HomeMy WebLinkAbout19-S-04 CCO 071.1.pdf CO County of Fresno
C �,5 Department of Public Works and Planning
O� S O Development Services&Capital Projects Division
ES� Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 7/25/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#071.1
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Underground Conduits ASI#3
Relocate panels(1 LM,1 HA, 1 LA)to new layout in the electric room of the Substation
Attachment(s):
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $17,372.89
Net Additive Calendar Days: �p
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: ��
Total Change Order Dollar Amount To Date $213,264.38
Adjusted Contract Dollar Amount: $11,577,764.38
Total Adjusted Calendar Days To Date: 74
Director's Change Order Limit Balance: 1 -$3,264.38
Adjusted Construction Completion Date: 1 12/09/21
Reviewed: Roger Davidson
o(,�.2,291;11 39P91)
Arc�hitenct
Reviewed: LaRue Goossen
Project Manager
r
Reviewed: Mandeep S. Sekhon N!--,
Construction Manager
Reviewed: William M.Kettler -
Division Manager
Approved: Steven E. White s E whzr a-
M1lte(lul 2,2022 09-49 Ppi)
Dire for
Approved: Brian Pacheco
Board of Supervisors Chairman S
Approval Date:
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriff's Office Thomas Trester
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
h CO County of Fresno
ru' Department of Public Works and Planning
O 83 O Development Services&Capital Projects Division
FRESH Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 7/25/2022
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#071.1
Construction Contract Dollar Amount(as awarded on 08/10120): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#071.1 is hereby approved by the County.
Change Order Scope of Work:
Underground Conduits ASI#3
Relocate panels(1 LM, 1 HA, 1 LA)to new layout in the electric room of the Substation
Attachment:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $17,372.89
Net Additive Calendar Days: �p
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: �p
Total Change Order Dollar Amount To Date: $213,264.38
Adjusted Contract Dollar Amount: $11,577,764.38
Total Adjusted Calendar Days To Date: 74
Adjusted Construction Completion Date: 12/09/21
LaRue Goossen LaRue Goossen(Jul 25,202215:26 PDT)
Project Manager Signature
Date: Jul 25,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material.labor and services required to complete the Scope of Work specified in
this Change Order.
2. The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
Accepted By: Klassen Corporation Rod Paine(Jul 25,202215:30 PDT)
Authorized Signature
Date: Jul 25,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
r
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 $91,000.00 5 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
CGO 009 - N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 $572,775.76 0 Storage Bldg.electric
CCO 012 $32,245.91 0 Substation electrical
CCO 013 $112,372.79 0 Electrical plan update
CCO 014 $7,444.00 0 Blockout revised data room
CCO 015 $14,657.00 0 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020 12/14/2021 $2,794.26 0 Fab.&Install metal sill flashing
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
CCO 022 - N/A
CCO 023 12/14/2021 $3,093.25 0 Plumbing alterations per ASI 2&3
CCO 024 12/14/2021 $795.79 0 Revised Architecturals
CCO 025 11/22/2021 $8,355.00 0 Install Overflow pipe minus penetration of gutter
CCO 026 $0.00 56 Metal Building Delay#1
CCO 027 12/29/2021 $4,486.63 0 Fur out West Exterior Wall
CCO 028 12/29/2021 $2,097.75 0 Hardware changes from rev.in dwgs.ASI 7
CCO 029 $12,487.64 1 Reroute 2.5'and 3"fire mains per RFI 64
CCO 030 $71,190.79 0 Overhead door material price increase
CCO 031 12/29/2021 $10,008.10 0 Ceramic tile alterations
CCO 032 12/29/2021 $6,806.50 0 Add.Recessed TV and Databoxes
CCO 033 1/19/2022 $3,212.39 0 Tower Closure Strips
CCO 034 12/29/2021 $3,261.63 0 Provide power&connection to(5)hand dryers
CCO 034.1 $1,784.20 0 Provide power&connection to(5)hand dryers r2
CCO 034.2 7/5/2022 $1,784.20 0 Provide power&connection to(5)hand dryers r3
CCO 035 12/29/2021 -$5,345.00 0 ASI to omit interior stone veneer and finish gyp board
CCO 036 $38,224.99 0 Alternate Sectional Doors
CCO 037 - N/A
CCO 038 6/28/2022 28 Extended site rain/mud delays
CCO 039 - N/A
CCO 040 1/18/2022 $5,557.64 0 Lighting for Sheriff Star
CCO 041 $267,768.79 0 Data Rack Revisions
CCO 041.5 6/20/2022 $66,691.06 15 Switchgear to 2000/Data Center Revisions
CCO 042 $7,334.25 0 Additional sunshade
CCO 043 3/30/2022 $3,633.89 0 Supply and Install"B"metal angle
CCO 044 2/16/2022 $3,352.40 0 Electrical for TV boxes
CCO 045 0 N/A
CCO 046 4/25/2022 $9,397.07 0 Submittal changes-Door hardware
CCO 047 3/8/2022 $3,082.34 0 Additional metal studs per new arch drawings
CCO 048 $53,421.75 - CE#068-Rule 16
CCO 048.1 6/10/2022 $44,855.53 0 CE#068-Rule 16
CCO 049 6/20/2022 $11,371.85 0 Install block wall
CCO 050 3/30/2022 $14,385.40 0 Tower and Entry Fascia Revision
CCO 051 4/8/2022 $4,459.67 0 Added circuits to IDU Units
CCO 052 - N/A
CCO 053 - N/A
CCO 054 4/20/2022 -$114.65 0 Delete Waste Dispensers&Add Hand Dryers
CCO 055 $71,905.65 0 Delayed lighting package order-ASI#03
CCO 056 6/28/2022 -$473.00 0 Memorial CMY wall alteration
CCO 057 4/22/2022 $3,054.20 0 Power&Connection to plumbing fixtures TP-1
CCO 058 6/28/2022 $308.85 0 Circulating pump power
CCO 059 - N/A
CCO 060 - N/A
CCO 061 $13,898.70 0 ASI 04-21-2022-01 Tower revisions
CCO 062 $8,108.54 - N/A
CCO 063 5/3/2022 $1,079.04 0 Install 6 footing sleeves
CCO 064 - N/A
CCO 065 - N/A
CCO 066 5/24/2022 $837.38 0 Cleanout relocation by TEV transformer
CCO 067 5/3/2022 $1,052.06 0 Additional CMU at removed gate
CCO 068 - N/A
CCO 069 6/17/2022 $5,468.33 1 Enlarged mechanical pad
CCO 070 - N/A
CCO 070.1 7/5/2022 j $2,946.78 0 Electrical room lighting
CCO 071.1 7/25/2022 I $17,372.89 I 0 Underground conduits
Totals $380,697.03 -$167,432.65 $1,289,922.22 $72,255.10 74
K PCCO #071 .1
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno, California 93727
Phone:(661)324-3000 Phone:
Fax: (661)324-3900 Fax:
Prime Contract Change Order #071 .1 : ASI #3 - Underground Conduits
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 7/14/2022 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 1
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $ 17,372.89
DESCRIPTION:
CE#105-ASI#3-Underground Conduits Storage
ATTACHMENTS:
CO#2 Substation Underground Relocations.pdf Sheriff Area 2 Substation Elec 2021-01-22 SI Plans-LAPTOP-2SAT4V36.Ddf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# Title Schedule Impact Amount
070 1 CE#105-ASI#3-Underground 17,372.89
TOTAL: $17,372.89
CHANGE ORDER LINE ITEMS:
PCO#070:CE#105-ASI#3-Underground
# Cost Code Description Type Amount
1 16-100-Electrical Subcontractor $15,456.31
Subtotal: $15,456.31
Fee:10.00%Applies to all line item types. 1,545.63
Insurance:1.40%Applies to all line item types. 216.39
Bond:1.00%Applies to all line item types. 154.56
Grand Total: $17,372.89
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 425,935.88
The contract sum prior to this PCCO was $ 11,790,435.88
The contract sum would be changed by this PCCO in the amount of $ 17,372.89
The new contract sum including this PCCO will be $ 11,807,808.77
The contract time will not be changed by this PCCO
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On:7/14/2022 10:29 AM
Electrical PowerSource ELECTRICAL
5796 S Elm Ave
Fresno, CA 93706
559-268-2861 LICENSE NUMBER 896863
Change Order #2 (Substation) Rev. 1
BILL TO INVOICE#20-087-2
Klassen Corp. DATE: 7.1 3.2 0 2 2
2021 Westwind Dr. TERMS Due on receipt
Bakersfield, Ca 93301
559-342-3000
DESCRIPTION AMOUNT
Labor: 83.22 hr. $6,696.71
Material Handling: $35.00
Estimating: $75.00
Total: $6,806.71
Description:
- Relocate panels (1 LM, 1 HA, 1 LA)to new lay out in the electric room of the
Substation.
Materials: $4,228.91
- 1" PVC Conduit w/fittings &wire
- 1-1/2" PVC Conduit w/fitting &wire
-2" PVC Conduit w/fittings
-4" PVC Conduit w/fittings
Equipment: $3,015.57
- Mini Ex (1 Week rental)
- Mini Ex compaction wheel (1 week)
- 24" mini ex bucket (1 week)
- Skid Steer to remove spoils (one day)
- Water Buffalo (Week rental)
Exclusion:
- Future Panels, Transformers & Disconnects
- Future Conduits and Wire for future panels
Overhead/Profit 10% $1,405.12
Change Order $15,456.31
7/13/2022 7:49:30 AM Electrical Power Source Inc. Page 1
Phone:559-268-2861 Fax:559-233-2414
Fresno County Substation :CO#002
Totals(Detailed)-Bid Summary: Default
Job Number CO300-2
Bid Date 6/23/2020
Bid Time 7:43:00 AM
Square Footage 0
Material Totals
Division Total Factor Extended
01 Raceway, Fittings&Boxes $2,387.77 0.00% $2,387.77
06 Underground/Site 1,528.98 0.00% 1,528.98
Total $3,916.75 $3,916.75
Sales Tax(7.97%) $312.16
Total Material $4,228.91
Labor Hours
Division Total Factor Extended
01 Raceway, Fittings&Boxes 9.44 0.00% 9.44
06 Underground/Site 73.78 0.00% 73.78
Total 83.22 83.22
Labor Rates
Category %of Total Hours Base Rate Burden Burden% Extended
Journeyman 80.000 66.576 $83.11 0.00 0.000 $5,533.13
4th year 2nd trimester apprentice 20.000 16.644 69.93 0.00 0.000 1,163.91
Total 100.000 83.220 x $80.47 (average of labor rate w/burden)_ $6,697.05
Non-Productive Labor
Description Hours Rate Factor Extended
Material Handling 1.00 $35.00 0.00% $35.00
Estimating 1.00 75.00 0.00% 75.00
Total $110.00
Total Labor (85.22 hours) $6,806.71
Direct Job Expenses
Description Total
Backhoe(mini ex)/compaction wheel/24"bucket(1we $1,860.45
water buffallo 447.13
Skidsteer(one Day) 707.99
Total $3,015.57
7/13/2022 7:49:30 AM Electrical Power Source Inc. Page 2
Phone:559-268-2861 Fax:559-233-2414
Fresno County Substation :CO#002
Totals(Detailed)-Bid Summary: Default
Job Subtotal(Prime Cost) $14,051.19
Overhead(0.00%) 0.00
Profit(10.00%) 1,405.12
Job Total $15,456.31
Actual Bid Price $15,456.31
Material to Direct Labor ratio: 0.39
Prime Cost per square foot $0.00
Job Total per square foot $0.00
Actual Bid Price per square ft $0.00
Labor cost per square foot $0.00
Labor hours per square foot 0.00
Gross Profit% 9.09
Gross Profit$ $1,405.12
Net Profit% 9.09
7/13/2022 7:50:04 AM Page 1
Fresno County Substation :CO#002
Item# Description Quantity Price Ext Price Labor Ext Labor
8315 4"Schedule 80 Std 45'Elbow 12.00 151.88 E 1,822.56 0.00 E 0.00
1208 4"PVC(Difficult) 60.00 732.28 C 439.37 50.25 C 30.15
1191 1-1/2"PVC Conduit 180.00 195.92 C 352.66 4.25 C 7.65
1204 2"PVC(Difficult) 70.00 384.91 C 269.44 18.00 C 12.60
1352 2"GRC Elbow 4.00 6,605.23 C 264.21 1.00 E 4.00
1189 1"PVC Conduit 170.00 141.85 C 241.15 4.00 C 6.80
8311 1-1/2"Schedule 80 Std 45'Elbow 4.00 2,772.89 C 110.92 0.00 E 0.00
1351 1-112"GRC Elbow 2.00 4,575.07 C 91.50 0.75 E 1.50
1205 2-1/2"PVC(Difficult) 20.00 406.07 C 81.21 27.00 C 5.40
1349 1"GRC Elbow 2.00 2,689.63 C 53.79 0.50 E 1.00
2123 4"PVC Coupling 6.00 680.06 C 40.80 0.22 E 1.32
2118 1-112"PVC Coupling 20.00 128.34 C 25.67 0.12 E 2.40
1595 4"Locknut 2.00 1,199.75 C 24.00 0.53 E 1.06
2069 4"PVC Male Adaptor 2.00 1,012.95 C 20.26 0.80 E 1.60
2119 2"PVC Coupling 12.00 166.73 C 20.01 0.14 E 1.68
2116 1"PVC Coupling 20.00 68.88 C 13.78 0.08 E 1.60
1592 2-1/2"Locknut 2.00 584.09 C 11.68 0.33 E 0.66
2066 2-1/2"PVC Male Adaptor 2.00 407.22 C 8.14 0.40 E 0.80
2120 2-1/2"PVC Coupling 2.00 301.21 C 6.02 0.16 E 0.32
2065 2"PVC Male Adaptor 2.00 233.25 C 4.67 0.30 E 0.60
1591 2"Locknut 2.00 219.42 C 4.39 0.27 E 0.54
2064 1-112"PVC Male Adaptor 2.00 184.03 C 3.68 0.25 E 0.50
1590 1-1/2"Locknut 2.00 151.86 C 3.04 0.20 E 0.40
2062 1"PVC Male Adaptor 2.00 106.05 C 2.12 0.18 E 0.36
1588 1"Locknut 2.00 84.19 C 1.68 0.14 E 0.28
Cycle Bill Im*oice
Click here for official document cove
Branch Remit To
Ahern Fresno ?,hero Fresno
3i91 E Date Ave Po Box 271390
Fresno,CA 93725-1933 Las Vegas,N'V'89127-1390
559-495-4000 Phone 702-647-8100 Phone
559-495-6000 Fax
Bill To Job Site
Electrical Power Source Sherriffs Station
4637 S Eastrl,-e 1129 NArmstrone a,-e
Fresno,CA 93725-9361 Fresno,CA 9372'
559-268-2861 Phone 559-268-2861 Phone
Irv:nice Date: 04116 21
Invoice 3-: 23097825-0003
Billed From: 04;06 21
Bill Through: 05 0=:1
Job¢: sherriffs staticn
PO=: pen�i:ng
Ordered By: chad louse rd
Rental Items
Qty Equipment Alin Day il'eek Month amount
1.00 Trailer,i%*-ter.500 560GaLGar. 130.00 130.00 300.00 �S5.:"I_
Eqp=:..�_2I
� -46 117LIE EXT500S
Serial*5%=M320KP000099
HR Out_0.000
Cat-Class:550-9242
Sales Items
Qty \ffI- UI-M Price -�m.unt
1.00 160642 EA 8.78 S.-S
Environmental Charge
1.00 CA HEAVY EQUIPMENT RENTAL TAX EA 439 4.39
Ca Heavy Equipment Rental Tax
1.00 DEL 0.00 0.00
Delivery Charge
Subtotal: ?Si.00
Miscellaneous Charges: 1; 1-
Damage Waiver: 8'.75
Tax: 47.35
Total: '33.27
SW113J _ CYCLE INVOICE
Branch Location:
RENTALS
AHERN FRESNO
PO Box 271390 3591 E DATE AVE
Las Vegas,NV 89127-1390 FRESNO CA 93725-1933
Thank you for choosing Ahern Rentals.
Contact us at 800-589-6797.
Customer: Job Site:
ELECTRICAL POWER SOURCE SHERRIFFS STATION
4637 S EAST AVE 1129 N ARMSTRONG AVE
FRESNO CA 93725-9361 FRESNO CA 93727
Page 1 of 1
Customer# Invoice# Invoice Date Billed From Billed To Written By Sales Rep
314651 1 23097828-002 03/26/21 1 03/09/21 04/06/21 CHAD/LOUIE/RD LOUIE ORTIZ
Ordered By Job# P.O. # Terms
CHAD/LOUIE/RD SHERRIFFS STATION PENDING Net 10 Days
Qty Equipment Min Day Week 4 Week Amount
1 EXC 28HP 10'5"DIG 3.5T 5'1"WIDE 300.00 300.00 1 900.00 1900.00 1900.00
EQP#: 131941 Make: KUBOTA Model: KX91R1AS2
1 EXC BUCKET 18" KX033/71/91/121/U35/040 0.00 0.00 0.00 0.00 N/C
EQP#: 0158878
1 EXC BUCKET 24" KX033/71/91/121/U35/040 25.00 25.00 70.00 195.00 195.00
EQP#: 0158879
1 EXC ATTACH COMPWHEEL 16" 100.00 100.00 300.00 600.00 600.00
EQP#: 172968 Make: AMERI COMP Model: DC16SKH Ser #: 061615819
SALES ITEMS:
Item Number Qty Unit Price
160642 1 EA 28.50 28.50
ENVIRONMENTAL CHARGE
CA HEAVY EQUIPMENT RENTAL TAX 1 EA 20.21 20.21
CA HEAVY EQUIPMENT RENTAL TAX
Sub-total: 2743.71
Rental Protection Plan: 404.2
7.98% Tax: 217.2
Total: 3365.16
THIS DOCUMENT IS ISSUED SUBJECT TO THE TERMS AND CONDITIONS OF THE RENTAL OUT CONTRACT, AND THE GENERAL TERMS AND
CONDITIONS OF SALE OF GOODS AND/OR SERVICES,AS APPLICABLE. ALL SUCH FOREGOING TERMS AND CONDITIONS ARE INCORPORATED
HEREIN BY REFERENCE, AS APPLICABLE. COPIES OF THE TERMS AND CONDITIONS OF THE RENTAL OUT CONTRACT,AND THE GENERAL
TERMS AND CONDITIONS OF SALE OF GOODS AND/OR SERVICES ARE AVAILABLE UPON REQUEST
PLEASE VISIT US ONLINE AT WWW.AHERN.COM TO SUBMIT A PAYMENT
or send payments to PO BOX 271390, LAS VEGAS, NV 89127-1390
SW113J _ CYCLE INVOICE
Branch Location:
RENTALS
AHERN FRESNO
PO Box 271390 3591 E DATE AVE
Las Vegas,NV 89127-1390 FRESNO CA 93725-1933
Thank you for choosing Ahern Rentals.
Contact us at 800-589-6797.
Customer: Job Site:
ELECTRICAL POWER SOURCE SHERRIFFS STATION
4637 S EAST AVE 1129 N ARMSTRONG AVE
FRESNO CA 93725-9361 FRESNO CA 93727
Page 1 of 1
Customer# Invoice# Invoice Date Billed From Billed To Written By Sales Rep
314651 1 23406655-001 05/13/21 1 04/27/21 05/25/21 CHAD/LOUIEO/JHB LOUIE ORTIZ
Ordered By Job# P.O. # Terms
CHAD/LOUIEO/JHB SHERRIFFS STATION NONE Net 10 Days
Qty Equipment Min Day Week 4 Week Amount
1 SKIDSTEER 42-60HP 1/2YD 1500-1950LB 275.00 275.00 700.00 1685.00 1685.00
EQP#: 158629 Make: JOHN DEERE Model: 318E Ser #: 1T0318EACF]286536
1 SKIDSTEER BUCKET 66" 0.00 0.00 0.00 0.00 N/C
EQP#: 0258950
SALES ITEMS:
Item Number Qty Unit Price
160642 1 EA 25.28 25.28
ENVIRONMENTAL CHARGE
CA HEAVY EQUIPMENT RENTAL TAX 1 EA 12.64 12.6
CA HEAVY EQUIPMENT RENTAL TAX
1 EA 90.00 90.00
DELIVERY CHARGE
10 Get 24/7 access to everything you need. Make secure payments, go paperless, download invoices into your ERP, avoid
duplicate payments, get faster lien releases, and much more!Sign up today for Ahern Access to easily manage your
account from a single portal at www.AhernAccess.com
Sub-total: 1812.92
Rental Protection Plan: 252.75
7.98% Tax: 143.58
Total: 2209.25
THIS DOCUMENT IS ISSUED SUBJECT TO THE TERMS AND CONDITIONS OF THE RENTAL OUT CONTRACT, AND THE GENERAL TERMS AND
CONDITIONS OF SALE OF GOODS AND/OR SERVICES,AS APPLICABLE. ALL SUCH FOREGOING TERMS AND CONDITIONS ARE INCORPORATED
HEREIN BY REFERENCE, AS APPLICABLE. COPIES OF THE TERMS AND CONDITIONS OF THE RENTAL OUT CONTRACT,AND THE GENERAL
TERMS AND CONDITIONS OF SALE OF GOODS AND/OR SERVICES ARE AVAILABLE UPON REQUEST
PLEASE VISIT US ONLINE AT WWW.AHERN.COM TO SUBMIT A PAYMENT
or send payments to PO BOX 271390, LAS VEGAS, NV 89127-1390