CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE AND GOLDEN STATE BLVD CHANGE ORDER NO. 5
INTERSECTION IMPROVEMENTS MARCH 23, 2022
CONTRACT NO. 20-20-C PAGE 1 OF 1
TO: AJ EXCAVATION INC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for this
contract. Because of the change(s), 23-WORKING DAYS will be added to the contract time.
GRANT A TIME EXTENSION
This time extension was requested by the contractor.
Grant a time extension of 23-working days according to Section 8-1.07B, "Time Adjustments," of the
Special Provisions due to the delays caused by the Union Pacific Railroad Company's subcontractor(Rail
Pro's)for completing their scheduled work.
NET COST THIS CHANGE ORDER: A$0.00 (NO COST)
NET TIME EXTENSION THIS CHANGE ORDER: 23 -WORKING DAYS
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
AJ EXCAVTION INC.
Contrac Mandeep S. Sekhon, PE
Interim Construction Engineer
APPROVED BY:
Digitally signed by Steve White
Steve White
Date:2022.03.29 14:34:51
Title D29JIA-AA -07'00'
Steven E. White, Director
Public Works and Planning
Accepted Date: �� JZ
Date:
Contractor We,the above signed contractor,have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified, and will accept as full payment therefore the
_Board of supervisors prices shown above.
_Const.Management
RE/Arch.
Design If the Contractor does not sign acceptance of this orders his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.