HomeMy WebLinkAbout2010C CCO 02.pdf COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
COUNTY SERVICE AREAS 30 & 32- CHANGE ORDER NO. 2
WATER SYSTEM IMPROVENTS APRIL 5, 2022
STATE WATER RESOURCES CONTROL- PAGE 1 OF 5
BOARD PROJECT NUMBER: 1000359-005C
DEPARTMENT OF WATER RESOURCES PROJECT NUMBER: 4600011626
CONTRACT NO. 20-10-C
TO: TEICHERT CONSTRUCTION:
Make the following changes to the plans and specifications or do work not included in the plans and
specifications for this contract. Because of the change(s), ZERO (0) WORKING DAYS will be added to the
contract time.
PART I: INCREASE/DECREASE/ELIMINATE ITEMS AT UNIT BID PRICES
This change was proposed by the engineer.
Item quantities in the Bid Book and subsequent change orders are estimates only. This Part adjusts item
quantities to the actual quantities used.
Increased Items:
Item Total
No. Description Unit Quantity C@ Price Amount NO
21 Type A V Water Service Lateral EA 2.00 $1,050.00 $ 2,100.00 3.77
Replacement
25 Permanent Trench Resurfacing TON 110.00 182.00 20,020.00 25.00
(Mains, Services, and
Appurtenances)
26 Sawcut, Remove and Replace LF 72.00 180.00 12,960.00 81.82
Concrete Curb and Gutter
27 Sawcut, Remove and Replace SF 64.00 42.00 2,688.00 32.00
Concrete Valley Gutter
35 1"Water Meter and Meter Box EA 2.00 1,350.00 2,700.00 3.77
62 Permanent Trench Resurfacing TON 142.50 190.00 27,075.00 25.00
(Mains, Services, and
Appurtenances)
63 Sawcut, Remove and Replace LF 86.00 152.00 13,072.00 24.86
Concrete Curb and Gutter
65 Sawcut, Remove and Replace SF 139.00 27.50 3,822.50 9.99
Concrete Sidewalk
90 Install Bollards for Fire Hydrant and EA 3.00 900.00 2,700.00 25.00
Air Valve
TOTAL INCREASE: $87,137.50
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above, and perform all services necessary for the work above specified,and will accept as full payment
—Board therefor the prices shown above.
_Const-Management
_RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and riling a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
COUNTY SERVICE AREAS 30 & 32- CHANGE ORDER NO. 2
WATER SYSTEM IMPROVENTS APRIL 5, 2022
STATE WATER RESOURCES CONTROL- PAGE 2 OF 5
BOARD PROJECT NUMBER: 1000359-005C
DEPARTMENT OF WATER RESOURCES PROJECT NUMBER: 4600011626
CONTRACT NO. 20-10-C
Decreased Items:
Item Total
No. Description Unit _Quantity Price Amount
7 State Water Resource Control Board $ 330.33 $ 1.00 $ 330.33 -66.07
- Notice of Intent
9 Supplemental Work Allowance $ 18,030.90 1.00 18,030.90 -60.10
30 Remove and Dispose of Asbestos EA 13.00 1,100.00 14,300.00 -81.25
Cement Pipe
43 State Water Resource Control Board $ 330.33 1.00 330.33 -66.07
- Notice of Intent
45 Supplemental Work Allowance $ 25,699.49 1.00 25,699.49 -85.66
50 6" PVC, C900, DR-14 Water Main LF 46.00 78.00 3,588.00 -1.62
64 Sawcut, Remove and Replace SF 11.00 35.00 385.00 -1.96
Concrete Valley Gutter
78 State Water Resource Control Board $ 330.33 1.00 330.33 -66.07
- Notice of Intent
86 4" Gate Valve Assembly EA 1.00 1,850.00 1,850.00 -50,00
100 Permanent Trench Resurfacing TON 13.44 250.00 3,360.00 -33.60
(Mains, Services, and
Appurtenances)
107 1" House Service Line LF 456.00 19.50 8,892.00 -24.58
111 Upgrade Grounding System EA 31.00 260.00 8,060.00 -40.26
113 1" House Service Line LF 663.00 19.50 12,928.50 -24.24
TOTAL DECREASE: $98,084.88
Eliminated Items:
Item Total
No. Description Unit Quantity Unit Price Amount (%)
10 Supplemental Work (Payment $ 2,500.00 $ 1.00 $2,500.00 100.00
Adjustment for Price Index
Fluctuations)
46 Supplemental Work (Payment $ 3,000.00 1.00 3,000.00 100.00
Adjustment for Price Index
Fluctuations)
66 Remove and Dispose of Asbestos EA 4.00 1,100.00 4,400.00 100.00
Cement Pipe
80 Supplemental Work (Payment $ 500.00 1.00 500.00 100.00
Adjustment for Price Index
Fluctuations)
Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Boa Business
ss office noted above,and perform all services necessary for the work above specified,and will accept as full payment
-Const.Management therefor the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
COUNTY SERVICE AREAS 30 & 32- CHANGE ORDER NO. 2
WATER SYSTEM IMPROVENTS APRIL 5, 2022
STATE WATER RESOURCES CONTROL- PAGE 3 OF 5
BOARD PROJECT NUMBER: 1000359-005C
DEPARTMENT OF WATER RESOURCES PROJECT NUMBER: 4600011626
CONTRACT NO. 20-10-C
84 6" PVC, C900, DR-14 Watermain LF 268.00 74.00 19,832.00 100.00
105 Upgrade Grounding System EA 53.00 260.00 13,780.00 100.00
Since you did not incur any costs associated with these items, no payment will be made for these bid items.
This change did not impact the critical path for the project, therefore, granting additional contract time was not
warranted.
TOTAL DECREASE: $44,012.00
TOTAL COST PART I: A$54,959.38 DECREASE
TOTAL TIME EXTENSION PART I: ZERO -WORKING DAYS
PART II: COMPENSATE FOR THE BID ITEM NO. 25 QUANTITY IN EXCESS OF 125 PERCENT
OF THE ORIGINAL ESTIMATED QUANTITY- EXTRA WORK
This compensation adjustment was proposed by the engineer.
Compensate for the additional trench paving, in excess of 125 percent of the original estimated quantity
of Bid Item No. 25, Permanent Trench Resurfacing (Mains, Services and Appurtenances), according to
Section 9-1.06B, "Increases of More Than 25 Percent," of the Standard Specifications. The estimated
bid quantity for this bid item was 440 tons of hot mix asphalt (HMA), however, a total of 723.10 tons of
HMA was used for the trench paving. The quantity up to 125 percent of the estimated bid quantity (550
tons) is paid at unit price of$182 in Bid Item No. 25, and the remainder(173.10 tons) is being paid at
an agreed adjusted unit price of$130, as extra work. The additional compensation (173.10 tons x
$130.00 per ton = $22,503.00) resulted in $22,503. This amount will be paid as extra work.
This work did not impact the critical path for the project, so granting additional contract time was not warranted.
TOTAL COST PART II: A $22,503 INCREASE
TOTAL TIME EXTENSION PART II: ZERO (0) -WORKING DAYS
PART III: COMPENSATE FOR THE BID ITEM NO. 62 QUANTITY IN EXCESS OF 125 PERCENT
OF THE ORIGINAL ESTIMATED QUANTITY - EXTRA WORK
This compensation adjustment was proposed by the engineer.
Compensate for the additional trench paving, in excess of 125 percent of the original estimated quantity
of Bid Item No. 62, Permanent Trench Resurfacing (Mains, Services and Appurtenances), according to
Section 9-1.06B, "Increases of More Than 25 Percent," of the Standard Specifications. The estimated
bid quantity for this bid item was 570 tons of hot mix asphalt(HMA), however, a total of 858.37 tons of
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment, furnish all materials,except as may otherwise be
_Business office noted above, and perform all services necessary for the work above specified,and will accept as full payment
_Board
Const.Management therefor the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
COUNTY SERVICE AREAS 30 & 32- CHANGE ORDER NO. 2
WATER SYSTEM IMPROVENTS APRIL 5, 2022
STATE WATER RESOURCES CONTROL- PAGE 4 OF 5
BOARD PROJECT NUMBER: 1000359-005C
DEPARTMENT OF WATER RESOURCES PROJECT NUMBER: 4600011626
CONTRACT NO. 20-10-C
HMA was used for the trench paving. The quantity up to 125 percent of the estimated bid quantity
(712.50 tons) is paid at unit price of$190 in Bid Item No. 62, and the remainder (145.87 tons) is being
paid at an agreed adjusted unit price of$170, as extra work. The additional compensation (145.87 tons
x $170.00 per ton = $24,797.90) resulted in $24,797.90. This amount will be paid as extra work.
This work did not impact the critical path for the project, so granting additional contract time was not warranted.
TOTAL COST PART III: A $24,797.90 INCREASE
TOTAL TIME EXTENSION PART III: ZERO (0) -WORKING DAYS
PART IV: ADJSUT COMPENSATE FOR THE ADDITIONAL EXCAVATION TO WORK AROUND
THE EXISING ASBESTOS PIPE CROSSINGS - EXTRA WORK
This compensation adjustment was requested by the contractor.
In accordance with Section 4-1.05, "Changes and Extra Work,"of the Standard Specifications, adjust
compensation for the additional excavation required in order to install watermain below the existing
asbestos pipe crossings through the project site as extra work. This compensation adjustment is being
made at an agreed lumpsum price of additional $5,000 ($3,000 for the Cantua Creek site and $2,000
for the El Porvenir site), according to Section 9-1.03, "Payment Scope," of the Special Provisions. This
amount will be paid as extra work.
This work did not impact the critical path for the project, so granting additional contract time was not warranted.
TOTAL COST PART IV: A $5,000 INCREASE
TOTAL TIME EXTENSION PART IV: ZERO (0) -WORKING DAYS
PART V: ABANDON AN UNMARKED EXISTING WATERMAIN (EL PORVENIR) - EXTRA WORK
This change was requested by the engineer.
In accordance with Section 4-1.05, "Changes and Extra Work," of the Standard Specifications, locate, cut, cap,
and abandon in place an existing watermain near the storage tank sta. 41+69 (El Porvenir), as extra work.
Perform the work according to the applicable sections of the Standard Specifications and Special Provisions.
Compensation for this work will be made as extra at force account on time and material basis according to
Section 9-1.04, "Force Account," of the Standard Specifications. The total compensation resulted in $6,241.06.
This amount will be,paid through Bid Item No. 9, "Supplemental Work Allowance,"with no net increase to the
contract.
This work did not impact the critical path for the project, so granting additional contract time was not warranted.
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and hereby agree,if
Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board therefor the prices shown above.
_Const.Management
_RE/Arch.
_Design If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
COUNTY SERVICE AREAS 30 & 32- CHANGE ORDER NO. 2
WATER SYSTEM IMPROVENTS APRIL 5, 2022
STATE WATER RESOURCES CONTROL- PAGE 5 OF 5
BOARD PROJECT NUMBER: 1000359-005C
DEPARTMENT OF WATER RESOURCES PROJECT NUMBER: 4600011626
CONTRACT NO. 20-10-C
TOTAL COST PART IV: $0.00 (PAID IN BID ITEM NO. 9)
TOTAL TIME EXTENSION PART IV: ZERO (0) -WORKING DAYS
NET COST THIS CHANGE ORDER: A $2,658.48 DECREASE
NET TIME EXTENSION THIS CHANGE ORDER: ZERO (0) WORKING DAYS
Jason Ai umada(Apr5,2022 10 50 PDT)
JASON AHUMADA, Resident Engineer
APPROVAL RECOMMENDED:
TEICHERT CONSTRUCTION
Contractor MANDEEP S. SEKHON,
l Interim Construction Engineer
By 2 o r' P'�� APPROVED BY:
Steve ` ,� h I tQ Digitally signed by Steve White
G V G vv G Date:2022.04.12 09:24:40
Title Pr""-4 a✓10.5-QlY -07'00'
U STEVEN E. WHITE, Director
Public Works and Planning
Accepted Date:
Date:
_Contractor We,the above signed contractor, have given careful consideration to the change proposed and.hereby agree,if
_Auditor Controller this proposal is approved,that we will provide all equipment,furnish all materials,except as may otherwise be
_Business office noted above,and perform all services necessary for the work above specified,and will accept as full payment
_Board
_Const.Management therefor the prices shown above.
RE/Arch.
_Design If the Contractor does not sign acceptance of this order,his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.