HomeMy WebLinkAbout16-S-04 CCO 24 BERNARDS.pdf COU County of Fresno
( Department of Public Works and Planning
�O 56 p Capital Projects Division
FR7�S� Steven E.White, Director
CONSTRUCTION CHANGE ORDER
Project: West Annex Jail (WAJ)
Contract No.: 16-S-04
Description: New Jail Facility
2208 Merced Street, Fresno, CA 93721
Contractor: Bernards
Address: 555 First Street
San Fernando, CA 91340
Request Date: 3/1/2022
Change Order Request No.: 24
Construction Contract Dollar Amount(as awarded on 11/14/17) 1 $81,756,000
Scope of work:See Attached Prime Contract Change Order
Change Order Dollar Amount $85,862
Net Additive Change Order Dollar Amount 1 $3,621,513
Net Deductive Change Order Dollar Amount $0
See attached Change Order Summary
Adjusted Contract Dollar Amount: $85,377,513
Original Completion Date June 29,2020
Net Additive Working Days 81
Net Deductive Working Days 0
Adjusted Contract Duration Date September 18,2020
Reviewed: Keith Eckert keckert 411312022 1:26:16 PM
Project Manager
Reviewed: William Kettler wkettler 411312022 1:31:00 PM
Division Manager
Approved., Bernard Jimenez bjimenez 411312022 2:03:25 PM
Planning and Resource Mangement Officer
Approved: Steven E. White stwhite 411312022 2:12:56 PM
Director
Approved. Daniel Cederborg dcederborg 411312022 2:33:29 PM
County Counsel
Approved: Paul Nerland
County Administrative Officer, CAO
Approved: Brian Pacheco
Chairman, Board of Supervisors
Scan and forward Director Approved Copy to: County Administrative Office Greg Reinke
PWP Business Office Kay Vang
Staff Analyst Linda Guerra
Construction Manager Kitchell
LETTER OF TRANSMITTAL -C.C.O. No. 024 March 1, 2022
Page 1 of 12
TO: Steven White, Director West Annex Jail
Public Works and Planning
ATTN: Will Kettler
Division Manager CONTRACT NO. 16-S-04
FROM:
Jim Anderson, Sr. Project Manager
Kitchell CEM
STATUS OF FUNDS
Contract Items $ 81,756,000.00 Original Allotment $ 85,843,800.00
Co. Furnished Materials $ 0.00 Supplemental Allotment $ 0.00
Previous CCO's $ 3,535,651.00 Total Allotment $ 85,843,800.00
This CCO $ 85,862.00 Obligated Funds $ 85,377,513.00
Total Obligated Fund $ 85,377,513.00 Unobligated Balance $ 466,287.00
Note: 1. Total allotment is the bid amount plus the Board Chairman's limit to authorize
Change Orders$4,087,800.00
DESCRIPTION IPCO 01711
RFI 47.1 —Missing Gate Details
WHY:
Contract documents did not provide details for a required gate replacement
HOW:
Lump Sum
COST:
A$2181.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0272)
ASI 073—Trench Drain at Loading Dock
WHY:
A trench drain was required to be installed at the exterior entrance to the loading dock for drainage.
HOW:
Time and Material
Letter Of Transmittal —C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 2 of 12
COST:
A$20,171.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION WCO 0318)
RFI 695—HVAC Duct Penetrating Fire Rated Walls
WHY:
(2) Fire/Smoke Dampers were not shown on the Contract Documents and were required to be
installed to include electrical and fire alarm interface scope.
HOW:
Lump Sum
COST:
A$8,530.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0359)
RFI 703 &703.1 —Sewage Grinder Pump (Horn and Strobe)
WHY:
An emergency horn and strobe was requested to be installed by Facilities in the event of failure on the
grinder pump.
HOW:
Lump Sum
COST:
A$8,151.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0278.1)
ASI 74—Added Data and Communications within Room 1114
WHY:
The Sheriff Dept. requested added data and communication ports installed within Program Room
1114.
