HomeMy WebLinkAbout2001C CCO 03.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
SAND CREEK BRIDGE REPLACEMENT ON ENNIS ROAD CHANGE ORDER NO. 3
FEDERAL PROJECT NUMBER: BRLO-5942(238) MARCH 3, 2022
CONTRACT NO. 20-01-C PAGE 1 OF 2
TO: AGEE CONSTRUCTION CORPORATION:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
this contract. Because of the change(s), 10-WORKING DAYS will be added to the contract time. The revised
date of completion for the Second Order of Work is March 21, 2022.
PART I: ADJUST PAYMENT FOR THE ADDITIONAL COSTS INCURRED DUE TO A REDUCTION IN
THE PREFABRICATED ARTICULATED CONCRETE BLOCKS (ACB) QUANTITY FROM THE
CONTRACT— EXTRA WORK
This payment adjustment was requested by the contractor.
Adjust payment for the costs incurred due to changes made to the project plans by the Design Consultant in
reference to Request for Information (RFI) No. 4; a 20-foot wide section of the prefabricated Articulated
Concrete Blocks (ACB) mats was deleted from the project plans. The Department elected to take possession
of the excess prefabricated ACB material. A total of 949.64 square feet of ACB materials were delivered to the
Department's Maintenance Yard No. 7. The Bid Item No. 73, Articulated Concrete Blocks (Slope Protection)
will be reduced by 949.64 square feet in a subsequent change order. The contractor will be compensated for
the cost of materials, delivery charges, and mark-ups. The payment adjustment will be made at a force account
according to Section 9-1.03," Payment Scope," of the Special Provisions. The total compensation resulted in
an increase of$20,966.51.
This payment adjustment did not impact the critical path for the project, so additional contract time was not
warranted.
TOTAL COST PART I: A $20,966.51 INCREASE
TOTAL TIME EXTENSION PART I: ZERO (0)-WORKING DAYS
PART II: GRANT A TIME EXTENSION
This change was requested by the contractor.
Grant a time extension of 10-working days to the "Second Order of Work" due to Covid-19 exposures (5
days), materials supply delays for the snap ties (2 days), and design conflicts for the pre-stressing
ducts and installed rebar reinforcement (3 days). This time extension is being granted according to
Section 8-1.07B, "Time Adjustments," of the Special Provisions.
TOTAL COST PART II: $0.00 (NO COST)
TOTAL TIME EXTENSION PART II: 10-WORKING DAYS
_Contractor We,the above signed contractor, have considered the change proposed and hereby agree, if this proposal is
Auditor Controller approved,that we will provide all equipment, furnish all materials,except as may otherwise be noted above,
Business office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors prices shown above.
_Const.Management
_RE/Arch.
Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
SAND CREEK BRIDGE REPLACEMENT ON ENNIS ROAD CHANGE ORDER NO. 3
FEDERAL PROJECT NUMBER: BRLO-5942(238) MARCH 3, 2022
CONTRACT NO. 20-01-C PAGE 2 OF 2
NET COST THIS CHANGE ORDER: A $20,966.51 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: 10-WORKING DAYS
r
{rfj y
JAMES DREWS, Resident Engineer
APPROVAL RECOMMENDED:
AGEE CONSTRUCTION CORPORATION
Contractor p
/Vol 6&L
MANDEEP S. SEKHON, Interim Construction Engineer
By: Alan Dirlam(Mar 4,2022 10:20 PST) Digitally signed by Steve White
Steve White Date:2022.03.04 13:30:15
-08'00'
Cheif Estimator STEVEN E. WHITE, Director of Public Works
Title: and Planning
Mar 4,2022
Accepted Date: Date: March 4, 2022
Contractor We,the above signed contractor,have considered the change proposed and hereby agree,if this proposal is
_Auditor Controller approved,that we will provide all equipment,furnish all materials,except as may otherwise be noted above,
_Business Office and perform all services necessary for the work above specified,and will accept as full payment therefore the
Board of Supervisors
_Const.Management prices shown above.
RE/Arch.
Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
LETTER OF TRANSMITTAL - C.C.O. NO. 3 MARCH 3, 2022
TO: STEVEN E. WHITE, DIRECTOR SAND CREEK BRIDGE REPLACEMENT
PUBLIC WORKS AND PLANNING ON ENNIS ROAD
FEDERAL PROJECT NO: BRLO-5942(238)
CONTRACT NO. 20-01-C
ATTN: MANDEEP S. SEKHON
INTERIM CONSTRUCTION ENGINEER
FROM:
JAMES DREWS, Resident Engineer
STATUS OF FUNDS:
Contract Items $ 2,697,777.00 Original Allotment $ 2,845,165.85
Dept. Furnished Materials $ 0.00 Supplemental. Allotment $ 0.00
Previous CCO's $ 50,390.00 Total Allotment $ 2,845,165.85
This CCO $ 20,966.51 Obligated Funds $ 2,769,133.51
Total Obligated Funds $ 2,769,133.51 Unobligated Balance $ 76,032.34
DIRECTOR'S LIMIT to sign change orders is: $ 147,388.85
PART I - DESCRIPTION:
Adjust compensation for the additional costs incurred due to a reduction in the prefabricated
Articulated Concrete Blocks (ACB) quantity from the contract — extra work.
WHY:
As a response to the Request for Information (RFI) No. 4, the Design Consultant revised the project
plans which resulted in a reduction of the prefabricated Articulated Concrete Blocks (ACB) quantity
(Bid Item No. 73) by 949.64 square feet. These prefabricated ACB mats were specifically made for
this project and the contractor was unable to return and obtain a refund. The Department decided to
take possession of this material. Consequently, the contractor incurred additional costs, including
cost of material and delivery, and requested to adjust compensation for these additional costs
incurred. Therefore, it was necessary to adjust compensation as extra work.
HOW:
The contractor provided documents supporting the additional costs incurred associated with the
above referenced change to the contract. The compensation adjustment is being made on a force
account according to Section 9-1.03, "Payment Scope," of the Special Provisions. The total
compensation adjustment resulted in $20,966.51, this amount will be paid as extra work.
COST:
A $20,966.51 Increase
LETTER OF TRANSMITTAL - C.C.O. NO. 3 MARCH 3, 2022
PART II - DESCRIPTION:
Grant a time extension.
WHY:
The contractor requested a 10-working days' time extension; five (5) workings days' delay due
to Covid-19 exposures, two (2) working days' delay due to the materials delivery delays (snap
ties), and three (3) working days' delay for resolving design conflict for the pre-stressing ducts
and rebars reinforcement. The contractor provided a time impact analysis for review and
approval. The contractor's request for these additional days was reviewed and approved.
HOW:
A total of 10 working days are being added to the allotted contract time for the Second Order of
Work in accordance with Section 8-1.07B, "Time Adjustments," of the Special Provisions.
COST:
$0.00 (No Cost)
NET COST THIS CHANGE ORDER: A $20,966.51 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: 10-WORKING DAYS