HomeMy WebLinkAbout2020C CCO 07.pdf COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER AMERICAN AVE AND GOLDEN STATE BLVD CHANGE ORDER NO. 07 INTERSECTION IMPROVEMENTS AUGUST 23, 2022 CONTRACT NO. 20-20-C PAGE 1 OF 3 TO: AJ EXCAVATION, INC.: Make the following changes to the plans and specifications or do work not in the plans and specifications for this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time. INCREASE/DEGREASE ITEMS AT UNIT PRICES: This change was proposed the engineer. Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item quantities to the actual quantities used. Increased Items: Item Total No. Description Unit Quantity Price Amount oN 13 Remove Roadside Sign and Post EA 2.00 $110.00 $220.00 9.52 16 Remove Trees EA 1.00 $250.00 $250.00 1.09 25 Place Hot Mix Asphalt Dike (Type A) LF 78.00 $10.00 $780.00 10.54 29 Strom Drainpipe Slurry Cement CY 3.00 $250.00 $750.00 25.00 Backfill 46 Thermoplastic Traffic Stripe (6" LF 153.00 $1.65 $252.45 76.50 Yellow Diagonal) 48 Thermoplastic Pavement Markings SF 755.00 $4.25 $3,208.75 52.29 (Retroreflective) 49 Thermoplastic Traffic Stripe (Detail 12) LF 922.00 $0.50 $461.00 28.81 50 Thermoplastic Traffic Stripe (Detail LF 270.00 $2.20 $594.00 67.50 22) 51 Thermoplastic Traffic Stripe (Detail LF 910.00 $0.70 $637.00 21.67 25A) 52 Thermoplastic Traffic Stripe (Detail LF 306.00 $0.70 $214.20 4.04 27B) 53 Thermoplastic Traffic Stripe (Detail LF 25.00 $2.20 $55,00 3.13 29) 54 Thermoplastic Traffic Stipe (Detail LF 555.00 $1.35 $749.25 15.86 38) 55 Paint Traffic Stripe (Detail 39) LF 100.00 $0.66 $66.00 5.00 56 Paint Traffic Stripe (Detail 39A) LF 1350.00 $0.70 $945.00 136.36 59 Pavement Marker (Retroreflective EA 65.00 $5.50 $357.50 23.64 Type D) -Yellow 60 Pavement Marker (Retroreflective EA 30.00 $5.50 $165.00 12.00 Type G) -Clear Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is Auditor approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above, _Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the _ Board of supervisors _const.Management prices shown above. RE/Arch. Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER AMERICAN AVE AND GOLDEN STATE BLVD CHANGE ORDER NO. 07 INTERSECTION IMPROVEMENTS AUGUST 23, 2022 CONTRACT NO. 20-20-C PAGE 2 OF 3 TOTAL INCREASE: $9,705.15 Decreased Items: Item Total No. Description Unit Quantity Price Amount e/10 1 Supplemental Work (Price Index $ 26,860.79 $1.00 $26,860.79 -33.58 Fluctuation) 9 State Water Resources Control $ 95.00 $1.00 $95.00 -9.50 Board Notice of Intent Filling Fee 14 Remove Pavement Marker EA 24.00 $1.00 $24.00 -24.00 24 Hot Mix Asphalt (Type A 3/4" Grading) TON 967.50 $70.00 $67,725.00 -6.86 26 Place Hot Mix Asphalt Dike (Type E) LF 56.00 $8.00 $448.00 -9.46 31 Minor Concrete-Median Curb & LF 9.00 $36.00 $324.00 -3.08 Gutter 32 Minor Concrete- Median Cap (3" SF 1,902.00 $4.00 $7,608.00 -13.99 Thick) 44 Thermoplastic Traffic Stripe (12" LF 218.00 $3.25 $708.50 -87.20 White) 45 Thermoplastic Traffic Stripe (6" LF 37.00 $1.55 $57.35 -10.57 White Diagonal) 47 Thermoplastic Traffic Stripe (4" LF 696.00 $1.10 $765.60 -55.68 White Diagonal) TOTAL DECREASE: $104,616.24 Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is _Auditor approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above, _Business Office and perform all services necessary for the work above specified,and will accept as full payment therefore the Board of Supervisors prices shown above. _ Const.Management RE/Arch. Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. COUNTY OF FRESNO CONSTRUCTION MANAGEMENT CONTRACT CHANGE ORDER AMERICAN AVE AND GOLDEN STATE BLVD CHANGE ORDER NO. 07 INTERSECTION IMPROVEMENTS AUGUST 23, 2022 CONTRACT NO. 20-20-C PAGE 3 OF 3 NET COST THIS CHANGE ORDER: $94,911.09 DEREASE NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS ROBERT HENDRICKSON, Resident Engineer APPROVAL RECOMMENDED: AJ EXCAVATION, INC., Contractor MANDEEP S. SEKHON, PE .411�9 6_wlffgt-t Construction Engineer By: Alisa Emrnett(Aup 31,2022 12:39 PDT) Digitally signed by Steve White Steve White Date:2022.09.02 13:43:00 - President STEVEN E. WHITE, Director of Public Works Title: and Planning Aug 31, 2022 Accepted Date: Date: Contractor We,the above signed contractor,have considered the change proposed and hereby agree, if this proposal is Auditor approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above, _Business Office and perform all services necessary for the work above specified,and will accept as full payment therefore the _Board of Supervisors _Const.Management prices shown above. _RE/Arch. _Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the specifications as to proceeding with the ordered work and filing a written protest within the time therein specified. LETTER OF TRANSMITTAL - C.C.O. NO. 07 AUGUST 23, 2022 TO: STEVEN E. WHITE, DIRECTOR AMERICAN AVE AND GOLDEN STATE BLVD PUBLIC WORKS AND PLANNING INTERSECTION IMPROVEMENTS CONTRACT NO. 20-20-C ATTN: MANDEEP S. SEKHON CONSTRUCTION ENGINEER FROM: ROBERT HENDRICKSON, Resident Engineer STATUS OF FUNDS: Contract Items $ 3,148,584.00 Original Allotment $ 3,318,513.20 Dept. Furnished Materials $ 0.00 Supplemental Allotment $ 247,307.50 Previous CCO's $ 297,304.74 Total Allotment $ 3,565,820.70 This CCO $ (94,911.09) Obligated Funds $ 3,350,977.65 Total Obligated Funds $ 3,350,977.65 Unobligated Balance $ 214,843.05 DIRECTOR'S LIMIT to sign change orders is: $ 169,929.20 DESCRIPTION: Increase/decrease items at unit prices. WHY: Item quantities in the Bid Book and subsequent change orders are estimates only. This part adjusts item quantities to the actual quantities used. Bid Item No.1 - Supplemental Work (Price Index Fluctuation) decreased by 33.58 percent, reflecting the actual supplemental funds expended on this project. This bid item is exempt from the requirements of Section 9-1.06 "Changed Quantity Payment Adjustment," of the Standard Specifications. This bid item was decreased to reflect the actual use of the allocated funds, resulting in a decrease of$26,860.79. Bid Item No. 44 - Thermoplastic Traffic Stripe (12" White), decreased by 87.50 percent, reflecting the actual quantity placed. The contractor did not make a request for adjustment of the unit price; and the actual payable quantities were paid at the unit price, resulting in a decrease of$708.50. Bid Item No. 46 - Thermoplastic Traffic Stripe (6" Yellow Diagonal) increased by 76.50 percent, reflecting the actual quantity placed. Payment for the increased quantity in excess of 125 percent of the estimated quantity resulted in an amount of$169.95. Since the payment for the quantity in excess of 125 percent resulted in less than $5,000, no adjustment to the unit price was made as per Section 9-1.06, "Changed Quantity Payment Adjustment," of the Standard Specifications; and the increased quantity was paid at the unit price, resulting in an increase of$252.45. Bid Item No. 47 - Thermoplastic Traffic Stripe (4" White Diagonal) decreased by 55.68 percent, reflecting the actual quantity placed. The contractor did not make a request for adjustment of the unit price; and the actual payable quantities were paid at the unit price, resulting in a decrease of$765.60. LETTER OF TRANSMITTAL - C.C.O. NO. 07 AUGUST 23, 2022 Bid Item No. 48 - Thermoplastic Pavement Marking (Retroreflective) increased by 52.29 percent, reflecting the actual quantity placed. Payment for the increased quantity in excess of 125 percent of the estimated quantity resulted in an amount of$1,674.50. Since the payment for the quantity in excess of 125 percent resulted in less than $5,000, no adjustment to the unit price was made as per Section 9-1.06, "Changed Quantity Payment Adjustment," of the Standard Specifications; and the increased quantity was paid at the unit price, resulting in an increase of$3,208.75. Bid Item No. 49 - Thermoplastic Traffic Stripe (Detail 12) increased by 28.81 percent, reflecting the actual quantity placed. Payment for the increased quantity in excess of 125 percent of the estimated quantity resulted in an amount of$61. Since the payment for the quantity in excess of 125 percent resulted in less than $5,000, no adjustment to the unit price was made as per Section 9-1.06, "Changed Quantity Payment Adjustment," of the Standard Specifications; and the increased quantity was paid at the unit price, resulting in an increase of$461. Bid Item No. 50 - Thermoplastic Traffic Stripe (Detail 22) increased by 67.50 percent, reflecting the actual quantity placed. Payment for the increased quantity in excess of 125 percent of the estimated quantity resulted in an amount of$674. Since the payment for the quantity in excess of 125 percent resulted in less than $5,000, no adjustment to the unit price was made as per Section 9-1.06, "Changed Quantity Payment Adjustment," of the Standard Specifications; and the increased quantity was paid at the unit price, resulting in an increase of$594. Bid Item No. 56 - Paint Traffic Stripe (Detail 39A) increased by 136.36 percent, reflecting the actual quantity placed. Payment for the increased quantity in excess of 125 percent of the estimated quantity resulted in an amount of$771.75. Since the payment for the quantity in excess of 125 percent resulted in less than $5,000, no adjustment to the unit price was made as per Section 9- 1.06, "Changed Quantity Payment Adjustment," of the Standard Specifications; and the increased quantity was paid at the unit price, resulting in an increase of$945. All other changes in the bid item quantities are minor and within the normal deviations for this type of construction. HOW: Increased/decreased item quantities at unit prices according to Section 9-1.06, "Changed Quantity Payment Adjustments," of the Standard Specifications. COST: A $94,911.09 Decrease NET COST THIS CHANGE ORDER: $94,911.09 DECREASE NET TIME EXTENSION THIS CHANGE ORDER: ZERO — (0) WORKING DAYS