HomeMy WebLinkAboutECC - CCO 006 - Signed.pdf Co County of Fresno
1 Department of Public Works and Planning
0 1 6 0 Development Services&Capital Projects Division
ARE`' Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Environmental Compliance Center
Contract No.: 20-S-01
Date: 10/6/2022
Contractor: BMY Construction Group, Inc.
Architect: Tiana Perez
Change Order No.: CCO#6
Construction Contract Dollar Amount as awarded on 7/13/2021 $2,660,000.00
Director's Change Order Limit: $145,500.00
Contract Time(Calendar Days): 200
Construction Start Date: 09/13/21
Original Construction Completion Date: 3/31/22
Change Order Scope of Work:
PCO#9-Flooring change PH2-ASI#03
PCO#14.1-Emergency eyewash station cost increase
PC0#16-Time extension due to MSB delays
PC0#17-Time&material for retaining wall at transformer pad
PCO#18-Tie into existing fire line
Attachment(s):
CO Summary,CO Proposal,PCO estimate
Net Additive Change Order Dollar Amount: $32,383.14
Net Additive Calendar Days: 91
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: 00
Total Change Order Dollar Amount To Date $54,205.49
Adjusted Contract Dollar Amount: $2,714,205.49
Total Adjusted Calendar Days To Date: 129
Director's Change Order Limit Balance: $91,294.51
Adjusted Construction Completion Date: 08/07/22
T-,w,q�2rrna.
Reviewed: Tiana Perez Tent P—,colt 26,2022 1101 PUT)
Architect
Ka M.E,arf
Reviewed: Keith Eckert K<„n M E<1(-26,2 22 104 Por,
'�Pr9jeect Manager
Reviewed: Mandeep S. Sekhon
Construction Manager
Reviewed: Will M.Kettler 111�-)A&'
Division Manager
Sfe✓en E Whife
Reviewed: Steven E. White Steven E Whlte(Olt 26,202215.20 PDT)
Director
Approved. Brian Pacheco Not Applicable
Board of Supervisors Chairman
Director Approval Date: Oct 26, 2022
Scan and forward Director Approved Copy to: CAO Paul Nerland
Resources Craig Nickel
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
coU County of Fresno
i' Department of Public Works and Planning
Development Services&Capital Projects Division
FRES Steven E.White,Director
COUNTY CHANGE ORDER REQUEST
Project: Environmental Compliance Center
Contract No.: 20S-01
Date: 10/6/2022
Contractor: BMY Construction Group,Inc.
5485 E.Olive Ave.
Fresno,California 93727
(569)243-4200
Change Order No.: CCO#6
Construction Contract Dollar Amount as awarded on 7/13/2021 $2,660,000.00
Original Construction Completion Date: 03131/22
CCO#6 is hereby approved by the County.
Scope of Work:
PCO#9-Flooring change PH2-ASI#03
PCO#14.1-Emergency eyewash station cost increase
PCO#16-Time extension due to MSB delays
PCO#17-Time&material for retaining wall at transformer pad
PCO#18-Tie into existing fire line
Attachment:
CO Summary,CO Proposal,PCO estimate
Net Additive Change Order Dollar Amount: $32,383.14
Net Additive Calendar Days: g1
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: row
Total Change Order Dollar Amount To Date: $54,205.49
Adjusted Contract Dollar Amount: $2,714,205.49
Total Adjusted Calendar Days To Date: 129
Adjusted Construction Completion Date: 08/07/22
Keith Eckert Keith M.Eckert 11(Oct 13,202210:41 PDT)
Project Manager
Date: Oct 13,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adiusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 20-S-01
Article VI shag apply.
Accepted By., BMY Construction Group,Inc.
Authorized Signature E4�
at
Date: �V T;•2X
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project: Environmental Compliance Center
D. 1VW Days Description
Change Orders
1 11/9/2021 $0.00 -$14,820.00 0 Includes PCO#1
2 1/6/2022 $36,635.08 $0.00 0 Includes PCO#3,4.1
3 3/21/2022 $22,784.56 $0.00 4 Includes PCO#2
4 5/2/2022 $2,811.62 -$30,720.00 27 Includes PCO#5.1,6.2,8,and 11
5 6/24/2022 $5,131.09 $0.00 7 Includes PCO#10.1, 13
6 10/6/2022 $32,383.14 $0.00 91 Includes PCO#9, 14.1, 16, 17, 18
Totals $99,745.49 1 -$45,540.00 129
Proposed
• • A.. Credit Rejected Pending � .
Change Orders
1 1 -$14,820.00 0 Omit 8'sidewalk on the north side of site
2 3 $22,784.56 4 Add fire system at PH1 -Shade Structure
3 2 $830.28 0 Storefront finish alteration
4 $37,711.89 0 Revised Fire Line per C4.0
4.1 2 $35,804.80 0 Revised Fire Line per C4.0-Alterations to site utility plan
5 $0.00 3.5 Rain Delays
5.1 4 $0.00 4 Rain Delays
6 -$28,000.00 0 Tire bark credit
6.1 Not used
6.2 4 -$30,720.00 0 Tire bark and labor credit
7 Not used
8 4 $0.00 23 Time extension for Metal Building Supply issues
9 6 $2,618.36 0 Flooring change PH2-ASI#3
9.1 $2,618.36 0 Flooring change PH2-ASI#3
10 $14,141.00 7 Refabricate Risers at Building 1 &2
10.1 5 $3,596.93 7 Refabricate Risers at Building 1 &2
11 4 $2,811.62 0 Frame Parapet PH2&Pony Walls PH3
12 $13,490.00 10 Time extension for Submittal#34
13 5 $1,534.16 0 Rebar add,credit move strip&PH1 footing sizes
14 $4,819.08 0 Emergency eyewash station cost increase
14.1 6 $2,158.00 0 Emergency eyewash station cost increase
15 Not used
16 6 $0.00 91 Time extension-MSB delays
17 6 $20,645.00 0 T&M for retaining wall at transformer pad
18 6 $6,961.78 0 Tie into existing Fire line
19 $63,029.00 0 HHS&purlin changes at shade structure
20 $51,103.42 0 Street light plan changes from bid to approved set
21 Not used
Totals $99,745.49 -$45,540.00 $107,809.33 $51,103.42
r
�.w
CONSTRUCTION
GROUP INCORPORATED
April 7, 2022
County of Fresno
Construction Division
A ttn: Keith Eckert
2220 Tulare Street,7th Floor
Fresno, CA 93721
Re: Environmental Compliance Center
BMY JOB NO. 21008
Subject: PCO#9— Flooring Change PH2—ASI#3
Mr. Eckert,
BMY Construction Group, Inc, (BMY) is providing the following PCO for the costs and time associated with the
changes made to Building 2 bathrooms. Per ASI#3 added a 4"cove out of viny sheet flooring with a cap.
