HomeMy WebLinkAbout19S04 CCO 67.pdf County of Fresno
t Department of Public Works and Planning
O� O Development Services&Capital Projects Division
FI2E�'� Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 6/7/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#067
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Additional CMU at removed gate.
Attachment(s):
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $1,052.06
Net Additive Calendar Days: F0
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date $62,937.89
Adjusted Contract Dollar Amount: $11,427,437.89
Total Adjusted Calendar Days To Date: 30
Director's Change Order Limit Balance: $147,062.11
Adjusted Construction Completion Date: 10/26/21
Reviewed: Davidson ` d-(JunfOl1
Rogery rdandson(Jun 20,202207 47 PDT)
Architect
Reviewed: LaRue Goossen MAP-- 0,202 Da,
Project Manager
Reviewed: Mandeep S. SekhonS'S`E�
Construction Manager
Reviewed: William M. Kettler —
Division Manager
Approved: Steven E. White E SfaverL WLi4�
more(J- DTI
Director
Approved: Brian Pacheco NOTAPPLICABLE
Board of Supervisors Chairman
Approval Date: J u n 20,2022
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriffs Office Thomas Trester
PWP Business Office Jamie Sylvester
StaffAnalyst Linda Guerra
c° County of Fresno
Department of Public Works and Planning
p 36 p Development Services&Capital Projects Division
FRE�� Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 6/7/2022
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#067
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#067 is hereby approved by the County.
Scope of Work:
Additional CMU at removed gate.
Attachment:
CO Coversheet,PCO Proposal and support documents
Net Additive Change Order Dollar Amount: $1,052.06
Net Additive Calendar Days: 10
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: 10
Total Change Order Dollar Amount To Date: $62,937.89
Adjusted Contract Dollar Amount: 1 $11,427,437.89
Total Adjusted Calendar Days To Date: 30
Adjusted Construction Completion Date: 1 10/26/21
LaRue Goossen LaRue Goossen(Jun 7,202215:36 PDT)
Project Manager Signature
Date: Jun 7,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article Vl shall apply.
AVOW A'Ilkg
Accepted By: Klassen Corporation Rod Paine(Jun 7,202215:40 PDT)
Authorized Signature
Date: Jun 7,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
hndaauerra@fresnocountyca.gov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
DescriptionI I Adj. Days
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 $91,000.00 5 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
GGO 009 - N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 $572,775.76 0 Storage Bldg.electric
CCO 012 $32,245.91 0 Substation electrical
CCO 013 $112,372.79 0 Electrical plan update
CCO 014 $7,444.00 0 Blockout revised data room
CCO 015 $14,657.00 0 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020 12/14/2021 $2,794.26 0 Fab.&Install metal sill flashing
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
CCO 022 - N/A
CCO 023 12/14/2021 $3,093.25 0 Plumbing alterations per ASI 2&3
CCO 024 12/14/2021 $795.79 0 Revised Architecturals
CCO 025 11/22/2021 $8,355.00 0 Install Overflow pipe minus penetration of gutter
CCO 026 $0.00 56 Metal Building Delay#1
CCO 027 12/29/2021 $4,486.63 0 Fur out West Exterior Wall
CCO 028 12/29/2021 $2,097.75 0 Hardware changes from rev.in dwgs.ASI 7
CCO 029 $12,487.64 1 Reroute 2.5 and 3"fire mains per RFI 64
CCO 030 $71,190.79 0 Overhead door material price increase
CCO 031 12/29/2021 $10,008.10 0 Ceramic tile alterations
CCO 032 12/29/2021 $6,806.50 0 Add.Recessed TV and Databoxes
CCO 033 1/19/2022 $3,212.39 0 Tower Closure Strips
CCO 034 12/29/2021 $3,261.63 0 Provide power&connection to(5)hand dryers
CCO 034.1 $1,784.20 0 Provide power&connection to(5)hand dryers r2
CCO 035 12/29/2021 -$5,345.00 0 ASI to omit interior stone veneer and finish gyp board
CCO 036 $38,224.99 0 Alternate Sectional Doors
CCO 037 - N/A
CCO 038 N/A
