HomeMy WebLinkAbout19-S-04 CCO 073.pdf F CO County of Fresno
C Department of Public Works and Planning
Development Services&Capital Projects Division
Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 7/27/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#073
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Provide material,labor,and equipment to complete the following concrete improvements:
1.Excavate,and install(14)bollards for PG&E pad.Bollards and bollard finish by others.
Attachment(s):
CO Coversheet, PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $14,985.54
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date $369,441.95
Adjusted Contract Dollar Amount: $11,733,941.95
Total Adjusted Calendar Days To Date: 80
Director's Change Order Limit Balance: -$159,441.95
Adjusted Construction Completion Date: 12/15/21
�da�idroh
Reviewed: Roger Davidson ,—;d—„-a,,o„13 48,o„
Architect
Reviewed: LaRue Goossen R�`a�A - aeon
Project Manager
Reviewed: Mandeep S. Sekhon
Construction Manager
Reviewed: William M. Kettler
Division Manager
Approved. Steven E. White yTEYEN e-cvff/7E
s EVEN ewHITE jA. 16 VOT
Dire or
Approved: Brian Pacheco V1—b,
Board of Supervisors Chairman
Approval Date: S E P 0 1 2022
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriff's Office Thomas Trester
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
F COUP', County of Fresno
Department of Public Works and Planning
O� BS O Development Services&Capital Projects Division
�RES� Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 7/27/2022
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#073
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#073 is hereby approved by the County.
Change Order Scope of Work:
Provide material,labor,and equipment to complete the following concrete improvements:
1.Excavate,and install(14)bollards for PG&E pad.Bollards and bollard finish by others.
Attachment:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $14,985.54
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: $369,441.95
Adjusted Contract Dollar Amount: $11,733,941.95
Total Adjusted Calendar Days To Date: 80
Adjusted Construction Completion Date: 12/15/21
LaRue Goossen LaRue Goossen(Jul 27,2022 13:13 PDT)
Project Manager Signature
Date: Jul 27,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1,Provide all equipment material.labor and services required to complete the Scope of Work specified in
this Change Order.
2. The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
AV0IY/ag
Accepted By: K/assen Corporation Rod Paine(Jul 28,2022 07:42 PDT)
Authorized Signature
Date: Jul 28,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerna,Staff Analyst
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
App. DVWW1JN=$)
1,11Z. Credit Rejected Pending Adj. Days Description
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 $91,000.00 5 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
GGO 009 - N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 $572,775.76 0 Storage Bldg.electric
CCO 012 $32,245.91 0 Substation electrical
CCO 013 $112,372.79 0 Electrical plan update
CCO 014 $7,444.00 0 Blockout revised data room
CCO 015 $14,657.00 0 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020 12/14/2021 $2,794.26 0 Fab.&Install metal sill flashing
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
CCO 022 - N/A
CCO 023 12/14/2021 $3,093.25 0 Plumbing alterations per ASI 2&3
CCO 024 12/14/2021 $795.79 0 Revised Architecturals
CCO 025 11/22/2021 $8,355.00 0 Install Overflow pipe minus penetration of gutter
CCO 026 $0.00 56 Metal Building Delay#1
CCO 027 12/29/2021 $4,486.63 0 Fur out West Exterior Wall
CCO 028 12/29/2021 $2,097.75 0 Hardware changes from rev.in dwgs.ASI 7
CCO 029 $12,487.64 1 Reroute 2.5"and 3"fire mains per RFI 64
CCO 030 $71,190.79 0 Overhead door material price increase
CCO 031 12/29/2021 $10,008.10 0 Ceramic tile alterations
CCO 032 12/29/2021 $6,806.50 0 Add.Recessed TV and Databoxes
CCO 033 1/19/2022 $3,212.39 0 Tower Closure Strips
CCO 034 12/29/2021 $3,261.63 0 Provide power&connection to(5)hand dryers
CCO 034.1 $1,784.20 0 Provide power&connection to(5)hand dryers r2
CCO 034.2 7/5/2022 $1,784.20 0 Provide power&connection to(5)hand dryers r3
CCO 035 12/29/2021 -$5,345.00 0 ASI to omit interior stone veneer and finish gyp board
CCO 036 $38,224.99 0 Alternate Sectional Doors
CCO 037 - N/A
CCO 038 6/28/2022 28 Extended site rain/mud delays
CCO 039 - N/A
CCO 040 1/18/2022 $5,557.64 0 Lighting for Sheriff Star
CCO 041 $267,768.79 0 Data Rack Revisions
CCO 041.5 6/20/2022 $66,691.06 15 Switchgear to 2000/Data Center Revisions
CCO 042 $7,334.25 0 Additional sunshade
CCO 043 3/30/2022 $3,633.89 0 Supply and Install"B"metal angle
CCO 044 2/16/2022 $3,352.40 0 Electrical for TV boxes
CCO 045 0 N/A
CCO 045.3 7/25/2022 $57,595.32 0 Extra work at force acc.for June
CCO 046 4/25/2022 $9,397.07 0 Submittal changes-Door hardware
CCO 047 3/8/2022 $3,082.34 0 Additional metal studs per new arch drawings
CCO 048 $53,421.75 - CE#068-Rule 16
CCO 048.1 6/10/2022 $44,855.53 0 CE#068-Rule 16
CCO 049 6/20/2022 $11,371.85 0 Install block wall
CCO 050 3/30/2022 $14,385.40 0 Tower and Entry Fascia Revision
CCO 051 4/8/2022 $4,459.67 0 Added circuits to IDU Units
CCO 052 - N/A
CCO 053 - N/A
CCO 054 4/20/2022 -$114.65 0 Delete Waste Dispensers&Add Hand Dryers
CCO 055 $71,905.65 0 Delayed lighting package order-ASI#03
CCO 056 6/28/2022 -$473.00 0 Memorial CMY wall alteration
CCO 057 4/22/2022 $3,054.20 0 Power&Connection to plumbing fixtures TP-1
CCO 058 6/28/2022 $308.85 0 Circulating pump power
CCO 059 - N/A
CCO 060 - N/A
CCO 061 $13,898.70 0 ASI 04-21-2022-01 Tower revisions
CCO 062 $8,108.54 - N/A
CCO 063 5/3/2022 $1,079.04 0 Install 6 footing sleeves
CCO 064 - N/A
CCO 065 - N/A
CCO 066 5/24/2022 $837.38 0 Cleanout relocation by TEV transformer
CCO 067 5/3/2022 $1,052.06 0 Additional CMU at removed gate
CCO 068 $75,413.07 6 N/A
CCO 068.1 $75,413.07 7 Courtyard Revisions
CCO 068.2 7/25/2022 $61,502.69 6 Courtyard Revisions
CCO 069 6/17/2022 $5,468.33 1 Enlarged mechanical pad
CCO 070 - N/A
CCO 070.1 7/5/2022 $2,946.78 0 Electrical room lighting
CCO 071.1 7/25/2022 $17,372.89 0 Underground conduits
CCO 072 - N/A
CCO 073 7/27/2022 $14,985.54 0 Install(14)bollards per PG&E pad
CCO 073.1 $7,691.90 0 Install(7)bollards per PG&E pad
CCO 074 - N/A
CCO 074.1 7/26/2022 $22,094.02 0 Storage BLDG structural pour back
CCO 075 - N/A
CCO 076 - N/A
CCO 077 - N/A
CCO 078 - N/A
CCO 079 - N/A
CCO 080 - N/A
Totals $536,874.60 -$167,432.65 $1,440,748.36 $79,947.00 80
K
PCCO #073
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno, California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #073: PG&E Bollard Installations
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 7/19/2022 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $ 14,985.54
DESCRIPTION:
CE#110-PG&E Bollard Installations
This is to install 14 bollards.
ATTACHMENTS:
COR#16 PG&E Bollard Installations pdf Fergeson Quote Ddf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
072 1 PG&E Bollard Installations 14,985.54
TOTAL: $14,985.54
CHANGE ORDER LINE ITEMS:
PCO#072: PG&E Bollard Installations
# Cost Code Description Type Amount
1 03-300-Cast-in-Place Concrete Installation of Bollards Subcontractor $10,528.23
2 16-100-Electrical Ferguson Bollards Subcontractor $2,804.11
Subtotal: $13,332.34
Fee:10.00%Applies to all line item types. 1,333.23
Insurance:1.40%Applies to all line item types. 186.65
Bond:1.00%Applies to all line item types. 133.32
Grand Total: $14,985.64
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $425,935.88
The contract sum prior to this PCCO was $ 11,790,435.88
The contract sum would be changed by this PCCO in the amount of $ 14,985.54
The new contract sum including this PCCO will be $ 11,805,421.42
The contract time will not be changed by this PCCO
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On:7/19/2022 05:14 PM
V&G Builders, Inc.
Contractor License#887235—DIR Registration 1000013156—SB 45117—DBE 38151
COR#16 DATE:07/19/2022
TO: FROM:
Curtis Gardner Carlos Gonzalez
Klassen Corporation V&G Builders, Inc
2021 W estwind Dr 1444 Fulton St.,Suite 210
Bakersfield,Ca,93301 Fresno,CA 93721
P: (661)477-3232 P: (559)907-1068
em al cpgonzalez@vg-builders.com
We are pleased to offer the following pricing to com Bete the following concrete im p-ovem ants:
Provide M aterial, Labor,and Equipm Ent to com bete the following concrete im p-ovem ents
1. Excavate,and install 14 bollards for PG&E pad. Bollards and bollard finish by others.
The total am cunt to com Oete the following im lxovem efts is..............................$10,528.23
Price
Provide M aterial, Labor, m ant to com bete the following concrete im govern ants
2. Excavate,and install 7 bollards for Bollards and bollard finish by others
The total am cunt to com Oete the following im p•ovem efts is.............................. .
See PCCO 073.1 for price of 7 bollards
PRICE IS BASED ON(2) MOBILIZATIONS; BID PROPOSALS GOOD FOR 30 DAYS
Specific Exclusions:
1. Bonds/Allowances/Inspection Costs/Perm ts/Testing/Flatness Test/Surveying
2. Engineering/shop drawings/professional services
3. Dem dition/Saw-cutti rig to accom m date dem o
4. Hauling excavation spoils from site
5. Steel Handrails/Sleeves/Em beds
6. Earthwork, Rough Grading(grades to be within 1/10 of an inch)/Scarifying/
Over-excavation/Lim eTreatm Ent/Com iaction of existing subgrade/Hazardous M aterial Rem cval
/Shoring/Geogrid/Dewatering/M ucking Footings/Backfilling of retaining walls/foundation
7. Fence Footings/Sign Footings/Light Post Footings
8. Site Utilities/Electrical/Vaults/Precast Concrete Pads/Thrust Blocks/Splash Blocks/catch
basins/wheel stops/concrete encasem Ent for utilities/light pole standards/Precast Concrete
9. Signage/Striping/Painting/Sealers/Sealants&epoxy resin joint sealant
10. Concrete Washouts
11. Concrete Restoration work as a result of dam zge from other trades
12. Vapor barrier repair due to dam zge from other trades
13. M ockups(Can be done on T&M basis)other than above
14. Exposed Concrete/Polished Concrete/Colored Concrete/Shotcrete/Gunite
Contractor License#887235 * 1444 Fulton Street* Fresno,CA 93721 * 559-907-1068
15. Concrete Em b--dm eats
16. Concrete Hardener
17. Grouting other than m entioned above
18. Overtim eAcceleration/Nightwork
19. Waterproofing/Drainage System /Rigid/Batt Insulation/Flashing/Fireblocking
20. Sum ppit
21. Concrete Benches/Skate stops/Caulking of joints/Truncated Dom ES/Gutter
22. Use of Jackham m es/Breakers to rem cve unforeseen rocks, boulders,etc.during excavation
23. Suspended Slab/Beam /Concrete over m Etal deck
24. Electrical/M echanical/Plum Ling/Landscaping Concrete Pads
V&G Builders, Inc.reserves the right to cancel concrete pours for inclem eit weather,(dry,excessive
heat,rain,or wind)and is not responsible for any delay caused by circum stances outside its control.
Weather cancellations will be considered an excusable delay and will not be subject to prem iam
m akeup or dam ages.
This Proposal is for the work herein only and no other work is included or im died.
If you have any questions,please contact us.
Respectfully,
Carlos Gonzalez
V&G Builders, Inc.