BMY is requesting the County to issue a Change Order adding $2,618,36 to the contract price. In order to
perform the work BMY is requiring a time extension of 0 calendar days.
This PCO is valid for 30 days. Due to unprecedent times in our industry, with volatile material pricing and
delivery, it is of the utmost importance that this PCO be processed quickly. Our industry is currently having
supply issues. The cost of material is on a consistent rise and it is not as readily available, with lead times getting
longer. This may directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down and get material and
products. At this time we need your assistance with timely approvals so we can minimize project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further information,
please do not hesitate to contact me.
Respectfully,
Dylan Medeiros
Project Engineer
Page 1 of 1
5485 East Olive Avenue - Fresno, CA 93727 - Phone (559) 2434200 - Fax (559) 222-2380
Lic No. 686178
1 ~1 J�J to PCO #009
CONSTRUCTION
GROUP INCORPORATED
BMY Construction Group Incorporated Project:210D8-Environmental Compliance Center-Contract#20-S-01
5485 East Olive Avenue 310 S.West Ave
Fresno,California 93727-2541 Fresno, California 937D6
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #009: CE #014 - Flooring Change -
PH2 - ASI #3
TO: The County of Fresno,Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E. Olive Ave
2220 Tulare Street,8th Floor Fresno.California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 009/0 CONTRACT: 21008-Environmental Compliance
Center-Contract#20-S-01 Prime
Contract
REQUEST RECEIVED FROM: Keith Eckert(The County of Fresno, CREATED 8Y: Dylan Medeiros(BMY Construction
Department of Public Works and Pie) Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 4/7/2022
._.. _. .. __ ._,_ ._._ _ _. .._ ._.,.....v. .. .........._.
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount based
SCHEDULE IMPACT: PAID IN FULL. No
EXECUTED: Na SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $2,618.36
POTENTIAL CHANGE ORDER TITLE:CE#014-Flooring Change-PH2-ASI 93
CHANGE REASON: Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract is Changed As Follows)
CE#014-Flooring Chan e-PH2-ASI#3
County supplied ASI No.03.to add a 4"cove base in rooms 102 and 103 in Building 2.
ATTACHMENTS:
PCO#9-_Prop al.pdf
# I Budget Code Description Amount
1 09-6513.S Base and Flooring/DFS.Subcontract Added cove per ASI#3 $2,345,00
Subtotal: $2,345.00
Project Manager(2.90%Applies to all line item types.): $68.01
General Liability(0.10%Applies to all line item types.): $2.35
Superintendent(2.00%Applies to all line item types.): $46.90
Project Engineer(1.50%Applies to all line item types.): $35.18
Overhead and Profit(3.50%Applies to all line item types.): $82.08
Health Insurance(0,75%Applies to all line item types.). $19.35
Bond(G.75%Applies to all line item types.): $19.49
Grand Total: $2,618.38
BMY Construction Group Incorporated Page 1 of 2 Printed On:4/7/2022 09:50 AM
LIQ Pco #009
CONSTRUCTION
GROUPrNCORPORAT£D
Erin Haagenson(The County of Fresno, The County of Fresno, Department of BMY Construction Group, Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,6th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 2 of 2 Printed On:4/712022 09:50 AM
Date: 4/6/2022 01 Al Change Order
To: mike DFS FLOORING g
1717 N.Gateway Blvd,Suite 106 Request
Customer PO: Fresno,CA 93727
CONTRACT Phone:(559)435-6100 Job No: 601265
Fax :(559)435-6700
Contractors License#999046 Request#: 1
DIR#1000006695
CO#: 0
Invoice To: Project:
BMY CONSTRUCTION GROUP, INC. ENVIRONMENTAL COMPLIANCE CENTER
5485 E. OLIVE AVENUE 310 S WEST AVENUE
FRESNO, CA 93727 FRESNO, CA 93706
MIKE MIKE
Phone: (559)243-4200 Phone: (559)243-4200
Fax: (559)222-2380 Fax: (559)222-2380
From: I Project Manager: Estimator:
RON CATES I WARD,CINDY CHRIS WADDELL
Description of Change Order Request:
CHG RMS 102/103 TO COVED SHEET VINYL FROM FLATLAY LINOLEUM
CHANGE RMS 1021103 TO SHEET VINYL FROM LINOLEUM
ADD
Manufacturer Color Name:
Style Color Number:
1 SV-1 SHEET VINYL SUPPLIED AND INSTALLED
FORBO INDUSTRIES,INC. TBD
ETERNAL STEP
Total ADD $2,345.00
Total This Option - Tax Included : $2,345.00
SALESMAN'S SIGNATURE Approximate Installation Start Date:
CUSTOMER'S AUTHORIZATION
41612022 10:3 7 AM Bid#:208245 Page I of I
CONSTRUCTION
GROUP INCORPORATED
May 18,2021
County of Fresno
Construction Division
Attn: Keith Eckert
2220 Tulare Street,711 Floor
Fresno,CA 93721
Re: Environmental Compliance Center
BMY JOB NO.21008
Subject: PCO#14—ESE-1 Price Increase
Revised—7/13122
Mr. Eckert,
BMY Construction Group, Inc.(BMY)is providing the following PCO for the costs and time associated with the changes made
to the emergency eye wash stations. County was possibly going to use existing eye wash stations, which delayed the
ordering of the new stations. A price increase has occurred due to ordering later than bid day. BMY will split the cost
difference due to communication error between delaying ordering of both ESE-1.
BMY is requesting the County to issue a Change Order adding $2,158 to the contract price. In order to perform the work
BMY is requiring a time extension of 0 calendar days.
This PCO is valid for 30 days. Due to unprecedent times in our industry,with volatile material pricing and delivery, it is of the
utmost importance that this PCO be processed quickly. Our industry is currently having supply issues.The cost of material is
on a consistent rise and it is not as readily available,with lead times getting longer. This may directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down and get material and products.
At this time we need your assistance with timely approvals so we can minimize project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further information, please do not
hesitate to contact me.
Respectfully,
Dylan Medeiros
Project Engineer
Page 1 of 1
5485 East Olive Avenue - Fresno, CA 93727 - Phone (559)243-4200 - Fax(559)222-2380
Lic No. 686178
= PCO #014
CONSTRUCTION
GROUP INCORPORATED
BMY Construction Group Incorporated Project:21008-Environmental Compliance Center-Contract#20-S-01
5485 East Olive Avenue 310 S.West Ave
Fresno,California 93727-2541 Fresno,California 93706
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #014: CE #019 - ESE-1 Cost
Increase
TO: The County of Fresno, Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 014/1 CONTRACT: 21008-Environmental Compliance
Center-Contract#20-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Dylan Medeiros(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 7/13/2022
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $2,158.00
POTENTIAL CHANGE ORDER TITLE: CE#019-ESE-1 Cost Increase
CHANGE REASON: Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#019-ESE-1 Cost Increase
Due to County possibly using their existing emergency eye wash station,and then directed to proceed with all new,a price increase has occurred.
