HomeMy WebLinkAbout2015C CCO 04.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING AVENUE CHANGE ORDER NO. 04
3 MILES EAST OF COLORADO AVENUE MARCH 4, 2022
FEDERAL PROJECT NUMBER: BRLS-5942(233) PAGE 1 OF 2
CONTRACT NO. 20-15-C
TO: VIKING CONSTRUCTION COMPANY, INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), SIXTY-ONE (61) -WORKING DAYS will be added to the contract
time.
GRANT A TIME EXTENSION TO THE SECOND ORDER OF WORK
This time extension was requested by the contractor.
Grant a time extension of 61-working days to the Second Order of Work due to changes in the critical path of
the project resulted from continuous construction through the flood season in lieu of a contract suspension,
according to Section 8-1.07B, "Time Adjustments," of the Special Provisions. In accordance with Section 8-
1.04C(2), "Second Order of Work," of the Special Provisions, "Multiple in-channel seasons may be required if
the Central Valley Flood Protection Board does not approve a time variance request and in-channel work has
not been completed within the time period defined in section 10-1.03." The CPM Baseline Schedule identified
a two-season construction schedule since it was unknown if the time variance permits (TVP) would be
approved. Since then, the Central Valley Flood Protection Board has approved the TVPs on a bi-weekly basis
to allow the work to proceed. This was not anticipated by the contractor at the start of construction, thus
changing certain critical path items on the baseline schedule. As identified (contractor letter dated February
11, 2022), the precast girders became the controlling critical path item, pushing the contract completion date
61-working days under a one-season work schedule. This time extension is being made at the contractor's
request, any additional manpower or materials needed, placement of such, will be absorbed by the contractor.
The contract time extension of 61-working days will be added with no additional compensation. This will not
change the allotted time for the road closure.
Contractor We,the above signed contractor,have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board of Supervisors
_Const.management therefore the prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
JAMES BYPASS BRIDGE REPLACEMENTS ON MANNING AVENUE CHANGE ORDER NO. 04
3 MILES EAST OF COLORADO AVENUE MARCH 4, 2022
FEDERAL PROJECT NUMBER: BRLS-5942(233) PAGE 2 OF 2
CONTRACT NO. 20-15-C
NET COST THIS CHANGE ORDER: $0.00 (NO COST)
NET TIME EXTENSION THIS CHANGE ORDER: 61-WORKING DAYS
RRhw-Gt cft Mg41g1G
Richard Stockwell(Mar 4,2022 12:22 PST)
Richard Stockwell, Resident Engineer
APPROVAL RECOMMENDED:
VIKING CONSTRUCTION COMPANY, INC.
Contractor Mandeep S. Sekhon, PE
Interim Construction Engineer
By Troy Cremons(Mar 7,202211:23PST) APPROVED BY:
Digitally signed by Steve White
Title
Vice President Steve White Oae:2022.03.0715:11:59
Steven E. White, Director
Mar 7,2022 Public Works and Planning
Accepted Date:
Date: March 7, 2022
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business Office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board of Supervisors
_Const.Management therefore the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.