HOW:
Letter Of Transmittal —C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 3of12
Time&Material
COST:
A$6,100.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0373)
ASI 90—Fuel Tank Relocation and Added Day Tank
WHY:
The only non-contract portion of ASI 90 is for fuel pipe covers at grade level in maintenance
walkways.
HOW:
Lump Sum
COST:
A$577.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 03761
RFl 815—Fire Sealant at Shaft Wall
WHY:
Contract Documents did not show the requirement for fire caulking at a new shaft wall assembly.
HOW:
Lump Sum
COST:
A$1,944.00 Increase
TIME:
No time extension requested by contractor
DESCRIPTION (PCO 0408)
RFI 791 &791.1 —Grinder Pump Electrical Outlet and Light
WHY:
In order to maintenance the grinder pump within the vault, an electrical outlet and light was installed
HOW:
Lump Sum
Letter Of Transmittal —C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 4 of 12
COST:
A$1,671.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 04271
RFI 951 —Tamper Switch Monitoring at Fire Sprinkler Risers
WHY:
(5) tamper switches were shown on the drawings but did not have corresponding direction to provide
monitoring by the fire alarm drawings.
HOW:
Lump Sum
COST:
A$8,168.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 04731
RFI 1001 —Staff Station Metal Shroud at Fire Sprinkler Piping
WHY:
Exposed fire sprinkler piping at Level 2 &3 Staff Station is a ligature issue.
HOW:
Lump Sum
COST:
A$2,559.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0481)
RFI 1010—CMU Wall Repair
WHY:
Contract documents showed the routing of ductwork that encroached into a door swing. The duct
needed to be removed and the cored hole patched
HOW:
Time and Material
Letter Of Transmittal—C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 5 of 12
COST:
A$4,544.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 04861
RFI 1011, 1011.1 —Deletion of Traffic Coating in Cell Chases
WHY:
Due to the complex mechanical and electrical work within the chases behind the cells, the Owner
elected to remove the traffic coating within all of the cell chases.
HOW:
Lump Sum
COST:
A$(53,373.00) Decrease
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 04951
RFI 1035, .1 & .2—Penetration Fire Sealant(FS-One Max)
WHY:
The SFM rejected the use of a penetration fire sealant (FS-One Max) due to the material drying too
rigid. The contractor was required to hire a 3rd party consultant to perform engineering and analysis
to prove to the SFM that the fire sealant complied with the State Code. The product was eventually
approved by the SFM.
HOW:
Lump Sum
COST:
A$9,280.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 05181
RFI 1070—Vertical Conduit in Guard Stations
WHY:
Exposed conduit was installed vertically in both the 2nd and 3rd floor guard stations. The Owner
Letter Of Transmittal—C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 6 of 12
elected to have the conduit enclosed within a stud framed wall.
HOW:
Lump Sum
COST:
A$6,151.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0251.1)
BFI's 589 &590—Basement and 1st Floor Fire Sprinkler Standpipes
WHY:
Credit related to the framing of sprinkler standpipes at the basement and 1 st floors.
HOW:
Lump Sum
COST:
A($2,504.00)Decrease
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0539)
RFI 1093—Electrical Outlet Conflict with Mirror
WHY:
An electrical outlet was in conflict with the placement of a mirror in the basement locker room. The
contractor was directed to install (2)smaller mirrors in lieu of relocation of the outlet.
HOW:
Lump Sum
COST:
A$368.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 05411
ASI 107—Sub-Dayroom Detention Furniture
WHY:
Due to space restrictions for ADA, adjustments were necessary to the tables and stools in Rooms
Letter Of Transmittal—C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 7 of 12
2111, 3111, 2121 & 3121. The Sheriff elected to have a removeable seat in the sub-dayrooms to
accomodate both handicap and non-handicap inmates.