County only had one existing eye wash station,and BMY was told to hold off ordering one of the ESE-1.
BMY field error delayed both ESE-1 being ordered.Cost to be split with the County.
ATTACHMENTS:
CO 21108-P007.pdf
# I Budget Code Description Amount
1 1 50-0004.0 Split Cost with County for ESE-1.0ther ESE-1 Delayed Ordering $4,316.00
BMY Construction Group Incorporated Page 1 of 2 Printed On:7/13/2022 11:58 AM
PCO #014
CONSTRUCTION
GROUP INCORPORATED
# Budget Code Description Amount
2 53-0001.0 Eye Wash Station.Other ESE-1 Delayed Ordering $(2,158.00)
Subtotal: $2,158.00
Project Manager(0.00%Applies to all line item types.): $0.00
General Liability(0.00%Applies to all line item types.): $0.00
Superintendent(0.00%Applies to all line item types.): $0.00
Project Engineer(0.00%Applies to all line item types.): $0.00
Overhead and Profit(0.00%Applies to all line item types.): $0.00
Health Insurance(0.00%Applies to all line item types.): $0.00
Bond(0.00%Applies to all line item types.): $0.00
Grand Total: $2,158.00
Erin Haagenson(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,6th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 2 of 2 Printed On:7/13/2022 11:58 AM
TODD COMPANIES DATE: 5/3/2022
P O BOX 6820 CONTRACTOR: BMY
VISALIA, CA 93290 JOB: 21-108 New Environmental Compliance Center
PH(559) 651-5820 DESCRIPTION: Added cost for ESE-1 at shade structure
FAX(559) 651-5830 and warehouse
E-MAIL jt2@jt2inc.com
T&M CHANGE ORDER Contract Time Extension: +/- 10 week lead time
21-108 -P007 pg 1 oft
Material Costs
DIRECT MATERIAL COST $ 3,567.24
SUBTOTAL MATERIAL $ 3,567.24
Labor Costs
LABORER HRS @ $ 59.76 HR. $ -
PLUMBER HRS @ $ 83.56 HR. $ -
OPERATOR HRS @ $ 84.98 HR. $ -
FOREMAN HRS @ $ 84.98 HR. $ -
MASON HRS @ $ 69.31 HR. $ -
P/R TAXES,INSURANCE,BENEFITS 40% OF E-G $ -
SUBTOTAL $ -
TRAVEL TIME TRIPS $ 60.00 TRIP $ -
TRAVEL TIME HRS @ $ 35.00 HR. $ -
SUBTOTAL LABOR $ -
Equipment/Other Costs
EQUIPMENT HRS @ $ - HR. $ -
EQUIPMENT HRS @ $ - HR. $ -
OTHER DAY @ $ - DAY $ -
SUBTOTAL OTHER DIRECT COST $ -
SUBTOTAL PRIME COSTS $ 3,567.24
OVERHEAD 10% $ 356.72
SUBTOTAL $ 3,923.96
PROFIT 10% $ 392.40
SUBTOTAL $ 4,316.36
TOTAL COST $ 4,316
ESTIMATOR:
R:\AR-Billings&Change Orders\Job Files 2021\21-108-BMY-New Environmental Compliance Center,Fresno\Changefile\P007-Added cost for
ESE-1\CO Detailsheet(long form)-P007
TODD COMPANIES DATE: 5/3/2022 1/0/1900 1/0/1900
P O BOX 6820 CONTRACTOR: BMY
VISALIA, CA 93290 JOB: 21-108 New Environmental Compliance Center
PH(559) 651-5820 DESCRIPTION: Added cost for ESE-1 at shade structure
FAX(559) 651-5830 and warehouse
E-MAIL jt2@jt2inc.com
T&M CHANGE ORDER Contract Time Extension: +/- 10 week lead time
21-108 -P007 pg2of2 0
Break down of materials: UOM Quantity Rate Total
ESE- 1 Bid Day EA -2 8,023.58 $ (16,047.16)
ESE-1 Current EA 2 9,807.20 $ 19,614.40
------------------
Total $ 3,567.24
Break down of total hours: Men Hrs Total
0
0
0
FOREMAN 0
MASON 0
Total Hours: 0
R:\AR-Billings&Change Orders\Job Files 2021\21-108-BMY-New Environmental Compliance Center,Fresno\Changefile\P007-Added cost for
ESE-1\CO Detailsheet(long form)-P007
CONTRACT CHANGE ORDER Page 1
From:
JT2 INC DBA TODD COMPANIES Change Order#: P007
1701 N. CLANCY COURT Change Order Date: 05/03/22
P O BOX 6820
VISALIA, CA 93290
(559) 651-5820 Fax (559) 651-5830
License: 788798
To: Prromect:
BMY-New Env. Compliance Center BMY-New Env. Compliance Center
5485 E. Olive Ave 310 S West Ave
Fresno, CA 93727 Fresno, CA 93706
Original Contract Amount: $458,050.00
Total Previous Change Orders: $38,147.00
Total Before this Change Order: $496,197.00
Amount of this Change Order: $4,316.00
Revised Contract Amount: $500,513.00
The Original Construction Agreement is hereby modified and amended by the following deviations from original plans and
specifications:
J5/06/22 (Lauren) - MM -ADDED COST FOR ESE-1 AT SHADE STRUCTURE AND WAREHOUSE. P007
t is mutually agreed that for such change the contract price is increased by$4,316,00 (Four Thousand Three Hundred Sixteen
and 00/100) payable with the payments due under the original construction agreement.
Time for completion of the above cited work is hereby extended 0 days beyond any completion date set forth in the original
;ontract for such work.
ill other provisions of the original contract and agreement shall remain in full force and effect without change because of the
above deviations.
IT2 INC DBA TODD COMPANIES BMY-New Env. Compliance Center
Signed: Signed:
)ated: Dated:
"itle: Title:
CONSTRUCTION
GROUP INCORPORATED
June 6,2022
County of Fresno
Construction Division
Attn: Keith Eckert
2220 Tulare Street, 7th Floor
Fresno, CA 93721
Re: Environmental Compliance Center
BMY JOB NO.21008
Subject: PCO#16—Time Extension—MSB Delays
Mr. Eckert,
BMY Construction Group, Inc. (BMY) is providing the following PCO for the costs and time associated with the
changes made to the completion date. The main switch gear was ordered last November 2021, (see attached power
report)estimated ship date is 6/8/22. Due to the excessive lead time, BMY is requesting a no cost time extension.