CCO 039 - N/A
CCO 040 1/18/2022 $5,557.64 0 Lighting for Sheriff Star
CCO 041 $267,768.79 0 Data Rack Revisions
CCO 042 $7,334.25 0 Additional sunshade
CCO 043 3/30/2022 $3,633.89 0 Supply and Install"B"metal angle
CCO 044 2/16/2022 $3,352.40 0 Electrical for TV boxes
CCO 045 0 N/A
CCO 046 4/25/2022 $9,397.07 0 Submittal changes-Door hardware
CCO 047 3/8/2022 $3,082.34 0 Additional metal studs per new arch drawings
CCO 048 - N/A
CCO 049 $11,371.85 0 Install block wall along south portion of east parking lot curb
CCO 050 3/30/2022 $14,385.40 0 Tower and Entry Fascia Revision
MID 051 4/8/2022 $4,459.67 0 Added circuits to IDU Units
CCO 052 - N/A
CCO 053 - N/A
CCO 054 4/20/2022 -$114.65 0 Delete Waste Dispensers&Add Hand Dryers
CCO 055 $71,905.65 0 Delayed lighting package order-ASI#03
CCO 056 - N/A
CCO 057 4/22/2022 $3,054.20 0 Power&Connection to plumbing fixtures TP-1
CCO 058 - N/A
CCO 059 N/A
CCO 060 - N/A
CCO 061 $13,898.70 0 ASI 04-21-2022-01 Tower revisions
CCO 062 $8,108.54 - N/A
CCO 063 5/3/2022 $1,079.04 0 Install 6 footing sleeves
CCO 064 - N/A
CCO 065 - N/A
CCO 066 5/24/2022 $837.38 0 Cleanout relocation by TEV transformer
IC CO 067 5/3/2022 I $1,052.06 0 Additional CMU at removed gate
CCO 068 - N/A
CCO 069 N/A
CCO 070 N/A
CCO 071 - N/A
Totals $229,782.89 -$166,845.00 $968,731.68 $351,395.74 30
K PCCO #067
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #067: Additional CMU at Deleted Gate
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 6/01 /2022 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $ 1,052.06
DESCRIPTION:
CE#098-Delete Door in CMU Wall
Credit for chain link to follow.
ATTACHMENTS:
COR#7 for door infill.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
066 1 Additional CMU at Deleted Gate 1,052.06
TOTAL: $1,052.06
CHANGE ORDER LINE ITEMS:
PCO#066:Additional CMU at Deleted Gate
# Cost Code Description Type Amount
1 04-200-Masonry Unit Subcontractor $936.00
Subtotal: $936.00
Fee:10.00%Applies to all line item types. 93.60
Insurance:1.40%Applies to all line item types. 13.10
Bond:1.00%Applies to all line item types. 9.36
Grand Total: $1,052.06
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 219,414.26
The contract sum prior to this PCCO was $ 11,583,914.26
The contract sum would be changed by this PCCO in the amount of $ 1,052.06
The new contract sum including this PCCO will be $ 11,584,966.32
The contract time will not be changed by this PCCO
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On:6/2/2022 04:40 PM
McCurley and Day Masonry = M
Division 4 License # 62054 DIR # 1000012425 Mk A
5740 E. Shields Ave. #104, Fresno CA, 93727 P: (559) 348-9890 F: (559) 348-9220
CHANGE ORDER REQUEST NO: 7 DATE: 5/31/22 PROJECT: Fresno County Sheriff Substation
CHANGE ORDER FOR: Delete 4'door in CMU fence. Drilling/epoxy by others.This price is only valid right now while we are
constructing the adjacent walls. If this is done at a later date the price will increase significantly.
Equipment Quantity Unit Of Unit Cost Equip.
Measure Costs
19'Scissor Lift day $ 45.00 $
Propane Shop Forklift day $ 75.00 $
Gradall/Skytrak Forklift day $ 190.00 $
Mixer day $ 80.00 $
Foreman Truck day $ 70.00 $
Concrete Saw day $ 65.00 $
Generator day $ 55.00 $
Grout Pump 0.4 cu yd $ 15.00 $ 6.00
Subtotal: ======= =======- =====> $ 6.00
Materials Quantity Unit Of Unit Material
Measure Cost Costs
8x8x16 split face gray CMU 33 ea $ 3.64 $ 120
8x4x16 smooth gray CMU cap 3 ea $ 4.10 $ 12
Gray mortar 160 Ibs $ 0.09 $ 14
Grout fill for block walls 0.4 cu yds $130.80 $ 52
Fabricated rebar 40 Ibs $ 0.60 $ 24
Rebar positioners 4 ea $ 0.40 $ 2
Subtotal: ======= ======== ======= ---------- =====> $ 225
Labor Quantity Unit Of Unit Labor
Measure Cost Costs
Mason 4 hour $ 81.41 $ 326
Hodcarrier 4 hour $ 69.07 $ 276
Subtotal: > $ 602
Total of Columns: $6 $225 $602
Sales Tax: $0 $18 $0
Total Costs: $6 $243 $602
Accepted by(Signature):
Name (Print): TOTAL COST: $ 851
Title: MARK-UP @ 10% $ 85
Company: TOTAL: $ 936
Date: