sum price of$6,431.65 according to Section 9-1.03, "Payment Scope," of the Special
Provisions.
COST:
A $6,431.65 Increase
PART VI - DESCRIPTION:
Remove temporary striping per the revised striping plan —extra work.
WHY:
The contractor had painted the temporary traffic striping per the original striping plan. As the striping
plan was revised to accommodate truck turns through the intersection, it required removal of the
temporary striping as extra work.
LETTER OF TRANSMITTAL - C.C.O. NO. 5 JANUARY 10, 2023
HOW:
The contractor was directed to perform this extra work according to Section 4-1.05, "Changes and
Extra Work," of the Standard Specifications. Compensation for this work will be made at an agreed
lump sum price of$3,449.60 according to Section 9-1.03, "Payment Scope," of the Special
Provisions.
COST:
A $3,449.60 Increase
PART VII- DESCRIPTION:
Install additional temporary traffic control devices for the signal turn-on —extra work.
WHY:
This project changed the intersection control from a one-way stop operation to a fully signalized
operation. In order to safely transition from a one-way stop to a full signalized control, the County
staff directed the contractor to install a total of three (3) portable changeable message signs
(PCMS), two (2) "STOP AHEAD" signs, and two (2) "STOP" signs for two weeks while the signal
was put on flash-red mode. Placement of these temporary traffic control devices was considered as
extra work.
HOW:
The contractor was directed to perform this extra work according to Section 4-1.05, "Changes and
Extra Work," of the Standard Specifications. Compensation for this work will be made at an agreed
lump sum price of$4,553.12 according to Section 9-1.03, "Payment Scope," of the Special
Provisions.
COST:
A $4,553.12 Increase
NET COST THIS CHANGE ORDER: A $29,914.40 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS