HomeMy WebLinkAbout19-S-04 CCO 045.3.pdf CO� County of Fresno
t �'+ Department of Public Works and Planning
Development Services&Capital Projects Division
FRESc' Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 7/25/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#045.3
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work: -
CE#062-AS[01-18-2022-01
Extra Work at force account for the month of June.
Attachment(s):
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $57,595.32
Net Additive Calendar Days: �p
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �p
Total Change Order Dollar Amount To Date $332,362.39
Adjusted Contract Dollar Amount: $11,696,862.39
Total Adjusted Calendar Days To Date: gp
Director's Change Order Limit Balance: -$122,362.39
Adjusted Construction Completion Date: 12/15/21
Reviewed: Roger Davidson
9
Architect
Reviewed: LaRue Goossen `p I `
Project t"Manager
Reviewed. Mandeep S. Sekhon -
Construction Manager
Reviewed. William M. Kettler
Division Manager
Approved: Steven E. White sr-vott,F WA4,&-
4 � PDT)
Dir for
Approved.' Brian Pacheco a.OL
Board of Supervisors Chairman
Approval Date: S E P 0 1 2*02.�,
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriff's Office Thomas Trester
PWP Business Office Jamie Sylvester
Staff Analyst Linda Guerra
coo� County of Fresno
+ Department of Public Works and Planning
O S O Development Services&Capital Projects Division
E9� Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 7/25/2022
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#045.3
Construction Contract Dollar Amount(as awarded on 08110/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#045.3 is hereby approved by the County.
Change Order Scope of Work:
CE#062-ASI 01-18-2022-01
Extra Work at force account for the month of June.
Attachment:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $57,595.32
Net Additive Calendar Days:
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days:
Total Change Order Dollar Amount To Date: $332,362.39
Adjusted Contract Dollar Amount: $11,696,862.39
Total Adjusted Calendar Days To Date: g0
Adjusted Construction Completion Date: 12/15/21
LaRue Goossen LaRue Goossen(Jul 25,2022 16:50 PDT)
Project Manager Signature
Date: Jul 25,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following.
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2. The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 15-S-05,
Article VI shall apply.
IFoRI�ar�r2
Accepted By., K/assen Corporation Rod Paine(Aug 1,2022 07:48 PDT)
Authorized Signature
Date: Aug 1,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
.. D. Days Description
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 $91,000.00 5 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
CGO 009 - N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 $572,775.76 0 Storage Bldg.electric
CCO 012 $32,245.91 0 Substation electrical
CCO 013 $112,372.79 0 Electrical plan update
CCO 014 $7,444.00 0 Blockout revised data room
CCO 015 $14,657.00 0 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020 12/14/2021 $2,794.26 0 Fab.&Install metal sill flashing
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
CCO 022 - N/A
CCO 023 12/14/2021 $3,093.25 0 Plumbing alterations per ASI 2&3
CCO 024 12/14/2021 $795.79 0 Revised Architecturals
CCO 025 11/22/2021 $8,355.00 0 Install Overflow pipe minus penetration of gutter
CCO 026 $0.00 56 Metal Building Delay#1
CCO 027 12/29/2021 $4,486.63 0 Fur out West Exterior Wall
CCO 028 12/29/2021 $2,097.75 0 Hardware changes from rev.in dwgs.ASI 7
CCO 029 $12,487.64 1 Reroute 2.5'and 3"fire mains per RFI 64
CCO 030 $71,190.79 0 Overhead door material price increase
CCO 031 12/29/2021 $10,008.10 0 Ceramic tile alterations
CCO 032 12/29/2021 $6,806.50 0 Add.Recessed TV and Databoxes
CCO 033 1/19/2022 $3,212.39 0 Tower Closure Strips
CCO 034 12/29/2021 $3,261.63 0 Provide power&connection to(5)hand dryers
CCO 034.1 $1,784.20 0 Provide power&connection to(5)hand dryers r2
CCO 034.2 7/5/2022 $1,784.20 0 Provide power&connection to(5)hand dryers r3
CCO 035 12/29/2021 -$5,345.00 0 ASI to omit interior stone veneer and finish gyp board
CCO 036 $38,224.99 0 Alternate Sectional Doors
CCO 037 - N/A
CCO 038 6/28/2022 28 Extended site rain/mud delays
CCO 039 - N/A
CCO 040 1/18/2022 $5,557.64 0 Lighting for Sheriff Star
CCO 041 $267,768.79 0 Data Rack Revisions
CCO 041.5 6/20/2022 $66,691.06 15 Switchgear to 2000/Data Center Revisions
CCO 042 $7,334.25 0 Additional sunshade
CCO 043 3/30/2022 $3,633.89 0 Supply and Install'B"metal angle
CCO 044 2/16/2022 $3,352.40 0 Electrical for TV boxes
CCO 045 0 N/A
