HomeMy WebLinkAboutCCO 083.1 signed.pdf Co County of Fresno
C Department of Public Works and Planning
O� s O Development Services&Capital Projects Division
FRES� Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 11/1/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#083.1
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,226.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Switchgear not per submittal
-The conduits feeding the transformer TDB-L are now outside the switchgear and need to be re-routed into SBL
Switchgear
Provide and install new 36x36xl8 nemal can,all new connectors between new neural can and SBL
Additional wire is needed to make the connections in SBL
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $5,645.78
Net Additive Calendar Days: �p
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �p
Total Change Order Dollar Amount To Date $422,881.26
Adjusted Contract Dollar Amount: $11,787,381.26
Total Adjusted Calendar Days To Date: 80
Director's Change Order Limit Balance: -$212,881.26
Adjusted Construction Completion Date: 12/15/21
Reviewed: Roger Davidson � Y%kfoN
Architect
Reviewed: Keith M.Eckert 11 °`�r
rc.en M.ea.rt i�3.mzz,ona ron
Project Manager
Reviewed: Mandeep S. Sekhon
Construction Manager
Reviewed: William M. Kettler
Division Manager
Approved. Steven E. White SfG✓en E whif-e
�.Ewn,v�wo.3.:ou
Director
Approved: Brian Pacheco %I
Boqfd cl upery ors Chairman
Approval Date: 01/12/2023
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriff's Office Thomas Trester
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
c°U County of Fresno
L Department of Public Works and Planning
p� y6 p Development Services&Capital Projects Division
FRES Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 11/1/2022
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#083.1
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,600.00
Original Construction Completion Date: 09/26/21
CCO#083.1 is hereby approved by the County.
Change Order Scope of Work:
Switchgear not per submittal
-The conduits feeding the transformer TDB-L are now outside the switchgear and need to be re-routed into SBL
Switchgear
-Provide and install new 36x36xl8 nemal can,all new connectors between new nemal can and SBL
-Additional wire is needed to make the connections in SBL
Attachment:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $5,645.78
Net Additive Calendar Days:
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days:
Total Change Order Dollar Amount To Date: $422,881.26
Adjusted Contract Dollar Amount: $11,787,381.26
Total Adjusted Calendar Days To Date: 80
Adjusted Construction Completion Date: 12/16/21
�ertGr til. ���re�t
Keith M.Eckert II Keith M.Eckert(Nov 2,202211:22 PDT)
Project Manager
Date: Nov 2,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following.
1 Provide all equipment,matenal,labor and services required to complete the Scope of Work specified in
this Change Order
2. The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply
RW Paa4e-
Accepted By: Klassen Corporation Rod Paine(Nov 2,202213:32 PDT)
Authorized Signature
Date: Nov 2,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721