HomeMy WebLinkAbout2102C CCO 02.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
LINCOLN AVENUE COLD PAVEMENT RECYCLING CHANGE ORDER NO. 2
LINCOLN AVENUE FROM SR 145 TO FIG AVENUE APRIL 27, 2022
FEDERAL PROJECT NUBMER: CMLSTBG-5942(300) PAGE 1 OF 1
CONTRACT NO. 21-02-C
TO: YARBS GRADING AND PAVING INC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) WORKING DAYS will be added to the contract time.
ALLOW FULL ROAD CLOSURE ON LINCOLN AVENUE DURING ROADWAY CONSTRUCTION
This change was requested by the contractor.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, allow full
roadway closure of Lincoln Avenue between SR 145 and one (1) mile east of SR 145, for a total of 20-
working days due to the potential public safety concerns during construction of the proposed
improvements in this area. This change is being made at no additional cost to the County.
This change did not impact the critical path for the project, so additional contract time was not warranted.
NET COST THIS CHANGE ORDER: $0.00 (NO COST)
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0)-WORKING DAYS
.2e6a�.tgS�au�uc,F,aei
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
YARBS GRADING & PAVING INC. u S
Contractor Mandeep S. Sekhon, PE
Interim Construction Engineer
Tlv� Y Ill-o GI`l
By Troy YYrbrough(May 3,20 11:04PDT) APPROVED BY:
W 1 1 I h +p Digitally signed by Steve White
President Date:2022.05.20 10:09:22
Title -07'00'
Steven E. White, Director
Public Works and Planning
May 3,2022
Accepted Date:
Date:
Contractor We,the above signed contractor,have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.