PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 9/12/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#045.5
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9126/21
Change Order Scope of Work:
Extra work at force account for August-ASI-01-18-2022-01
Attachment(s):
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $6,737.03
Net Additive Calendar Days: p�
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: p�
Total Change Order Dollar Amount To Date �— $389,944.19
Adjusted Contract Dollar Amount: $11,754,444.19
Total Adjusted Calendar Days To Date: 80
Director's Change Order Limit Balance: -$179,944.19
Adjusted Construction Completion Date: 12/15/21
PR�Q�%RJOH
Reviewed: Roger Davidson ,aavldson(Sep II.30II 35:23 PDT)
Architect
Reviewed: LaRue Goossen
Prooilect Manager
Reviewed: Mandeep S. Sekhon
Construction Manager
Reviewed: William M.Kettler
Division Manager
sio")1 E wh4"o-
Approved: Steven E. White
Dire
�or 4L
Approved: Brian Pacheco Ii1...
Board of Supervisors Chairman
Approval Date:
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriffs Office Thomas Trester
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
COGS County of Fresno
Department of Public Works and Planning
Q y 0 Development Services&Capital Projects Division
FR'E�a� Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 9/12/2022
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#045.5
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#045.5 is hereby approved by the County.
Change Order Scope of Work:
Extra work at force account for August-ASI-01-18-2022-01
Attachment:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $6,737.03
Net Additive Calendar Days: p�
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: p�
Total Change Order Dollar Amount To Date: $389,944.19
Adjusted Contract Dollar Amount: $11,754,444.19
Total Adjusted Calendar Days To Date: g0
Adjusted Construction Completion Date: 12/15/21
AAA.
LaRue Goossen LaRue Goossen(Sep 12,2022 11:30 PDT)
Project Manager Signature
Date: Sep 12,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
DOGt�911�le
Accepted By: Klassen Corporation Rod Paine(Sep 12,202211:47 PDT)
Authorized Signature
Date: Sep 12, 2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
PCCO #45.5
K lessen
carporaGior
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #45.5: Extra Work at Force Account for
August - ASI 01-18-2022-01
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 9/08/2022 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Approved REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $6,737.03
DESCRIPTION:
CE#062-Extra Work at Force Account-ASI 01-18-2022-01
Extra Work at Force Account-ASI 01-18-2022-01
ATTACHMENTS:
Forced Work August 2022 PCCO#45pdf Force Work Labor-Equipment August PCCO#45.xls
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
45.5 1 Extra Work at Force Account for August-ASI 01-18-2022-01 6,737.03
TOTAL: $6,737.03
CHANGE ORDER LINE ITEMS:
PCO#45.5:Extra Work at Force Account for August-ASI 01-18-2022-01
# I Cost Code Description Type Amount
1 16-100-Electrical PCCO 45.5-Forced Work for August Subcontractor $5,993.80
Subtotal: $5,993.80
Fee:10.00%Applies to all line item types. 599.38
Insurance:1.40%Applies to all line item types. 83.91
Bond:1.00%Applies to all line item types. 59.94
Grand Total: $6,737.03
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 552,732.64
The contract sum prior to this PCCO was $ 11,917,232.64
The contract sum will be increased by this PCCO in the amount of $ 6,737.03
The new contract sum including this PCCO will be $ 11,923,969.67
The contract time will not be changed by this PCCO