HomeMy WebLinkAbout2102C CCO 01.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
LINCOLN AVENUE COLD PAVEMENT RECYCLING CHANGE ORDER NO. 1
LINCOLN AVENUE FROM SR 145 TO FIG AVENUE MARCH 1, 2022
FEDERAL PROJECT NUBMER: CMLSTBG-5942(300) PAGE 1 OF 3
CONTRACT NO. 21-02-C
TO: YARBS GRADING AND PAVING INC:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), ZERO (0) WORKING DAYS will be added to the contract time.
PART I: UTILIZE RECYCLABLE PAVEMENT FABRIC
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, utilize a
recyclable pavement fabric(Trumbull Trupave or similar) in lieu of the non-recyclable (Mirafi MPV500 or
similar) pavement fabric for the pavement interlayer. Payment for this change will be made as an additional
agreed unit price of$0.385 per square yard (in addition to the unit bid price of Bid Item No. 53, Paving Fabric)
according to Section 9-1.03," Payment Scope," of the Special Provisions. The estimated quantity of the fabric
is 77,440 square yards; the estimated additional cost resulted in $29,814.40 (77,440 SY x $0.385 per SY =
$29,814.40). This amount will be adjusted to reflect the actual amount of fabric placed upon completion. This
additional payment will be made as extra work for the completed work.
This change did not impact the critical path for the project, so additional contract time was not warranted.
TOTAL COST PART I: A $29,814.40 INCREASE
TOTAL TIME EXTENSION PART I: ZERO (0)-WORKING DAYS
PART II: COMPENSATE THE CONTRACTOR FOR THE CALIFORNIA STATEWIDE CRUDE OIL PRICE
INDEX FLUCTUATION
This compensation adjustment was requested by the contractor.
Compensate the contractor per the methods established in the Standard Specifications and Special
Provisions Section 9-1.07 for fluctuations greater than or less than five percent in the California
statewide crude oil index for the month the material was placed, when compared to the index published
for the month of the bid opening. The California Statewide Crude Oil Price Index for the bid opening
month, August 2021, was 403.9. The index was 456.2 in November 2021 and 433.5 in December 2021
which applies to the Pay Estimate No. 4 for the quantity of asphalt in the hot mix asphalt (HMA) and
paving asphalt used for the pavement interlayer.
The asphalt content in the 3/-inch HMA from Vulcan-Ashlan plant was 4.56 percent. The percent was
reduced to 3.87 percent to account for the 15 percent reclaimed asphalt pavement(RAP). The
adjustment applies to 2,715.74 tons of 3/-inch HMA placed in November and 8,193.59 tons of'/-inch HMA
placed in December 2021. Also, paving asphalt(PG-64-16) was utilized on the project. A total of 12.15
tons of asphalt was used on the project in November 2021, and 36.77 tons used in December2021.
Contractor We,the above signed contractor,have considered the change proposed and hereby agree, if this proposal is
_Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
_Business Office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
LINCOLN AVENUE COLD PAVEMENT RECYCLING CHANGE ORDER NO. 1
LINCOLN AVENUE FROM SR 145 TO FIG AVENUE MARCH 1, 2022
FEDERAL PROJECT NUBMER: CMLSTBG-5942(300) PAGE 2 OF 3
CONTRACT NO. 21-02-C
The total adjustment compensation for price index fluctuation is being made as agreed price in
accordance with Section 9-1.03, "Payment Scope" of the Special Provisions, resulting in an increase of
$7,535.60. This amount will be paid through Bid Item No. 1, Supplemental Work (Payment
Adjustments for Price Index Fluctuations) with no net cost increase to the contract.
This change did not impact the critical path for the project, so additional contract time was not warranted.
TOTAL COST PART II: $0.00 (PAID IN BID ITEM NO. 1)
TOTAL TIME EXTENSION PART II: ZERO (0)-WORKING DAYS
PART III: ADJUST COMPENSATOIN FOR THE USE OF WARM MIX ASPHALT
This compensation adjustment was requested by the contractor.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, use warm mix
asphalt for the placement of the overlay at the Lincoln Avenue, from Fig Avenue to Cornelia Avenue. Payment
for the additional cost will be paid at an agreed unit price of$6.60 per ton (in addition to the unit bid price of Bid
Item No. 49, Hot Mix Asphalt (Type A%" Grading)) according to Section 9-1.03, "Payment Scope," of the
Special Provisions. A total of 3,718.38 tons of the warm mix asphalt was utilized; the additional compensation
resulted in $24,541.30 (3,718.38 tons x$6.60 per ton = $24,541.30). This amount will be made as extra work.
This work did not impact the critical path for the project, so granting additional contract time was not warranted.
TOTAL COST PART III: A $24,541.30 INCREASE
TOTAL TIME EXTENSION PART III: ZERO (0)-WORKING DAYS
Contractor We,the above signed contractor, have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
_Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
_Board of Supervisors
_Const.Management prices shOWn above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
LINCOLN AVENUE COLD PAVEMENT RECYCLING CHANGE ORDER NO. 1
LINCOLN AVENUE FROM SR 145 TO FIG AVENUE MARCH 1, 2022
FEDERAL PROJECT NUBMER: CMLSTBG-5942(300) PAGE 3 OF 3
CONTRACT NO. 21-02-C
NET COST THIS CHANGE ORDER: A $54,355.70 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0)-WORKING DAYS
,Pe6a,:.tgS�ac,2 .y
Robert Hendrickson, Resident Engineer
APPROVAL RECOMMENDED:
YARBS GRADING & PAVING INC.
Contractor Mandeep S. Sekhon, PE
Interim Construction Engineer
By, Troyrbrough(Mar3,20 09:21 PST) APPROVED BY:
President Steve ` h ite Digitally signed by Steve White
v �i V�i v v 1 1 `�i Date:2022.03.03 14:20:00
Title -08'00'
Steven E. White, Director
Public Works and Planning
Mar 3,2022
Accepted Date: March 3, 2022
Date:
Contractor We,the above signed contractor, have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
Business Office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.