CCO 045.3 7/25/2022 $57,595.32 0 Extra work at force ace.for June
CCO 046 4/25/2022 $9,397.07 0 Submittal changes-Door hardware
CCO 047 3/8/2022 $3,082.34 0 Additional metal studs per new arch drawings
CCO 048 $53,421.75 - CE#068-Rule 16
CCO 048.1 6/10/2022 $44,855.53 0 CE#068-Rule 16
CCO 049 6/20/2022 $11,371.85 0 Install block wall
CCO 050 3/30/2022 $14,385.40 0 Tower and Entry Fascia Revision
CCO 051 4/8/2022 $4,459.67 0 Added circuits to IDU Units
CCO 052 - N/A
CCO 053 - N/A
CCO 054 4/20/2022 -$114.65 0 Delete Waste Dispensers&Add Hand Dryers
CCO 055 $71,905.65 0 Delayed lighting package order-ASI#03
CCO 056 6/28/2022 -$473.00 0 Memorial CMY wall alteration
CCO 057 4/22/2022 $3,054.20 0 Power&Connection to plumbing fixtures TP-1
CCO 058 6/28/2022 $308.85 0 Circulating pump power
CCO 059 - N/A
CCO 060 - N/A
CCO 061 $13,898.70 0 ASI 04-21-2022-01 Tower revisions
CCO 062 $8,108.54 - N/A
CCO 063 5/3/2022 $1,079.04 0 Install 6 footing sleeves
CCO 064 - N/A
CCO 065 - N/A
CCO 066 5/24/2022 $837.38 0 Cleanout relocation by TEV transformer
CCO 067 5/3/2022 $1,052.06 0 Additional CMU at removed gate
CCO 068 $75,413.07 6 N/A
CCO 068.1 $75,413.07 7 Courtyard Revisions
CCO 068.2 7/25/2022 $61,502.69 6 Courtyard Revisions
CCO 069 6/17/2022 $5,468.33 1 Enlarged mechanical pad
CCO 070 - N/A
CCO 070.1 7/5/2022 $2,946.78 0 Electrical room lighting
CCO 071.1 7/25/2022 $17,372.89 0 Underground conduits
Totals $499,795.04 -$167,432.65 $1,440,748.36 $72,255.10 80
I!
PCCO #045.3
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno, California 93727
Phone:(661)324-3000 Phone:
Fax: (661)324-3900 Fax:
Prime Contract Change Order #045.3: Extra Work at Force Account for
June - ASI 01 -18-2022-01
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED 7/20/2022 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-Proceeding REVISION: 3
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $ 57,595.32
DESCRIPTION:
CE#062-ASI 01-18-2022-01
Extra Work at Force Account for the month of June.
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
045 1 Extra Work at Force Account-ASI 01-18-2022-01 57,595.32
TOTAL: $57,595.32
CHANGE ORDER LINE ITEMS:
PCO#045: Extra Work at Force Account-ASI 01-18-2022-01
# Cost Code Description Type Amount
1 16-100-Electrical Subcontractor $51,241.39
Subtotal: $51,241.39
Fee:10.00%Applies to all line item types. 5,124.14
Insurance:1.40%Applies to all line item types. 717.38
Bond:1.00%Applies to all line item types. 512.41
Grand Total: $57,595.32
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 354,444.70
The contract sum prior to this PCCO was $ 11,718,944.70
The contract sum would be changed by this PCCO in the amount of $ 57,595.32
The new contract sum including this PCCO will be $ 11,776,540.02
The contract time will not be changed by this PCCO
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On:7/21/2022 09:35 AM
Electrical PowerSource ELECTRICAL
5796 S Elm Ave
Fresno, CA 93706
559-268-2861 LICENSE NUMBER 896863
Forced Work June 2022 Rev. 1
BILL TO INVOICE#
Klassen Corp. DATE 07.19.2022
2021 Westwind Dr. TERMS Due on receipt
Bakersfield, Ca 93301
559-342-3000
DESCRIPTION AMOUNT
Forced Work Labor, equipment& Material breakdown for the month of June.
Ahern Sheet is for reference only. Equipment section is based on the Ahern
sheet provided and already calculated into the excel sheet.
Labor and equipment:
1. 6.13.2022 $1,519.73
2. 6.14.2022 $696.72
3. 6.15.2022 $1,331.00
4. 6.16.2022 $1,443.41
5. 6.17.2022 $852.65
6. 6.21.2022 $672.24
7. 6.22.2022 $800.86
Total Cost: $7,316.61
Description:
1. 6.13.2022
Exposed 2" conduit for EV charging power. Trench for 4" conduit at vault
location.
2. 6.14.2022
Expose 2" conduit for EV charging power. Trench for 4" conduit at vault
location.
3. 6.15.2022
Trench in between buildings for 4" conduit.
4. 6.16.2022
Provided trench to electrical room for 4" spare conduit for solar. (Not done yet)
Provided trench for EV charger(not done yet)
Cut trench to 3x5 box to main conduit bank on the west side of substation
5. 6.17.2022
Trenched to center of the site for Power and data.
6. 6.21.2022
Trench to center of the site for Power and data.
Repair 4" conduit
Installed 120' of 1" PVC
Trenched Lighting run on the south side of building
7. 6.22.2022
Trenched to center of the site for power and data
Trenched joint trench
Installed 1" conduit
Repaired conduit
Trench layout
Material:
1. Please see attached receipts for all material
a. S105627613.0001 $2,032.35
b. S105628336-0001 $9,705.97
c. S105629055-0001 $32,186.46
d. Total: $43,924.78
Equipment:
1. Backhoe cost included in labor section above.
See Labor breakdown for cost.
Labor Cost: $7,316.61
Material Cost: $43,924.78