HOW:
Lump Sum
COST:
A$16,460.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 05451
RFI 1100—Custody Admin Outlet Relocation
WHY:
Electrical outlet in room 1149 was shown incorrectly on a fire rated shaft wall and was required to be
relocated.
HOW:
Lump Sum
COST:
A$618.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 05471
RFI 1103 Paint Type Clarification in Room 1146E
WHY:
The room finish schedule did not indicate a paint type within this room.
HOW:
Lump Sum
COST:
A$2,068.00 Increase
DESCRIPTION (PCO 0507.11
RFI 1043—Main Jail Roof Patch for Vent from Diesel Day Tanks
WHY:
The vent piping for the new diesel fuel tanks in the Main Jail were required to penetrate the roof which
required the penetrations to be patched.
Letter Of Transmittal—C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 8 of 12
HOW:
Lump Sum
COST:
A$2,221.00 increase
TIME:
No time extension requested by contractor.
DESCRIPTION WO 05511
RFI's 1091, .1 & .2—Fan Coil Electrical
WHY:
Rewire fan coils at an external Variable Frequency Drive to be compatible with the specified inverter
motor.
HOW:
Lump Sum
COST:
A$1,216.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION WO 05531
RFI 1116—VAV Controller Power @ Room 1170
WHY:
The Variable Air Volume Controller in the mechanical room 1170 did not show power on the Contract
Documents
HOW:
Lump Sum
COST:
A$959.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION WO 05541
ASI 108—Install a stud framed wall at the Basement tunnel to the NAJ
WHY:
The exterior wall on the NAJ within the new tunnel had vapor membrane on it that could not be
removed. The Sheriff requested that the wall be stud framed and drywalled.
Letter Of Transmittal—C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 9 of 12
HOW:
Lump Sum
COST:
A$6,467.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0555)
RFI 1119—Deletion of Asphaltic Seal at new Parking Lot
WHY:
Contract documents required an asphaltic sealer on the new asphalt at the parking lot which was not
necessary.
HOW:
Lump Sum
COST:
A($3,275.00) Decrease
DESCRIPTION (PCO 0561)
RFI 1121 —Irrigation Connection to Existing NAJ
WHY:
The existing irrigation system at the NAJ was connected to irrigation prior to the WAJ construction and
needed to be re-connected.
HOW:
Lump Sum
COST:
A$2,146.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 05621
RFI 1122—Power to Water heater in Basement
WHY:
Power was not shown for the water heater in the basement on the Contract Documents
HOW:
Letter Of Transmittal —C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 10 of 12
Lump Sum
COST:
A$3,544.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0569)
RFI 1126& .1 — 120V Power to Door Hold Open Devices
WHY:
120V power was not shown for(4)door hold open devices on the Contract Documents
HOW:
Lump Sum
COST:
A$3,071.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0570)
RFI 1141 —Relay for Smoke Purge
WHY:
The variable frequency drive within the motor control system did not have the means to control the
speed of the fans for smoke purge. A control relay was required to be added.
HOW:
Time&Material
COST:
A$4,733.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0581) (Reference PCO 5411
ASI 107.1 —Table and Stool Modifications in Rooms 2090 &3090
WHY:
Rooms 2090 & 3090 were not listed in the original ASI 107 and require the same adjustments as
shown in PCO 541.
HOW:
Letter Of Transmittal—C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 11 of 12
Lump Sum
COST:
A$3,878.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 0554.1)
ASI 108—Paint and Wall Guards at Tunnel Wall
WHY:
(Reference PCO 554)—This PCO is directly related to the painting and added wall guards on the new
stud framed wall in the tunnel.
HOW:
Lump Sum
COST:
A$3,731.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION WCO 0587)
RFI 1160—East Alley Gate Hardware
WHY:
The specified electric door strike at the north and south metal gates did not work with the framing. A
surface mounted strike was required.