BMY is requesting the County to issue a Change Order adding $0 to the contract price. In order to perform the work
BMY is requiring a time extension of 91 calendar days.
This PCO is valid for 30 days. Due to unprecedent times in our industry,with volatile material pricing and delivery, it
is of the utmost importance that this PCO be processed quickly. Our industry is currently having supply issues. The
cost of material is on a consistent rise and it is not as readily available, with lead times getting longer. This may
directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down and get material and
products. At this time,we need your assistance with timely approvals so we can minimize project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further information, please
do not hesitate to contact me.
Respectfully,
Dylan Medeiros
Project Engineer
Page 1 of 1
5485 East Olive Avenue • Fresno, CA 93727 • Phone (559) 243-4200 • Fax(559)222-2380
Lic No. 686178
PCO #016
CONSTRUCTION
GROUP INCORPORATED
BMY Construction Group Incorporated Project:21008-Environmental Compliance Center-Contract#20-S-01
5485 East Olive Avenue 310 S.West Ave
Fresno,California 93727-2541 Fresno,California 93706
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #016: CE #022 - Time Extension -
MSB Delays
TO: The County of Fresno, Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 016/0 CONTRACT: 21008-Environmental Compliance
Center-Contract#20-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Dylan Medeiros(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 6/6/2022
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: 91 days PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $0.00
POTENTIAL CHANGE ORDER TITLE: CE#022-Time Extension-MSB Delays
CHANGE REASON: Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#022-Time Extension-MSB Delays
The main switch gear was ordered last November 2021,the ship date has been 6/8/22.
Due to the excessive lead time,BMY is requesting a time extension for 91 days.
Completion-5/16/22
Revised Completion-8/15/22
ATTACHMENTS:
ECC Power Status Report.pdf
Erin Haagenson(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,6th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 1 of 1 Printed On:6/6/2022 10:47 AM
CoE D JOB STATUS REPORT FOR: Nov 11,2021
WESTECH SYSTEMS INC PAGE 001 OF 001
corvsouonTED E-T-AL o--a --,INC. 827 JEFFERSON
CLOVIS,CA 93612-2250
ENVIRONMENTAL COMPLIANCE CENTER
Customer PO#:46099
CED-FRESNO A APPROVED NOT RELEASED
CONSOLIDATED ELECTRICAL DISTRIBUTORS APPROVED AND RELEASED
3145 S.NORTHPOINTE DR. B
FRESNO,CA 93725 N APPROVED AS NOTED
TEL:5594780996 R RELEASED
FAX:5594960845
H HOLD FOR RELEASE
JOB ID#:C000000213 S SUBMITTED
JOB DESIGNATION:POWER W WAIVED-NO SUBMITTAL REQUIRED
X REJECTED
Z REVISE&RESUBMIT
STS QTY TYP RELEASE RELEASE EST SHIP SHIPPED SHIPPED CARRIER/ CARRIER.PRO#
ORDERED DII&M QTY DATE & QTY DATE LOCATION
1 MSB SQD SQD STANDARD SWBD 11/03/21 1 06/08/22
1 PANEL A SQD NQ MB PANEL INTERIOR 11/03/21 1 11/24/21
1 PANEL A SQD NC50SWMD 11/03/21 1 11/19/21
1 PANEL A SQD MH50 11/03/21 1 11/24/21
1 PANEL B SQD NQ MB PANEL INTERIOR 11/03/21 1 11/24/21
1 PANEL B SQD MH44 11/03/21 1 11/10/21 1 11/09/21 UPS
1ZV349Y4032507
7891
1 PANEL B SQD NC44SWMD 11/03/21 1 11/24/21
1 PANEL C SQD NC50SWMD 11/03/21 1 11/24/21
1 PANEL C SQD MH50 11/03/21 1 11/22/21
1 PANEL C SQD NQ MB PANEL BOARD 11/03/21 1 11/24/21
1 LOT LOT BILLING 11/03/21
CONSTRUCTION
GROUP INCORPORATED
July 20,2022
County of Fresno
Construction Division
Attn: Keith Eckert
2220 Tulare Street,7th Floor
Fresno, CA 93721
Re: Environmental Compliance Center
BMY JOB NO.21008
Subject: PCO#17—T&M Retaining Wall at Transformer pad
Mr. Eckert,
BMY Construction Group, Inc. (BMY) is providing the following PCO for the costs and time associated with the
changes made to transformer pad. Grading plan did not allow for a transformer pad be installed per PG&E
requirements. Grade of the locations were not shown flat. PG&E required a retaining wall be built per their green
book clearances. Cast in place was the only option due to pressure treated wood only allowing 12" maximum
height.
BMY is requesting the County to issue a Change Order adding $20,645.00 to the contract price, In order to
perform the work BMY is requiring a time extension of 0 calendar days.
This PCO is valid for 30 days. Due to unprecedent times in our industry, with volatile material pricing and
delivery, it is of the utmost importance that this PCO be processed quickly. Our industry is currently having
supply issues.The cost of material is on a consistent rise and it is not as readily available,with lead times getting
longer. This may directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down and get material and
products. At this time we need your assistance with timely approvals so we can minimize project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further information,
please do not hesitate to contact me.
Respectfully,
Dylan Medeiros
Project Engineer
Page 1 of 1
5485 East Olive Avenue - Fresno, CA 93727 - Phone(559) 243-4200 - Fax (559) 222-2380
Lic No. 686178
PCO #0'17
CONSTRUCTION
GROUP INCORPORATED
BMY Construction Group Incorporated Project:21008-Environmental Compliance Center-Contract#20-S-01
5485 East Olive Avenue 310 S.West Ave
Fresno,California 93727-2541 Fresno,California 93706
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #017: CE #023 - T&M Transformer
Retaining (Nall
TO: The County of Fresno, Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBERIREVISION: 017/0 CONTRACT: 21008-Environmental Compliance
Center-Contract#20-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Dylan Medeiros(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 6/13/2022
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $20,645.00
POTENTIAL CHANGE ORDER TITLE:CE#023-T&M Transformer Retaining Wall
CHANGE REASON:Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#023-T&M Transformer Retaining Wall
Due to elevation changes and location of the transformer pad a retaining wall is required to meet PG&E clearances.BMY proceeded on T&M to build a
cast in place retaining wall per PG&E green book.
