HomeMy WebLinkAbout2020C CCO 06.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE AND GOLDEN STATE BLVD CHANGE ORDER NO. 6
INTERSECTION IMPROVEMENTS MAY 11, 2022
CONTRACT NO. 20-20-C PAGE 1 OF 2
TO: AJ EXCAVATION INC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for this
contract. Because of the change(s), 2-WORKING DAYS will be added to the contract time.
BACKFILL AND GRADE DRAINAGE DITCH BETWEEN STA. 115+23 AND STA. 119+82 (AMERICAN
AVENUE) - EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, backfill and grade
the newly excavated drainage ditch along the northside of American Avenue between Sta. 115+23 and Sta.
119+82. Grade this area with a 4 to 1 slope and match to the original ground. Utilize surplus materials available
on site for backfill. Perform all work according to Section 19, "Earthwork," of the Standard Specifications and/or
Special Provisions, as directed by the Resident Engineer. Payment for this work will be made as extra work at an
agreed lump sum price of$12,077.28 according to Section 9-1.03, "Payment Scope," of the Special Provisions.
This price includes compensation of all labor, materials, equipment, overhead costs, markups, and incidentals for
performing the work, no additional compensation will be made thereafter. This amount will be paid through Bid
Item No. 2, Supplemental Work, with no net increase to the contract.
Two working days will be added to the contract time for this work.
Contractor We,the above signed contractor,have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
—Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE AND GOLDEN STATE BLVD CHANGE ORDER NO. 6
INTERSECTION IMPROVEMENTS MAY 11, 2022
CONTRACT NO. 20-20-C PAGE 2 OF 2
NET COST THIS CHANGE ORDER: $0.00 (PAID IN BID ITEM NO. 2)
NET TIME EXTENSION THIS CHANGE ORDER: TWO (2) -WORKING DAYS
,P.o6o.:.tyS�au�uc.�aoz
ROBERT HENDRICKSON, Resident Engineer
APPROVAL RECOMMENDED:
AJ EXCAVTION INC.
Contractor MANDEEP S. SEKHON, PE
Interim Construction Engineer
By Alisa Emmett(May 16,202212:12 PDT) APPROVED BY:
Digitally signed by Steve White
President Steve White Date:2022.05.24 10:53:41
Title -07'00'
STEVEN E. WHITE, Director
Public Works and Planning
May 16,2022
Accepted Date:
Date:
Contractor We,the above signed contractor,have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.