PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 1/4/2023
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#045.6
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Adjusted Change Order Allowance(as awarded on 01/03/23) $795,515.00�
Change Order Allowance: $568,225.001
Director's Change Order Limit: $216,000.001
Contract Time(Calendar Days): 1 322
Construction Start Date: 1 11/09/20
Original Construction Completion Date: 9126121
_Change Order Scope of Work:
Extra work at force account-ASI 01-18-2022-01
Attachments:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $7,640.71
Net Additive Calendar Days:
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: 0
Total Change Order Dollar Amount To Date $430,521.97
Adjusted Contract Dollar Amount: $11,795,021.971
Total Adjusted Calendar Days To Date: 80
Director's Change Order Limit Balance: $220,521.97
Adjusted Construction Completion Date: 12/16/21
Reviewed: Roger Davidson �da� h11121 sr,
Architect
KeiEly Eck2rE
Reviewed: Keith M. Eckert 11 s„,,,,, ,
Project Manager
Reviewed: Mandeep S. Sekhon
Construction Manager
Reviewed: William M. Kettler
Division Manager
Approved: Steven E. White
Director
Approved: Sal Quintero
Board oCupe
i rs CI irman
Approve 01/13/2023
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriff's Office Thomas Trester
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
F� Co County of Fresno
+ �y Department of Public Works and Planning
Q� Development Services&Capital Projects Division
Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 1/4/2023
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#045.6
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#045.6 is hereby approved by the County.
Change Order Scope of Work:
Extra work at force account-ASI 01-18-2022-01
Attachment:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $7,640.71
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: $430,521.97
Adjusted Contract Dollar Amount: $11,795,021.97
Total Adjusted Calendar Days To Date: 80
Adjusted Construction Completion Date: 12/15/21
Keith M.Eckert ll Keit Eck�4,2023 14:45 PST)
Project Manager
Date: Jan 4,2023
By signing acceptance of this Change Order,the Contractor shall agree to the following.
1.Provide all equipment material.labor and services required to complete the Scope of Work specified in
this Change Order
2 The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article V1 shall apply.
�D�y
Accepted By., Klassen Corporation Rod Paine(Jan 4,202316:45 PST)
Authorized Signature
Date: Jan 4,2023
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,StaffAna/yst
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721