ATTACHMENTS:
PCO#17-Tags.adf
# I Budget Code Description Amount
1 50-0002.0 T&M Retaining Wall.Other T&M PG&E Retaining Wall $18,490.17
Subtotal: $18,490.17
Project Manager(2.90%Applies to all line item types.): $536.21
General Liability(0.10%Applies to all line item types.): $18.49
Superintendent(2.00%Applies to all line item types.): $369.80
Project Engineer(1.50%Applies to all line item types.): $277.35
Overhead and Profit(3.50%Applies to all line item types.): $647.16
Health Insurance(0.75%Applies to all line item types.): $152.54
Bond(=0.75%Applies to all line item types.): $153.28
Grand Total: $20,645.00
BMY Construction Group Incorporated Page 1 of 2 Printed On:7/20/2022 10:34 AM
PCO #017
CONSTRUCTION
GROUP INCORPORATED
Erin Haagenson(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,6th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 2 of 2 Printed On:7/20/2022 10:34 AM
DAILY EXTRA WORK REPORT
MCONSTRUCTION GROUP INC. BMY Construction Group, Inc
B 0 W E R ♦ M I T C M E L L ♦ Y E M 0 T 0
Date: TIME AND MATERIALS WORK REPORT
WorePreformed'For: e ;n: VJCJI
Description of Work: F lua t ;n
Location of Work: c
Labor Equipment
item I Name Hrs Rate Amount Item Description Hrs Rate Amount
1 I V,4w k g 7q--?0 ? tom® 1 foR6rAgn T c
2 1 Aj ft f1 �- C? 2
3 >.t 9' a 3
4 4
5 5
6 6
7 7
sj s
Subtotal 9
Burden Subtotal
Overhead Overhead
Profit Profit
Total i4 oo r q 0 Total 13 -,o
Material Subcontractor
Item Description Qty Unit Cost Amount Item Subcontractor HRS Rate Amount
1 1, N 7, i 6 . H� 1
2 3/Li" C9.-; 3;, 'k 2
3 2-x1-1 f�l �>a.-7 9 I -06 3
4 f<FIx 4
5 5
6 6
7 7
Subtotal t? 8
Tax S.L Subtotal
Overhead Overhead
Profit
Total 19 c Total
Acceptance Section
_ I Totals Section
1,L �-c Description Amount
Contractor's Representative Labor }4cw.Lfc
Equipment t o
Material
Subcontractor's Representative Freight
Subcontractor
Bond
Liability
Owner's Representative J Total
9/15/2020 Page 1 of 1 BMY TM Daily Sheet
DAILY EXTRA WORK REPORT
MCONSTRUCTION GROUP INC. BMY Construction Group, Inc
B O W E R ♦ M ► T C H E L L ♦ Y E M O T 0
Date: 3- TIME AND MATERIALS WORK REPORT
Work Preformed For: pov + w C)+"nic
Description of Work: In six V1 Q r^ -t-
Location of Work: 6 LC,
Labor Equipment
Item I Name Hrs Rate Amount Item Description Hrs Rate Amount
2 cv SE is 2
3 3
4 4
5 5
6 6
7 7
8 8
Subtotal 9
Burden Subtotal
Overhead Overhead
Profit Profit
Total iq c, , Total
Material Subcontractor
Item Description Qty Unit Cost Amount Item Subcontractor HRS Rate Amount
2 Y 2
3 3
4 4
5 5
6 6
7 7
Subtotal 8
Tax Subtotal
Overhead Overhead
Profit
Total q W, Ta Total
Acceptance Section
Totals Section
Description Amount
Contractor's Representative Labor %9 1aaS70
Equipment_ q Ip,_-ty
Material
Subcontractor's Representative Freight,
Subcontractor
Bond
Liability,
Owner's Representative Totall Yjp3.yq
9/15/2020 Page 1 of 1 BMY TM Daily Sheet
DAILY EXTRA WORK REPORT
MCONSTRUCTION GROUP INC. BMY Construction Group, Inc
60WEEI ♦ M ITCH ELL ♦ YEMOTO
Date: G h 7 TIME AND MATERIALS WORK REPORT
Work Preformed For: vv 9, Re} Ernwu 11
Description of Work: vc ,MV KT:rC LV )i
Location of Work: 9CL
Labor Equipment
Item Name Hrs Rate Amount Item Description Hn; Rate Amount
1 Rfl)1 1 G 17,4c 1
2 2
3 3
4 n g 4
5 5
6 6
7 7
8 8
Subtotal 9
Burden Subtotal
Overhead Overhead
Profit Profit
Total rjSSo,q Total
Material Subcontractor
Item Description Qty Unit Cost Amount Item Subcontractor HRS Rate Amount
1 1
2 2
3 3
4 4
5 5
6 6
7 7
Subtotal 8
Tax Subtotal
Overhead Overhead
Profit
Total Total
Acceptance Section
Totals Section
�I Description Amount
Contractor's Representative Labor
Equipment
Material
Subcontractor's Representative Freight
Subcontractor
Bond
Liabilit
Owner's Representative Total 7s.50,
9/15/2020 Page 1 of 1 BMY TM Daily Sheet
DAILY EXTRA WORK REPORT
MCONSTRUCTION GROUP INC. BMY Construction Group, Inc
B O W E R ♦ M I T C H E L L ♦ Y E M 6 T 0
Date: TIME AND MATERIALS WORK REPORT
Work Preformed For: R wRil
Description of Work: c! �.V fYiti
Location of Work: 6cc-
Labor Equipment
Item Name Hrs Rate Amount Item Description Hrs Rate . Amount
1 1
2 2
3 s 3
4 v 4
5 JUs -
5
6 � •�i. 6
7 7
8 8
Subtotal 9
Burden Subtotal
Overhead Overhead
Profit Profit
Total 3(-7s. c Total
Material Subcontractor
Item Description Qty Unit Cost Amount Item Subcontractor HRS Rate Amount
1 ('-a(\C-?, t— I U 10.6 1
2 2
3 3
4 4
5 5
6 6
7 7
Subtotal 8
Tax Subtotal
Overhead Overhead
Profit
Total 6 10,Gg' Total
Acceptance Section
Totals Section
Description Amount
Contractor's Representative Labor ' 7 S 6,0
Equipment
Material
Subcontractor's Representative Freight
Subcontractor
Bond
Liability
Owner's Representative Total i{ 46,6
9/15/2020 Page 1 of 1 BMY TM Daily Sheet
DAILY EXTRA WORK REPORT
MCONSTRUCTION GROUP INC. BMY Construction Group, Inc
B 0 W E R ♦ M I T C H E L L ♦ Y E M 0 T 0
Date: 2�h TIME AND MATERIALS WORK REPORT
Work Preformed For:
Description of Work: S R`�P+ z it
Location of Work:
Labor Equipment
Item Name Hrs Rate Amount Item Description Hrs Rate Amount
1 ?,ftui 7. C3 1
2 .5 OS" q�' 1 1 2
3 3
4 pwc, l 4
5 5
6 6
7 7
8 8
Subtotal 9
Burden Subtotal
Overhead Overhead
Profit Profit
[--.Total i 5-j,coo Total
Material Subcontractor
Item Description Qty Unit Cost Amount Item Subcontractor HRS Rate Amount
1 1
2 2
3 3
4 4
5 5
6 6
7 7
Subtotal 8
Tax Subtotal
Overhead Overhead
Profit
Total Total
Acceptance Section
e Totals Section
Description Amount
Contractor's Representative Labor
Equipment,
Material
Subcontractor's Representative Freight
Subcontractor
Bond
Liability
Owner's Representative Total 318-$-,c&
9/15/2020 Page 1 of 1 BMY TM Daily Sheet
WHITE CAP, BRANCH ADDRESS INVOIINVOICEO NUMBER E
025-FRESNO 10016311619
White Cap,L.P. (559)294-9000
PO Box 4944,Orlando,FL 32802-4944 5780 E.SHIELDS AVE. INVOICE DATE
FRESNO CA 93727 06/17/2022
FRESNO CUSTOMER PO NUMBER
ENROLLMENT TOVEN:j HLP QHB FBG
TERRITORY: PLEASE REMIT PAYMENT TO:
SOLD TO: 145283000 SHIP TO: 10003145353 White
it Ca ,BOX L.P.
