HomeMy WebLinkAboutCCO 26 16-S-04 Bernards.pdf LETTER OF TRANSMITTAL - C.C.O. No. 026 July 26, 2022
Page 1 of 5
TO: Steven White, Director West Annex Jail
Public Works and Planning
ATTN: Will Kettler
Division Manager CONTRACT NO. 16-S-04
FROM:
Jim Anderson, Sr. Project Manager
Kitchell CEM
STATUS OF FUNDS
Contract Items $ 81,756,000.00 Original Allotment $ 85,843,800.00
Co. Furnished Materials $ 0.00 Supplemental Allotment $ 0.00
Previous CCO's $ 3,724,458.00 Total Allotment $ 85,843,800.00
This CCO $ 171,111.00 Obligated Funds $ 85,651,569.00
Total Obligated Fund $ 85,651,569.00 Unobligated Balance $ 192,231.00
Note: 1. Total allotment is the bid amount plus the Board Chairman's limit to authorize
Change Orders $4,087,800.00
DESCRIPTION (PCO 0173)
ASI 042— Radio System Changes
WHY:
The Sheriff IT requested a low voltage cable installed between the WAJ and Main Jail for the new
Digital Antenna System
HOW:
Time & Material
COST:
A$3,385.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0424)
AS[ 100—Guard Station Ceiling, HVAC and Lighting
WHY:
Design documents did not show fire/smoke dampers in ductwork penetrating the 2nd and 3rd floor
guards stations. A total of (4) FSD's were required to be installed along with associated power and
fire alarm connections.
I
I
Letter Of Transmittal — C.C.O. No 026
Contract No. 16-S-04
July 26, 2022
Page 2 of 5
HOW:
Time and Material
COST:
A $51,683.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0566)
RFI 1125—Colored Sidewalk Concrete (City Requirement)
WHY:
The City of Fresno required that a particular colored dye was required in the City Right-of-Way for
sidewalks.
HOW:
The County and Contractor split the costs submitted by the subcontractor
COST:
A$2,050.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0580)
ASI 110, RFI's 1147/1145— Elevators Heat/Smoke Detection (Material Only)
WHY:
The designed fire alarm systems within each of the elevator shafts did not comply with the State Fire
Code per the SFM and each shaft required a different smoke and heat detection system (Vesda and
Protector Wire).
HOW:
Time and Material
COST:
A $75,104.00 Increase
TIME:
No time extension requested by contractor.
Letter Of Transmittal — C.C.O. No 026
Contract No. 16-S-04
July 26, 2022
Page 3of5
DESCRIPTION (PCO 0608)
RFI 1207 —Core Furniture Receptacle Circuits
WHY:
Power connections required by the Countys furniture provider were different than what was expected
by the Contract documents
HOW:
Lump Sum
COST:
A $783.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0647)
ASI 117 —Cell Lighting Modifications (Night Light Function)
WHY:
Each of the lights within the cells did not have a "night light" function and were required to be rewired.
HOW:
Time and Material
COST:
A 27,343.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0648)
RFI 1129.3—Street Tree Planting Conflict
WHY:
The area where a tree was required to be planted had concrete under the area and could not be
planted. Direction was given to place colored concrete. The tree was replanted in a different area.
HOW:
Lump Sum
COST:
A$1,769.00 Increase
TIME:
No time extension requested by contractor
I
Letter Of Transmittal — C.C.O. No 026
Contract No. 16-S-04
July 26, 2022
Page 4 of 5
DESCRIPTION (PCO 0649)
City of Fresno Permit Fee- Landscaping
WHY:
Cost for contractor to procure the landscaping permit through Fresno City
HOW:
Lump Sum
COST:
A $936.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0650)
Remove Temporary Fire Water Valve at Central Plant
WHY:
Contractor was required to install a temporary fire water valve in the Central Plant to isolate water flow
and install a Post Indicator Valve that was found under the existing asphalt.
HOW:
Lump Sum
COST:
A $1,956.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0652)
AS[ 115—ADA Video Visitation Swing Stool
WHY:
The ADA swings stools located in sub-dayrooms needed to be removed and modified to comply with
ADA requirements
HOW
Lump Sum
COST:
A $4,641.00 Increase
TIME:
No time extension requested by contractor.