HOW:
Lump Sum
COST:
A$1,117.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 05881
RFI 1142—Fans for Fire Alarm Control Missing
WHY:
Fan coils shown on the mechanical drawings were not shown on the fire alarm drawings to be
interfaced with the smoke evacuation system.
Letter Of Transmittal—C.C.O. No 024
Contract No. 16-S-04
March 1, 2022
Page 12 of 12
HOW:
Lump Sum
COST:
A$2,876.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 05961
RFI 1163—TV Receptacle Faceplates
WHY:
The power receptacle faceplate for the TV's in the dayrooms was too large affecting the installation of
the TV mounting bracket. The faceplates needed to be changed.
HOW:
Lump Sum
COST:
A$487.00 Increase
TIME:
No time extension requested by contractor.
DESCRIPTION (PCO 06011
Main Jail CAN Equipment Upgrade
WHY:
An upgrade to the system was required for the system to provide the Sheriff requested messaging as
the initial components were not compatible with the existing system.
HOW:
Lump Sum
COST:
A$9,027.00 Increase
TIME:
No time extension requested by contractor.
NET COST THIS CCO : $85,862.00 INCREASE AND 0 CALENDAR DAY EXTENSION
" Prime Contract Change Order
Detailed
Date: 1/2712022
To Contractor: Contract Number. 16-S-004
Bernards Change Order Number: 024
1781 E Fir Ave,#205
Fresno,CA 93720
The Contract is hereby revised by the following Items:
Contract Change Order#024
PCO Description Amount
0171 RFI 47.1-Missing Gate&CMU Wall Details $2,181.00
0272 ASI 073-Trench Drain at Dods $20,171.00
0318 RFI 0695-F1-HVAC Duct Penetrating Fire Rated Wags $8.530.00
0359 RFI 0703,703.1-Site-Sewage Grinder Pump Ethernet(Hom and Strobe) $8,151.00
0278.1 ASI 74-Program Room 1114-Low Voltage Only $6,100.00
0373 ASI 90-Fuel Tank Relocation and Added Day Tank $577.00
0376 RFi 816-Building Shaft Wall Fire Rated Assembly $1,944.00
0408 RFl 791,791 A-Grinder Pump Vault-Light and Outlet $1.671.00
0427 RF1951-LO Tamper Switches—FA Monitoring $8,168.00
0473 RFI 1001-L2_L3-Staff Computer Station Shroud $2.559.00
0481 RFI 1010-L2-1.3 Tier-CMU Wall Repair(ASI-098) $4,544.00
0486 RFI 1011,1011.1-1_2-L3_Cell Chases—Traffic Coating_Clarifleation $(53,373.00)
0495 RF1 1035,1035.1.1035.2-Bldg_Thru Sprinkler Pipe Penetrations—Flexible $9,280.00
Sealant
0518 RF11070-1.2-1_3 Tier Guard Station-Vertical Conduit-Enclosed Chase $6,151.00
0251.1 RFI 599.590-First Floor and Basement Standpipe Locations S(2,504.00)
0539 RF11093-Bldg-Electrical Outlet Conflict Room 0007 $368.00
0541 ASI 107-2111,3111,2121 and Sub-Dayroom Detention Furniture $16.460.00
0545 RFI i 100-Bidg 1149 Custody Admin Outlet Relocation $618.00
0547 RFI 1103-Lt HPC-1 Paint Clarification @ 1146B $2.068.00
0607.1 RF11043-Main Jail Fuel Day Tank Venting-Roof Patch $2,221.00
0651 RF11090,1090.1.1090.2-Bldg-Fan Coil Electrical Requirements $1,216.00
0553 RFI 1116-Li VAV Controller Box-Power @ Mech Rm 1170 $959.00
0554 ASI 108_Tunnel Connection Furred Wail $6,467.00
0556 RFI 1119-Site Asphaltic Seal Coat(Guardtop) $(3,275.00)
0561 RFl 1121-Site irrigation Connection to Existing-NE Comer $2,146.00
0562 RFI 1122-Bidg Basement Room 0032 WH-1 Power $3,544.00
0569 RF11126,1126.1-Door Holder-120v Power $3,071.00
0570 RFI 1141-Relay for Smoke Purge $4,733,00
0581 ASI 107.1-L2-L3 Sub-Dayroom Detention Furniture-Reference ASI 107 and $3,878.00
RFI 1053.1
0554.1 ASt 108—Tunnel Connection Furred Walt Paint and Guards $3,731.00
0587 RFI 1160-Exd_East Alley Gate Hardware(G1 B&G2A) $1,117,00
0588 RFI 1142-Bldg_Fans for FA Control Missing $2,876,00
0596 RFl 1163-1_2-1_3_TV Receptacles in Dayrooms $487.00
0601 Main Jail CATV Equip Upgrade S9,027,00
(� Prime Contract Change Order
Detailed
The original Contract Value was............... .............. ............................................................................ .... $81,756,000,00
Sum of changes by prior Prime.Contract Change Orders............................................................................... $3,535,661.00
The Contract Value prior to this Prime Contract Change Order was....... ............................................... $8512911651,00
The Contract Value will be changed by this Prime Contract Change Order in the amount of.,........................ $85,862,00
The new Contract Value Including this Prime Contract Change Order will be.................................................. $85,377,513.00
TheContract duration will be changed by........................................................................................................ o Days
The revised Completion date as of this Prime Contract Change Order is................................................ September 18,2D20
1 Prime Contract Change Order
Detailed
Approval Recommended
Bemards Kitchell CENT
CONTRACTOR PROJECT MANAGER
By Bruce Waltz By Jim Anderson
SIGNATURE/..�>h-s SIGNATURE —
DATE vZf f1 ,;;- 2— DATE 311/2022
Approval Recommended Approved By
DLR Fresno County
PROJECT MANAGER DIRECTOR
By Gregg Williams By Steven White
SiGNATUR SIGNATURE
DATE 2/14/22 DATE ��7
Approved By '
Fresno Coun �V Fresno County
COUNTY COUNSEL COUNTY ADMINISTRATIVE OFFICER
BY Daniel C.Cederborg By Paul Neriand
SIGNATURE SIGNATURE
DATE DATE
Fresno County
CHAIRMAN,BOARD OF SUPERVISORS
By Brian Pacheco
SIGNATURE
DATE
Prime Contract Change Order
Detailed
We the abovo-signed contractor,have given careful consideration to the change proposed and hereby agree,when this proposal Is approved
that we will provide all equipment furnish all materials,except as may otherwise be noted above,and perform all services necessary forthe work
stove specified,and will accept as full payment therefor the prices shown above.
If the Contractor does not sign acceptance of this order,his attention Is directed to the requirements of the Specifications as to proceeding with
the ordered work and filing a written protest within the time therein specified.
By accepting a Change Order,Contractor agrees to the changes,If any,In the Contract Price specified for each Rem and to the specified
Extension of Time allowed,It any,for completion of the entire Work on account of such Change Order,and agrees to furnish all labor and
materials and perform all Work necessary to complete all additional Work specified therein for the price adjustment and wthin the time specified
therein. Contractor shall make no additional claim for adjustment to the Contract Price or Contract Time,nor for additional costs or damages,on
account of the work referenced In such Change Order. A Change Order duly Issued by the Owner and accepted by the Contractor shall
constitute a complete accord and satisfaction as to the Work,Contract Price,and Contract Tome changed thereby. Contractor shall defend and
Indemnify the Owner,its officers,employees,agents and consultants,If any Subcontractor asserts any claim against the Owner that contradicts.
or is Inconsistent with,a duly Issued Change Order accepted by Contractor. Section 0126 00,1.9
1