40
RECEIVED CYPRESS,CA 90630-0040
BMY CONSTRUCTION GROUP I JUN 2 0 2022 YARD
5485 E OLIVE AVE 5485 E.OLIVE AVE
FRESNO CA 93727 FRESNO CA 93727
BMY CONST. GROUP
ORDER DATE =. OM*R No. ORDERED$Y.
: . ACEAtNfr MANAGER TAKEN 81''',T
06/17/2022 47719506 RAUL ZARCO DELUCA,DAVE LEVATINO,JAKE
enANCH ,u rlosNo:. To" owminourm., CUSFUUM JIMno.
025 10003145353 NET 30 DAYS 5.WALK IN YARD
LOIE PARiNUMwR OESCRIPTION QTYORD UtMTPRICE ,..QTYBKO ,':ATYSHP7 TAX
n. MST"
1 339MD03448 3/4"X4'X8'7PLY MDO PLYWOOD 14 97.39 EA 0 14 1,363.46 113.84
2 11334C 3/4"CLEAR PINE CHAMFER 140 0.2568 FT 0 140 35.95 3.00
3 339DF2416 2"X4"X16'#2 AND BET DOUGLAS FIR 14 22.79 EA 0 14 319.06 26.65
LUMBER
4 15170205 5LB 3D BLUE LATH NAIL 1 23.29 BOX 0 1 23.29 1.95
2 1%ASSESSMENT CA STATE 1%LUMBER ASSESSMENT 1 16.82 EA 0 1 16.82 0.00
BMY INVOICE APPROVAL OZ v"�
PRO IECT# 7ZiQQA CODE #
AUTI iORIZED BY: -_
P,M Slip _
DATE-:
DATE:- TO BE PAID:]a
_
The White Cap Family of Brands includes All-Tex Waterproofing Solutions,Harmac,Kenseal,Marvel Building&Masonry Supply,MASONPRO,
and Williams Equipment&Supply.Learn more at About.WhiteCap.com
THESE ITEMS ARE CONTROLLED BY THE U.S.GOVERNMENT AND AUTHORIZED FOR EXPORT ONLY TO THE COUNTRY OF
ULTIMATE DESTINATION FOR USE BY THE ULTIMATE CONSIGNEE OR END-USER(S)HEREIN IDENTIFIED. THEY MAY NOT BE
RESOLD,TRANSFERRED OR OTHERWISE DISPOSED OF TO ANY OTHER COUNTRY OR ANY PERSON OTHER THAN THE
AUTHORIZED ULTIMATE CONSIGNEE OR END-USER(S),EITHER IN THEIR ORIGINAL FORM OR AFTER BEING INCORPORATED INTO
OTHER ITEMS,WITHOUT FIRST OBTAINING APPROVAL FROM THE U.S.GOVERNMENT OR AS OTHERWISE AUTHORIZED BY U.S.
LAW AND REGULATIONS.
For questions regarding this invoice please call 1-866-857-0295. TOTAL GROSS 1,758,58
NO REFUNDS OR EXCHANGES ON NON STOCK MERCHANDISE TOTAL TAX 145.44
Visit https://www.whitecap.com/terms/terms-conditions-of-sale-terms to view TOTAL SHIPPING complete terms and conditions. AND HANDLING 0.00
RECEIVED BY: SIGNATURE COPY ON FILE TOTAL INVOICE 1,904.02
Page 1 of 1
CONSTRUCTION
GROUP INCORPORATED
BMY EQUIPMENT CHARGE TAG
JOB# 21003 JOB NAME:
EQUIPMENT#:
EQUIPMENT DESCRIPTION: rL(
MONTH&YEAR OF USE: j
HOW MANY"WORKDAYS"or"MONTHS"ON SITE:
SUPERINTENDENT or PM SIGNATURE: 1L1d4
Office Use:
Quantity $Rate $Extension Code
Day Rate
Week Rate � ��r�yQB ���•() ��'�z��
Month Rate
Delivery to Jobsite Rate
Pick Up From Jobsite Rate
TOTAL 653,08
1-4 work days=Day Rate 5 to 15 work days=Week Rate 16+work days=Monthly Rate
SEND TO HOWARD BEYER WHEN THIS FORM IS COMPLETED
GMP,T&M and Force Account Projects only
CONSTRUCTION
GROUP INCORPORATED
BMY EQUIPMENT CHARGE TAG
JOB# 2 j 00 JOB NAME:
EQUIPMENT M
EQUIPMENT DESCRIPTION:
MONTH&YEAR OF USE:
HOW MANY"WORK DAYS"or"MONTHS"ON SITE: .; S
SUPERINTENDENT or PM SIGNATURE: k10
Office Use:
F- Quantity $Rote $Extension Code
Day Rate lzgo
Week Rate `�
Month Rate
Delivery to Jobsite Rate 100
Pick Up From Jobsite Rate l d0 too
-- TOTAc �1630 OQ
1-4 work days=Day Rate 5 to 15 work days= Week Rate 16+work days Monthly Rate
SEND TO HOWARD BEYER WHEN THIS FORM IS COMPLETED
GMP,T&M and Force Account Projects only
A SERVING THE ENTIRE CENTRAL SAN JOAQUIN VALLEY
PLAZA, CONCRETE, INC. CALL(559)994-9314 or(559)994-9982
tow—i BUSINESS ADDRESS:2121 E,MALAGA AVE.-FRESNO,CA 93725
ORDER r.✓ JOB r. TR DATE: ^+
q 7r
NO,E
SOLDTO• INVOICE N® 2847
JOB ADDRESS:• CITY:
f Q ho
NEAREST CROSS!MAP PAGE:
OTY PPRICE ANT
i CUBIC YARD METER READING SACK CONTENT CONCRETE !6 c) L O
ADMIX
ARRIVED START
T ENBD FIBER
im DELIVERY CHARGE
TAUCIC� IPYEV WOOF APER WAL SUBTOT
ROJE T# C DE#, T L D—O
UTHO IZED E Y: STAmnwfTIME
D.M. s i P JaAE65,URCHARGE
ATE: SATURDAYISUNDA
ATE TO BE P ID: I&AL
TYPE OF PAYMINT CASH CHECK CHARGE CREDIT
pp (3V^ 1q2 AMOUNT DUE I
e-I rQ.y cw q3 �l�
BYrm SIGNING � 10a g oNs
Ttn Cuff" )Corstrcs w-M Ise a Tway(5)rniesutes frw I q00&0 LCvml=usW by t o Cu0 m�ow Men Ilene-4 b6ChM
dav®ry wo be Mr-Awd,w a Geliverles as made to t a best 5 not
be h&rule for wy dm&V mjwd where ls"ih rr
Chcc p d 2%psr m0ntr°Q24%APR)will be charge',l 82=P0 t
cmditn,stir ws%w,tnd kft*w aearted in owww d i or t
`manses dst—rsL plc.aa accept'�=as%"mbm'oat wa lah i
ft mstz n to warn dea erect.— de. wl9 also bw is( s
teas,end wm of wftctm.TM contirared Ww wndit+rx-A 9, wean
Plan cmaa*Iac and V*Custw*dC4r&ackw.
NOW saswraMM"NOMAMspa ^ Agent
ma PoPrruwo AM CEMENT
PnacartYAg:r rinse X _.
PLAZA CONCRETE, INC. sEBlRFalmt?efTiftEmIRALaANdQAfliifNl vAm"
lfus um AwRem-mi E,mAIAGA AvL-FREBIA CA,93725 CALL(559)994-9314 or(W9)994-9982
ORDER t J08�: I OD� GATE
2OLDTIJ: IHvo�EHoN o
XO ADOWSS: GTM
WAFT r r g;iMAPPAGE
cTr PMCE Afr1T
�1qo I+ETER RE oO sAM WCRETE �-
ADMIX
AFffM START
JOB
.JM JOB
DELIVERY CHARGE .
TRUCKt ME'I7:R YAFM 51ARO END SUSTDTAL
TAX
STAlIDBY TUE
Ott) FUEL SURCHARGE
sATURDAr
DELJVERY
PREY SAL
TYPE GF PAv r OW CHINCKn CKVW cram
Custom w Accepts the$1OD.00 Penalty AS Checks (Initials)
By 1fItiNM MOW THE OWOMSUOOWRWMFI UNDER8TAMS a AGREES TO Tf1E FDIADONG TOM&COMMONS
7he0eelwseeCensaoM�aaw�watis *��►� ekop,rwe*mftOJOWAPM10 eeAssn+daewweberae.fWt.pWWWdWInarpk
The wIt b.sibwed Ave(�n�inlsss hw urMoadinp Oma pet YardfUnit a a4 the arrival d fie brkk m sfkr Dory
quad by tw Dyer ttb tlnfs wtM be ohsrysd out at a Fab d$iJW per n FAL No dekns br dsbY ertootaMmd on
deftwry Va be slowed,ee ON del"MIS sn made to ttm beet of aw abft As ardws an for spat cudaide dslMy-nm e•.a r•,rK• wih not
be told nnpordbe for sny damaps oauad when d~ft ktafde of the property bne,No mhaab a sdlustrner"INOW Oft tap,A RNiance
Chsrp of 2%per month(4i%APA)wM ba dope b.al unpaid fhOM The CuSkmodConvedoregressla pay d fgaMWd ie Dab of
to am rb attornye bee,and kglat s acwuad N tM ewrk of lOO 121' PLEASE SE ADVISED in 1ha ewnt OdI ft YNolos Y urn or
beoorrw maws R puns swap)to a 1"W no0os trot wd wna...b r... fntard b Iles,nndWWs fbn spaknt b properly on which
ire arswWs wen ddvoad rw..or..n u� wi aleo�i bpM cn the Drocssdk+0e is coilera:Ob aarpsa owed bickW g eii NWOM attote»y's
lees,erd oosb of cdsdoa Its oortlrrrsd terms revewe aide of ifs Dativmy invek a an a teen drill apreerrwnt between
nm er..r.hm.and the
errsns "a uo awsti Ao"m IV s I Apard for the Customsr/Can
irrrsn X,
500003
1
CONSTRUCTION
GROUP INCORPORATED
July 13,2021
County of Fresno
Construction Division
Attn: Keith Eckert
2220 Tulare Street,711 Floor
Fresno,CA 93721
Re: Environmental Compliance Center
BMY JOB NO.21008
Subject: PCO#18—Tie into Existing Fire Line
Mr. Eckert,
BMY Construction Group, Inc.(BMY)is providing the following PCO for the costs and time associated with the changes made
to the fire line point of connection. RFI#8 states to refer to utility plan sheet C4.0 for POC.There is an existing line 7'-8'south
that can be tied into. Cost seen below. Another option is to pay the City to bring the fire service to the correct location per
utility drawings.
BMY is requesting the County to issue a Change Order adding $6,961.78 to the contract price. In order to perform the work
BMY is requiring a time extension of 0 calendar days.
This PCO is valid for 30 days. Due to unprecedent times in our industry,with volatile material pricing and delivery, it is of the
utmost importance that this PCO be processed quickly. Our industry is currently having supply issues.The cost of material is
on a consistent rise and it is not as readily available,with lead times getting longer. This may directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down and get material and products.
At this time we need your assistance with timely approvals so we can minimize project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further information, please do not
hesitate to contact me.