1
I
Letter Of Transmittal — C.C.O. No 026
Contract No. 16-S-04
July 26, 2022
Page 5 of 5
DESCRIPTION (PCO 0656)
ASI 118 —Guard Station Dimmer
WHY:
The Sheriffs Dept requested added dimmer light switches added to the level 2 & 3 guard stations
HOW:
Lump Sum
COST:
A $1,461.00 Increase
TIME:
No time extension requested by contractor.
NET COST THIS CCO : $171,111.00 INCREASE AND 0 CALENDAR DAY EXTENSION
I
i
I
I
Prime Contract Change Order
Detailed
Date: 7/12/2022
To Contractor: Contract Number: 16-S-004
Bemards Change Order Number: 026
1781 E Fir Ave,#205
Fresno,CA 93720
The Contract is hereby revised by the following items:
Contract Change Order#026
PCO Description Amount
0173 ASI 042-Radio System Changes $3,385.00
0424 ASI 100-Guard Station Ceiling,HVAC and Lighting $51,683.00
0566 RFI 1125-Site T Sidewalk-Stamped Concrete(City of Fresno)Requirement $2,050.00
0580 ASI 110-RF1117/1145-Elev Vesda Sys(MaCl Only) $75,104.00
0608 RFI 1207-Core Furniture Receptacle Circuits $783.00
0647 ASI 117-Cell Lighting Modification-at 12-1-3-Reference RFI#1215 Cell $27,343.00
Lighting Control
0648 RFI 1129.3-Site NW Street Tree Planting Conflict $1,769.00
0649 City of Fresno Permit Fee-Landscaping $936.00
0650 Remove Temporary Valve at CUP $1,956.00
0652 ASI 115-ADA Video Visitation Swing Stool L2-L3 $4,641.00
0656 ASI 118-Guard Station Dimmer $1,461.00
The original Contract Value was....................................................................................................................... $81.756,000.00
Sum of changes by prior Prime Contract Change Orders................................................................................ $3,724,456.00
The Contract Value prior to this Prime Contract Change Order was................................................................ $85,480,458.00
The Contract Value will be changed by this Prime Contract Change Order in the amount of.......................... $171,111.00
The new Contract Value including this Prime Contract Change Order will be.................................................. $85,651,569.00
The Contract duration will be changed by....................... ........... 0 Days
......................................................................
The revised Completion date as of this Prime Contract Change Order is....................................................... September 18,2020
1
i
D UN= Prime Contract Change Order
Detailed
Approval Recommended
Bemards Kitchell CEM
CONTRACTOR PROJECT MANAGER
By Bruce Waltz By Jim Anderson
(�/
SIGNATURE A 4R SIGNATUR`
DATE / �-2-� ZZ DATE
Approval Recommended Approved By
DLR Fresno County
PROJECT MANAGER DIRECTOR
BY Gregg Williams By Steven White
SIGNATURE �7 cC� SIGNATURE
DATE 7/26/22 DATE 22
Approved By
Fresno County Fresno County
COUNTY COUNSEL COUNTY ADMINISTRATIVE OFFICER
BY Daniel .Cede borg BY Paul Nerland
SIGNATUR "� SIGNATURE
DATE �.., DATE
Fresno County
CHAIRMAN,BOARD OF SUPERVISORS
BY Brian Pacheco
SIGNATURE AL
DATE l b-l if 4)L
OEM= Prime Contract Change Order
Detailed
We the above-signed contractor,have given careful consideration to the change proposed and hereby agree,when this proposal is approved,
that we will provide all equipment,furnish all materials,except as may otherwise be noted above,and perform all services necessary for the work
above specified,and will accept as full payment therefor the prices shown above.
If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the Specifications as to proceeding with
the ordered work and filing a written protest within the time therein specified.
By accepting a Change Order,Contractor agrees to the changes,if any,in the Contract Price specified for each item and to the specified
Extension of Time allowed,if any,for completion of the entire Work on account of such Change Order,and agrees to furnish all labor and
materials and perform all Work necessary to complete all additional Work specified therein for the price adjustment and within the time specified
thereir-L Contractor shall make no additional claim for adjustment to the Contract Price or Contract Time,nor for additional costs or damages,an
account of the work referenced in such Change Order. A Change Order duly issued by the Owner and accepted by the Contractor shall
constitute a complete accord and satisfaction as to the Work,Contract Price,and Contract Time changed thereby. Contractor shall defend and
indemnify the Owner,its officers,employees,agents and consultants,if any Subcontractor asserts any claim against the Owner that contradicts,
or is inconsistent with,a duty issued Change Order accepted by Contractor. Section 0126 00,1.9