PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 911212022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#076.2
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9126/21
Change Order Scope of Work:
Extra work at force account for August-11 additional conduits/ATS conduits
Attachment(s):
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $8,149.07
Net Additive Calendar Days: p�
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: p�
Total Change Order Dollar Amount To Date $398,093.26
Adjusted Contract Dollar Amount: $11,762,593.26
Total Adjusted Calendar Days To Date: g0
Director's Change Order Limit Balance: -$188,093.26
Adjusted Construction Completion Date: 12/15/21
Reviewed: Roger Davidson � lahz15 22 PDT)Architect
Reviewed: LaRue Goossen C. nager;
Project Ma o
Reviewed: Mandeep S.Sekhon � S
Construction Manager
Reviewed: William M.Kettler
Division Manager
Approved: Steven E. White s C-Wkife-
Dir or OkL
Approved: Brian Pacheco
Board of Supervisors Chairman a
Approval Date:
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriffs Office Thomas Trester
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
h CO° County of Fresno
�6 Department of Public Works and Planning
O ! O Development Services&Capital Projects Division
E6} Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 9/12/2022
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#076.2
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500,00
Original Construction Completion Date: 09/26/21
CCO#76.2 is hereby approved by the County.
Change Order Scope of Work:
Extra work at force account for August-11 additional conduits/ATS conduits
Attachment:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $8,149.07
Net Additive Calendar Days: p�
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: p�
Total Change Order Dollar Amount To Date: $398,093.26
Adjusted Contract Dollar Amount: $11,762,593.26
Total Adjusted Calendar Days To Date: gp
Adjusted Construction Completion Date: �Q. ^ 12/15/21
LaRue Goossen La Rue Goossen(Sep 12,2022 11:35 PDT)
Project Manager Signature
Date: Sep 12,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
Accepted By: Klassen Corporation Rod Paine(Sep 12,2022 11:51 PDT)
Authorized Signature
Date: Sep 12,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
< PCCO #076.2
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #076.2: Extra Work at Force Account
August - 11 Additional Conduits/ATS Conduits
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED 9/08/2022 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Approved REVISION:
'RANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $8,149.07
DESCRIPTION:
ATTACHMENTS:
CO#024 ASI 07-22-2022-01 Relocated Curb and ATS Cond pdf C04023 ATS Conduit Relocation pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
76.2 1 11 Additional Conduits/ATS Conduits 8,149.07
TOTAL: $8,149.07
CHANGE ORDER LINE ITEMS:
PCO#76.2:11 Additional Conduits/ATS Conduits
# Cost Code Description Type Amount
1 16-100-Electrical PCCO#076.2-Forced Work Labor August-11 Additional Conduits/ATS
Subcontractor $7,250.06
Conduits
Subtotal: $7,250.06
Fee:10.00%Applies to all line item types. 725.01
Insurance:1.40%Applies to all line item types. 101.50
Bond:1.00%Applies to all line item types. 72.50
Grand Total: $8,149.07
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 559,469.67
The contract sum prior to this PCCO was $ 11,923,969.67
The contract sum will be increased by this PCCO in the amount of $ 8,149.07
The new contract sum including this PCCO will be $ 11,932,118.74
The contract time will not be changed by this PCCO
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On:9/8/2022 03:58 PM