Respectfully,
Dylan Medeiros
Project Engineer
Page 1 of 1
5485 East Olive Avenue • Fresno, CA 93727 • Phone (559)243-4200 • Fax(559)222-2380
Lic No. 686178
= PCO #018
CONSTRUCTION
GROUP INCORPORATED
BMY Construction Group Incorporated Project:21008-Environmental Compliance Center-Contract#20-S-01
5485 East Olive Avenue 310 S.West Ave
Fresno,California 93727-2541 Fresno,California 93706
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #018: CE #031 - Tie into Existing
Fire Service
TO: The County of Fresno, Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 018/0 CONTRACT: 21008-Environmental Compliance
Center-Contract#20-S-01 Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Dylan Medeiros(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 7/13/2022
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $6,961.78
POTENTIAL CHANGE ORDER TITLE: CE#031 -Tie into Existing Fire Service
CHANGE REASON: Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#031 -Tie into Existing Fire Service
Existing fire service is located 7'-8'south of what is shown on the plans,and 6'below grade.
ATTACHMENTS:
CO 21108-P009.pdf
# I Budget Code Description Amount
1 22-0100.S Plumbing/TODD.Subcontract Tie into existing fire line $6,235.00
Subtotal: $6,235.00
Project Manager(2.90%Applies to all line item types.): $180.82
General Liability(0.10%Applies to all line item types.): $6.24
Superintendent(2.00%Applies to all line item types.): $124.70
Project Engineer(1.50%Applies to all line item types.): $93.53
Overhead and Profit(3.50%Applies to all line item types.): $218.23
Health Insurance(0.75%Applies to all line item types.): $51.44
Bond(0.75%Applies to all line item types.): $51.82
Grand Total: $6,961.78
BMY Construction Group Incorporated Page 1 of 2 Printed On:7/13/2022 07:46 AM
PCO #018
CONSTRUCTION
GROUPINCORPORATED
Erin Haagenson(The County of Fresno, The County of Fresno,Department of BMY Construction Group,Inc.
Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,6th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 2 of 2 Printed On:7/13/2022 07:46 AM
TODD COMPANIES DATE: 6/7/2022
P O BOX 6820 CONTRACTOR: BMY
VISALIA, CA 93290 JOB: 21-108 New Environmental Compliance Center
PH(559) 651-5820 DESCRIPTION: Tie in existing fire service at S. West
FAX(559) 651-5830 Ave. existing 8" service is 8' south and 6'
E-MAIL jt2@jt2inc.com below grade.
T&M CHANGE ORDER Contract Time Extension:
21-108 -P009 pg 1 oft
Material Costs
DIRECT MATERIAL COST $ 2,753.60
SUBTOTAL MATERIAL $ 2,753.60
Labor Costs
PLUMBER 8 HRS @ $ 83.56 HR. $ 668.48
OPERATOR 4 HRS @ $ 84.98 HR. $ 339.92
P/R TAXES,INSURANCE,BENEFITS 40% OF E-G $ 403.36
SUBTOTAL $ 1,411.76
TRAVEL TIME TRIPS $ 60.00 TRIP $ -
TRAVEL TIME 2 HRS @ $ 35.00 HR. $ 70.00
SUBTOTAL LABOR $ 1,481.76
Equipment/Other Costs
EQUIPMENT-Aluminum Shield 1 DAYS @ $ 110.00 DAY $ 110.00
EQUIPMENT-Service Truck 4 HRS @ $ 25.00 HR. $ 100.00
EQUIPMENT-Mini Excavator 8 HRS @ $ 65.00 HR. $ 520.00
EQUIPMENT-Water Truck 4 HRS @ $ 83.00 HR. $ 187.50
SUBTOTAL OTHER DIRECT COST $ 917.50
SUBTOTAL PRIME COSTS $ 5,152.86
OVERHEAD 10% $ 515.29
SUBTOTAL $ 5,668.15
PROFIT 10% $ 566.81
SUBTOTAL $ 6,234.96
TOTAL COST $ 6,235
ESTIMATOR:
R:WR-Billings&Change Orders\Job Files 2021\21-108-BMY-New Environmental Compliance Center,Fresno\Changefile\P009-Tie in existing
fire service\CO Detailsheet(long form)-P009
TODD COMPANIES DATE: 6/7/2022
P O BOX 6820 CONTRACTOR: BMY
VISALIA, CA 93290 JOB: 21-108 New Environmental Compliance Center
PH (559) 651-5820 DESCRIPTION: Tie in existing fire service at S. West
FAX (559) 651-5830 Ave. existing 8" service is 8' south and 6'
E-MAIL jt2@jt2inc.com below grade.
T&M CHANGE ORDER Contract Time Extension:
21-108 -P009 pg2of2 0
Break down of materials: UOM Quantity Rate Total
8" C900 DR 14 FT 20 44.55 $ 891.00
8"MJ 90 EA 2 216.00 $ 432.00
Concrete YDS 2 340.00 $ 680.00
DIR Fee EA 1 270.00 $ 270.00
Megalug kit EA 4 120.15 $ 480.60
------------------
Total $ 2,753.60
Break down of total hours: Men Hrs Total
OPERATOR-Excavate and install 1 4 4
PLUMBER-Excavate and install 2 4 8
Total Hours: 12
RAAR-Billings&Change Orders\Job Files 2021\21-108-BMY-New Environmental Compliance Center, Fresno\Changefile\P009-Tie in existing
fire service\CO Detailsheet(long form)-P009
CONTRACT CHANGE ORDER Page 1
From:
JT2 INC DBA TODD COMPANIES Change Order#: P009
1701 N. CLANCY COURT Change Order Date: 06/07/22
P O BOX 6820
VISALIA, CA 93290
(559)651-5820 Fax (559) 651-5830
License: 788798
To: Project.
BMY-New Env. Compliance Center BMY-New Env. Compliance Center
5485 E. Olive Ave 310 S West Ave
Fresno, CA 93727 Fresno, CA 93706
Original Contract Amount: $458,050.00
Total Previous Change Orders: $38,147.00
Total Before this Change Order: $496,197.00
Amount of this Change Order: $6,235.00
Revised Contract Amount: $502,432.00
The Original Construction Agreement is hereby modified and amended by the following deviations from original plans and
specifications:
06/14/22 (Lauren) - DB -TIE IN EXISTING FIRE SERVICE AT S. WEST AVE. EXISTING 8" SERVICE IS 8' SOUTH AND 6'
BELOW GRADE. P009
It is mutually agreed that for such change the contract price is increased by$6,235.00 (Six Thousand Two Hundred Thirty-Five
and 00/100) payable with the payments due under the original construction agreement.
Time for completion of the above cited work is hereby extended 0 days beyond any completion date set forth in the original
contract for such work.
All other provisions of the original contract and agreement shall remain in full force and effect without change because of the
above deviations.
JT2 INC DBA TODD COMPANIES BMY-New Env. Compliance Center
Signed: Signed:
Dated: Dated:
Title: Title: