CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING AVENUE CHANGE ORDER NO. 05
3 MILES EAST OF COLORADO AVENUE MAY 2, 2022
FEDERAL AID NUMBER: BRLS-5942(233) PAGE 1 OF 2
CONTRACT NO. 20-15-C
TO: VIKING CONSTRUCTION COMPANY, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), TWO (2) -WORKING DAYS will be added to the contract time.
REPLACE EXISTING DAMAGED ASPHALT CONCRETE SURFACING — EXTRA WORK
This extra work was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, replace
approximately 1,005 square yards of the existing damaged asphalt concrete surfacing to a 4-inch depth, at the
locations marked by the engineer (between the two bridges). Perform this work in accordance with Section 39-
3.02, "Replace Asphalt Concrete Surfacing," of the Special Provisions with the following revisions: Section 39-
3.02C Construction — 1) the hot mix asphalt (HMA) depth 4-inches in all locations, and can be paved back in
one lift; 2) the minimum width 6-inches, and the cold planed material becomes the property of the contractor
and to be disposed of; 3) the payment is made at $220 per ton of HMA as an agreed unit price according to
Section 9-1.03, "Payment Scope," of the Special Provisions. This agreed unit price includes compensation of
all labor, materials, equipment, overhead costs, markups, and incidentals for performing this work. The
estimated quantity for this work resulted in 215 tons, and the total estimated cost resulted in (215 tons x $220
per ton = $47,300) $47,300. The actual payment will be made as extra work based on the actual quantity used
in the field, a subsequent change order will be executed to reflect any changes.
Two (2) working days will be added to the allotted contract time and to the road closure timeline.
NET COST THIS CHANGE ORDER: A $47,300 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: TWO (2) -WORKING DAYS
NET ROAD CLOSURE TIME EXTENSION THIS CHANGE ORDER: TWO (2) -WORKING DAYS
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business Office noted above, and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING AVENUE CHANGE ORDER NO. 05
3 MILES EAST OF COLORADO AVENUE MAY 2, 2022
FEDERAL AID NUMBER: BRLS-5942(233) PAGE 2 OF 2
CONTRACT NO. 20-15-C
Richard Stockwell(May 2,2022 14:18 PDT)
Richard Stockwell, Resident Engineer
VIKING CONSTRUCTION COMPANY, INC.
Contractor Mandeep S. Sekhon, PE
Interim Construction Engineer
By Troy(`Cemons(May 5,2022 13:49 PDT) APPROVED BY:
Digitally signed by Steve White
Vice President Steve White Date:2022.05.0616:33:15
Title -07'00'
Steven E. White, Director
May 5,2022 Public Works and Planning
Accepted Date:
Date:
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.