HomeMy WebLinkAboutCCO 080 - signed.pdf co`'� County of Fresno
Department of Public Works and Planning
Development Services&Capital Projects Division
FR85� Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 10/18/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#080
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225 0-0
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: F 11/09/20
Original Construction Completion Date: 9/26121
Change Order Scope of Work:
Electrical alterations per ASI-07-19-2022-01 at storage area.
Attachment(s):
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $13,088.21
Net Additive Calendar Days:
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days:
Total Change Order Dollar Amount To Date $414,742.20
Adjusted Contract Dollar Amount: $11,779,242.20
Total Adjusted Calendar Days To Date: 80
Director's Change Order Limit Balance: -$204,742.20
Adjusted Construction Completion Date: 12/15/21
Reviewed: Roger Davidson
..d:o miza.zou uao Pon
Architect
Reviewed: LaRue Goossen —ALA.—
Reviewed: Mandeep S. Sekhon f ky S.Su�
Construction Manager
Reviewed: William M. Kettler
Division Manager
Approved: Steven E. White s``yoo,E wh4iv
cwna.�xa,c.zozz is:si ron
Director
Approved: Brian Pacheco
Boa of u rvis Chairman
App Dat . 01/12/2023
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriffs Office Thomas Trester
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
c°�, County of Fresno
19— Department of Public Works and Planning
p� 56 p Development Services&Capital Projects Division
Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 10/18/2022
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#080
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500,00
Original Construction Completion Date: 09/26/21
CCO#080 is hereby approved by the County.
Change Order Scope of Work:
Electrical alterations per ASI-07-19-2022-01 at storage area.
Attachment:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $13,088.21
Net Additive Calendar Days: �p
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �p
Total Change Order Dollar Amount To Date: $414,742.20
Adjusted Contract Dollar Amount: $11,779,242.20
Total Adjusted Calendar Days To Date: gp
Adjusted Construction Completion Date: 12/15/21
LaRue Goossen IaRueGoossen(Oct19,202212:09 PDT)
Project Manager Signature
Date: Oct 19,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following
1 Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order
2 The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply
,Fog'�ai�re
Accepted By: Klassen Corporation Rod Paine(oct O,202208:25 PDT)
Authorized Signature
Date: Oct 20,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Ueda Guerra,Staff Analyst
L'
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721