2
X14 Bollard Footings 12"Dia X 35"D SHO RI LO PD FEE C oncrete 1 .44 2 40.00 $ 345.60 $0.00
56 LF Forms FormsZxl2 4 5.00 $ 220.00
0.00 $ 0.00
0.00 $ 0.00 $0.00
0.00 $ 0.00
0.001 i $0.00 1 $0.00
Total Materials $ 565.60 1 $0.00
Equipment
Item Ltal Credit _jl
750 Skidsteer 3 H6.92 8 rs $ 295.36 $0.00
Auger 3 00 1 $ 300.00 $0.00
F450 3 6.92 2 2 HR$ 812.24 $0.00
F150 2 5.14 2 2 HR$ 553.08 $0.00
$0.00 $0.00
Total Equipme $1,960.68 $0.00
Layout 0.20 H son Foreman 5.18 21 ncluded in LR$ 190.36
0.25Q1 em ent Mason 8 5.36 21 ncluded in LR$ 170.72
0 01 ncluded in LR$ 0.00
Excavation 1 son Foreman 9 5.18 81 ncluded in LR$ 761.44
C 1 2 ement Mason 8 5.36 1 6 1 ncluded in LR$ 1,365.76
0 01 ncluded in LR$ 0.00
Formwork 0 z M 1 son Foreman 5.18 41 ncluded in LR$ 380.72
0.6 2 ement Mason 8 5.36 81 ncluded in LR$ 682.88
0 01 ncluded in LR$ 0.00
Pour Concrete 1 son Foreman 9 5.18 81 ncluded in LR$ 761.44
C 1 3 ement Mason 8 5.36 2 4 1 ncluded in LR$ 2,048.64
0 01 ncluded in LR$ 0.00
Strip/Cleanup 0 .6 ement Mason 8 5.36 81 ncluded in LR$ 682.88
0 01 ncluded in LR$ 0.00
80 T otal Labor $7,044.84 $0.00
Subtotal $9,571.12 $0.00
Contractor Subtotal $ 9,571.12
10%C ontractor O P $957.11
Total $10,528.23
Subtotal $ 10,528.23
0% G L $ 0.00
Project Time Impact 3.25 Days T otal $ 10,528.23
LS 1
Unit Price $ 10,528.23
Price Quotation # B461278
FEL CLOVIS #1100
300 PARKCREEK DRIVE
CLOVIS,CA 93611
Phone:559-442-3333
Fax:559-325-9617
Bid No.......: B461278
Bid Date...: 07/19/22 Cust Phone:
Quoted By: MJD Terms.........: CASH ON DEMAND
Customer.: ****CASH SALE-#1100**** Ship To.......: CUSTOMER PICK-UP
DO NOT MAIL
300 PARKCREEK DRIVE
CLOVIS,CA 93611
Cust PO#..: BOLLARD QUOTE Job Name.: BOLLARD QUOTE
Item Description Quantity Net Price UM Total
FIGP80SLVCAP 4X80 T X PE RMV POST W/CAP 3 267.120 EA 801.36
FIGP80TXPECAP 4X80 GALV T X PE NIP W/CAP 11 F 163.240 EA 1 1795.64
Subtotal: $2597.00
Inbound Freight: $0.00
Tax: $207.11
Order Total: $2804.11
Quoted prices are based upon receipt of the total quantity for immediate shipment(48 hours).SHIPMENTS
BEYOND 48 HOURS SHALL BE AT THE PRICE IN EFFECT AT TIME OF SHIPMENT UNLESS NOTED OTHERWISE.
QUOTES FOR PRODUCTS SHIPPED FOR RESALE ARE NOT FIRM UNLESS NOTED OTHERWISE.
CONTACT YOUR SALES REPRESENTATIVE IMMEDIATELY FOR ASSISTANCE WITH DBE/MBE/WBE/SMALL BUSINESS
REQUIREMENTS.
Seller not responsible for delays, lack of product or increase of pricing due to causes beyond our control,and/or
based upon Local,State and Federal laws governing type of products that can be sold or put into commerce.This
Quote is offered contingent upon the Buyer's acceptance of Seller's terms and conditions,which are
incorporated by reference and found either following this document,or on the web at
https://www.ferguson.com/content/website-info/terms-of-sale.Govt Buyers:All items quoted are open market
unless noted otherwise.
LEAD LAW WARNING: It is illegal to install products that are not"lead free" in accordance with US Federal or
other applicable law in potable water systems anticipated for human consumption. Products with *NIP in the
description are NOT lead free and can only be installed in non-potable applications. Buyer is solely responsible
for product selection.
WATER FLOW RATE NOTICE: Lavatory Faucets with flow rates over 0.5 GPM are not allowed for'public use' in
California.
COVID-19 ORDER:ANY REFERENCE TO OR INCORPORATION OF EXECUTIVE ORDER 14042 AND/OR THE EO-
IMPLEMENTING FEDERAL CLAUSES(FAR 52.223-99 AND/OR DFARS 252.223-7999) IS EXPRESSLY REJECTED BY
SELLER AND SHALL NOT APPLY AS SELLER IS A MATERIALS SUPPLIER AND THEREFORE EXEMPT UNDER THE
EXECUTIVE ORDER.