HomeMy WebLinkAbout2001C CCO 02.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
SAND CREEK BRIDGE REPLACEMENT ON ENNIS ROAD CHANGE ORDER NO. 2
FEDERAL PROJECT NUMBER: BRLO-5942(238) OCTOBER 28, 2021
CONTRACT NO. 20-01-C PAGE 1 OF 2
TO: AGEE CONSTRUCTION CORPORATION: You are hereby directed to make the herein described
changes from the plans and specifications or do the following described work not included in the plans and
specifications on this contract. Because of the proposed change, 10 WORKING DAYS will be granted to the
allotted contract time. The revised date of completion for the Second Order of Work is February 24, 2021.
PART I: INCREASE ITEMS AT UNIT PRICES
Increased Items:
Item Total
No. Description Unit Quantity Price Amount °�
8 Treated Wood Waste LB 1,140.00 $0.80 $ 912.00 4.75
36 Remove Fence (Type WM) LF 36.00 7.00 252.00 20.00
40 Rock Excavation CY 66.00 51.00 3,366.00 6.09
41 Rock Excavation (Large Boulders-2 CY 570.00 80.00 45,600.00 380.00
tons or more)
51 Remove Roadside Sign EA 4.00 65.00 260.00 44.44
TOTAL INCREASE:-$50,090— 4 5at31V ms�
TOTAL COST PART I: A $50,390 INCREASE
TOTAL TIME EXTENSION PART I: ZERO WORKING DAYS
PART II: GRANT A TIME EXTENSION:
Grant a time extension of 10-working days to the "Second Order of Work" due to time required to
perform the additional rock excavation (large boulders-2 tons or more) as noted in Part I of this Contract
Change Order. The time extensions shall apply according to Section 8-1.0713 of the Special Provisions.
TOTAL COST PART II: $ 0.00 (NO COST)
TOTAL TIME EXTENSION PART II: 10 WORKING DAYS
NET COSTS THIS CHANGE ORDER: A $50,390 INCREASE
NET TIME EXTENSION THIS CCO: 10 WORKING DAYS
_ Contractor-white We,the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
_Auditor-Canary this proposal is approved,that we will provide all equipment, furnish all materials,except as may otherwise be
Bus.office-Green noted above,and perform all services necessary for the work above specified,and will accept as full payment
Board-Pink therefor the prices shown above.
_Const.Mgmt-Blue
_RE/Arch.-Blue
_Proj.oev.-Goldenrod If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
Contractor before specifications as to proceeding with the ordered work and filing a written protest within the time therein
Approval-White specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
SAND CREEK BRIDGE REPLACEMENT ON ENNIS ROAD CHANGE ORDER NO. 2
FEDERAL PROJECT NUMBER: BRLO-5942(238) OCTOBER 28, 2021
CONTRACT NO. 20-01-C PAGE 2 OF 2
JAMES DREWS, Resident Engineer
APPROVAL RECOMMENDED:
AGEE CONSTRUCTION CORPORATION,
Contractor
nn pp MAI, ION, Interim Construction Engineer
By:
Ste�e� 6-lyhlI e
Steven E White(Nov 11,202109:30 PST)
Chief Estimator STEVEN E. WHITE, Director of Public Works
Title: and Planning
Nov 4' 2021 Nov 11 2021
Accepted Date. Date:
Contractor-white We,the above signed contractor,have given careful consideration to the change proposed and hereby agree, if
_Auditor-Canary this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Bus.Office-Green noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board-Pink
_Const.Mgmt-Blue therefor the prices shown above.
_RE/Arch.-Blue
_Proj.Dev.-Goldenrod If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
_Contractor before specifications as to proceeding with the ordered work and filing a written protest within the time therein
Approval-white specified.
LETTER OF TRANSMITTAL - C.C.O. NO. 2 OCTOBER 28, 2021
TO: STEVEN E. WHITE, DIRECTOR SAND CREEK BRIDGE REPLACEMENT
PUBLIC WORKS AND PLANNING ON ENNIS ROAD
FEDERAL PROJECT NO: BRLO-5942(238)
CONTRACT NO. 20-01-C
ATTN: MANDEEP SEKHON
INTERIM CONSTRUCTION ENGINEER
FROM:
JAMES DREWS, Resident Engineer
STATUS OF FUNDS:
Contract Items $ 2,697,777.00 Original Allotment $ 2,845,165.85
Dept. Furnished Materials $ 0.00 Supplemental. Allotment $ 0.00
Previous CCO's $ 0.00 Total Allotment $ 2,845,165.85
This CCO $ 50,390.00 Obligated Funds $ 2,748,167.00
Total Obligated Funds $ 2,748,167.00 Unobligated Balance $ 96,998.85
DIRECTOR'S LIMIT to sign change orders is: $ 147,388.85
PART I - DESCRIPTION:
Increase items at unit prices.
WHY:
The bid quantities in the Bid Book are estimates only. This change order reflects the actual
quantities required for the construction of the above referenced project. Therefore, it was necessary
to increase the bid quantity of Bid Item No. 8, 36, 40, 41 and 51.
HOW:
The quantities of the above referenced bid items were increased at the unit bid prices according to
Section 9-1.03, "Payment Scope" of the Special Provision, resulting in an increase of$50,390.
COST:
$50,390 Increase
PART II DESCRIPTION:
Grant a Time Extension.
WHY:
Grant a 10 working days' time extension to the allotted contract time for the Second Order of
Work due to additional time required to perform the additional rock excavation (large boulders-2
tons or more).
LETTER OF TRANSMITTAL - C.C.O. NO. 2 OCTOBER 28, 2021
HOW:
A total of 10 working days are being added to the allotted contract time for the Second Order of
Work in accordance with Section 8-1.07B Time Adjustments of the project Special Provisions.
COST:
$0.00 No Cost
NET COST THIS CHANGE ORDER: $50,390 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: 10 WORKING DAYS
2001C LOT 02
Final Audit Report 2021-10-28
Created: 2021-10-28
By: Mandeep Sekhon(msekhon@fresnocountyca.gov)
Status: Signed
Transaction ID: CBJCHBCAABAAuKPSUYyr_kejc6MgabNsAMfO1912W11i
"2001 C LOT 02" History
Document created by Mandeep Sekhon (msekhon@fresnocountyca.gov)
2021-10-28-9:27:26 PM GMT-IP address:64.171.224.83
Document emailed to James Drews (jdrews@fresnocountyca.gov)for signature
2021-10-28-9:27:57 PM GMT
Email viewed by James Drews Qdrews@fresnocountyca.gov)
2021-10-28-9:28:34 PM GMT-IP address: 104.47.64.254
Document e-signed by James Drews (jdrews@fresnocountyca.gov)
Signature Date:2021-10-28-9:29:27 PM GMT-Time Source:server-IP address:73.41.204.115
Agreement completed.
2021-10-28-9:29:27 PM GMT
Q Adobe Sign