HomeMy WebLinkAboutCCO 035.pdf CO,U'� County of Fresno
�d Department of Public Works and Planning
�RES�O Development Services&Capital Projects Division
Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 1/14/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#035
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9126/21
Change Order Scope of Work:
ASI to omit interior stone veneer and finish gypsum board.
Attachment(s):
PCO proposal and support docs
Net Additive Change Order Dollar Amount:
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: -$5,345.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date -$12,058.18
Adjusted Contract Dollar Amount: $11,352,441.82
Total Adjusted Calendar Days To Date: 30
Director's Change Order Limit Balance: $222,058.18
Adjusted Construction Completion Date: 10/26/21
Reviewed: Roger Davidson
Architect Signature
Reviewed: LaRue Goossen '"10
""'
Project Manager Signature
Reviewed: Mandeep Sekhon
Construction Manager Signature
Reviewed: Will Kettler
Division Manager
Approved: Steven E. White sty e W&,,0-
whl,J-1
Director Signature
Approved: Brian Pacheco NOTAPPLICABLE
Board of Supervisors Chairman Signature
Approval Date: Jan 18,2022
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriffs Office Thomas Trester
PWP Business Office Kay Vang
Staff Analyst Linda Guerra
Director Steve White
coU,� County of Fresno
Department of Public Works and Planning
O� s Development Services&Capital Projects Division
Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 12/29/2021
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#035
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#035 is hereby approved by the County.
Scope of Work:
ASI to omit interior stone veneer and finish gypsum board.
Attachment:
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $0.00
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: -$5,345.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: -$12,058.18
Adjusted Contract Dollar Amount: $11,352,441.82
Total Adjusted Calendar Days To Date: 30
Adjusted Construction Completion Date: 10/26/21
LaRue Goossen t� --
o�zs. P.,
Project Manager Signature
Date: Dec 29,2021
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
,hod plvke
Accepted By: Klassen Corporation ROEP,in(-11,2022 09 cos„
Authorized Signature
Date: Jan 11,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
lindaeuerraffresnocountvca.eov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 - $16,857.00 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
12129 009 N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 - $572,775.76 Storage Bldg.electric
CCO 012 $32,245.91 Substation electrical
CCO 013 - $112,372.79 Electrical plan update
CCO 014 - $7,444.00 Blockout revised data room
CCO 015 - $14,657.00 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 - $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020 12/14/2021 $2,794.26 0 Fab.&Install metal sill flashing
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
CCO 022 NOT USED
CCO 023 12/14/2021 $3,093.25 0 Plumbing alterations per ASI 2&3
CCO 024 12/14/2021 $795.79 0 Revised Architecturals
CCO 025 11/22/2021 $8,355.00 0 Install Overflow pipe minus penetration of gutter
CCO 026 $0.00 Metal Building Delay#1
CCO 027 12/29/2021 $4,486.63 0 Fur out West Exterior Wall
CCO 028 12/29/2021 $2,097.75 0 Hardware changes from rev.in dwgs.ASI 7
CCO 031 12/29/2021 $10,008.10 0 Ceramic tile alterations
CCO 032 12/29/2021 $6,806.50 0 Add.Recessed TV and Databoxes
CCO 033 $3,212.39 1 Tower Closure Strips
CCO 034 12/29/2021 $3,261.63 0 1 Provide power&connection to(5)hand dryers
CCO 035 12/29/2021 -$5,345.00 0 IASI to omit interior stone veneer and finish gyp board
Totals $154,786.82 -$166,845.001 $731,670.351 $35,458.30 Totals 30
K
PCCO #035
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax: (661)324-3900 Fax:
Prime Contract Change Order #035: ASI 12-14-2021 -01 Interior Stone
Credit
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 12/21 /2021 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: ($5,345.00)
DESCRIPTION:
CE#050-ASI 12-14-2021-01 Interior Stone Credit
ASI to omit Interior Stone Veneer and finish gypsum board.
ATTACHMENTS:
COR for ASI 12-14-2021-01.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
035 ASI 12-14-2021-01 Interior Stone Credit (5,345.00)
TOTAL: ($5,345.00)
CHANGE ORDER LINE ITEMS:
PCO#035:ASI 12-14-2021-01 Interior Stone Credit
# I Cost Code Description Type Amount
1 1 04-200-Masonry Unit Subcontractor ($5,345.00)
Subtotal: ($5,345.00)
Grand Total ($5,345.00)
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 125,242.21
The contract sum prior to this PCCO was $ 11,489,742.21
The contract sum would be changed by this PCCO in the amount of ($5,345.00)
The new contract sum including this PCCO will be $ 11,484,397.21
The contract time will not be changed by this PCCO
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On: 12/21/2021 05:08 PM
McCurley and Day Masonry
Division 4 License # 620562 DIR # 1000012425 :Kka
A
5740 E. Shields Ave. #104, Fresno CA, 93727 P: (559) 348-9890 F: (559) 348-9220
CHANGE ORDER REQUEST NO: 3 DATE: 12/20/2021 PROJECT: Fresno County Sheriff Substation
CHANGE ORDER FOR: ASI 12-14-2021-01 Delete interior stone veneer. Material is custom order/non-returnable.
Equipment Quantity Unit Of Unit Cost Equip.
Measure Costs
19'Scissor Lift day $ 45.00 $ -
Propane Shop Forklift (1) day $ 75.00 $ (75.00)
Gradall/Skytrak Forklift day $ 190.00 $ -
Mixer (1) 1 day $ 80.00 $ (80.00)
Foreman Truck (1) day $ 70.00 $ (70.00)
Concrete Saw (1) day $ 65.00 $ (65.00)
Generator (1) day $ 55.00 $ (55.00)
Grout Pump cu yd $ 15.00 $ -
Subtotal: _______ ________ _____> $ (345.00)
Materials Quantity Unit Of Unit Material
Measure Cost Costs
Stone veneer flat (221) sq ft $ $
Stone veneer corner (53) If $ - $
Pallets (2) ea $ - $
Mortar (2,158) Ibs $ - $
Subtotal:I=======1========I _______ _________ _____> 1 $ -
Labor Quantity Unit Of Unit Labor
Measure Cost Costs
Mason (30) hour $ 81.41 $ (2,442)
Hodcarrier (30) hour $ 69.07 $ (2,072)
Subtotal: _______ ________ _______ _________ _______ ___________ _____> $ (4,514)
Total of Columns: -$345 $0 -$4,514
Sales Tax: $0 $0 $0
Total Costs: -$345 $0 -$4,514
Accepted by (Signature):
Name (Print): TOTAL COST: $ (4,859)
Title: MARK-UP @ 10% $ (486)
Company: TOTAL: $ (5,345)
Date: