HomeMy WebLinkAbout2020C CCO 03.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE AND GOLDEN STATE BLVD CHANGE ORDER NO. 3
INTERSECTION IMPROVEMENTS JANUARY 25, 2021
CONTRACT NO. 20-20-C PAGE 1 OF 2
TO: AJ EXCAVATION INC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) -WORKING DAYS will be added to the contract time.
PART I: UPGRADE THE TRAFFIC SIGNAL BATTERY BACKUP SYSTEM — EXTRA WORK
This change was requested by the engineer.
According to Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, upgrade the battery
backup system to two (2) 500-watt ZincBlue or equal batteries for the traffic signal . The upgraded system shall
conform to the requirements of the Plans, Standard Specifications and/or the project Specifications. Payment
for this work will be made as extra work at an agreed lump sum price of$5,440.40, according to Section 9-
1.03, "Payment Scope," of the Special Provisions. The agreed lump sum price is the difference between the
actual cost of the upgraded battery backup system and the typical batter backup system ($11,940.40-
$6,500.00 = $5,440.40). This price includes compensation of all labor, materials, equipment, overhead costs,
markups, and incidentals associated with this change; no additional payment will be made.
This change did not impact the critical path of the project schedule, therefore, granting additional time was not
warranted.
TOTAL COST PART I: A $5,440.40 INCREASE
TOTAL TIME EXTENSION PART I: ZERO (0) -WORKING DAYS
PART II: FURNISH TWO (2) ADDITIONAL ACTIVATED LED BLANK-OUT SIGNS — EXTRA WORK
This change was requested by the engineer.
According to Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, furnish and provide to
the County a total of two (2) 30" x 24", Tapco (R3-1) and (R3-2) activated LED blank-out or equal signs
conforming the requirements of the Plans, Standard Specifications and/or the project Specifications. Payment
for this work will be made as extra work at an agreed lump sum price of$10,838, according to Section 9-1.03,
"Payment Scope," of the Special Provisions. This price includes compensation of all labor, materials,
equipment, overhead costs, markups, and incidentals associated with this change; no additional payment will
be made.
This change did not impact the critical path of the project schedule, therefore, granting additional time was not
warranted.
TOTAL COST PART II: A $10,838.00 INCREASE
TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS
Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment,furnish all materials, except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefor the
Board
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
AMERICAN AVENUE AND GOLDEN STATE BLVD CHANGE ORDER NO. 3
INTERSECTION IMPROVEMENTS JANUARY 25, 2021
CONTRACT NO. 20-20-C PAGE 2 OF 2
NET COST THIS CHANGE ORDER: A $16,278.40 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) -WORKING DAYS
ROBERT HENDRICKSON, Resident Engineer
APPROVAL RECOMMENDED:
A.J. EXCAVATION, INC.
Contractor
MANDEEP S. SEKHON, Interim Construction
W/fa 151ff#19a Engineer
Alisa Emmett(Jan 25,2022 16:35 PST)
St�rre-� E 1NGc�te-
Steven E White(Jan 25,2022 16:44 PST)
President STEVEN E. WHITE, Director of Public Works
Title: and Planning
Accepted Date: Jan 25' 2022 Date: Jan 25, 2022
Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment,furnish all materials, except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified, and will accept as full payment therefor the
Board
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.