PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 1/14/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#031
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9126/21
Change Order Scope of Work:
Ceramic tile alterations
Attachment(s):
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $10,008.10
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date -$16,781.31
Adjusted Contract Dollar Amount: $11,347,718.69
Total Adjusted Calendar Days To Date: 30
Director's Change Order Limit Balance: $226,781.31
Adjusted Construction Completion Date: 10/26/21
Reviewed: Roger Davidson
Architect Signature
Reviewed: LaRue Goossen '"�"
Project Manager Signature
Reviewed: Mandeep Sekhon
Construction Manager Signature
Reviewed: Will Kettler
Division Manager
Approved: Steven E. White sty e W&,,0-
Whl,J-16
Director Signature
Approved: Brian Pacheco NOTAPPLICABLE
Board of Supervisors Chairman Signature
Approval Date: Jan 18,2022
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriffs Office Thomas Trester
PWP Business Office Kay Vang
Staff Analyst Linda Guerra
Director Steve White
coU,� County of Fresno
Department of Public Works and Planning
O� s Development Services&Capital Projects Division
Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 12/29/2021
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#031
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#031 is hereby approved by the County.
Scope of Work:
Ceramic tile alterations
Attachment:
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $10,008.10
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: -$16,781.31
Adjusted Contract Dollar Amount: $11,347,718.69
Total Adjusted Calendar Days To Date: 30
Adjusted Construction Completion Date: 10/26/21
LaRue Goossen
Project Manager Signature
Date: Jan 3,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
Accepted B Klassen Cor oration Rost'palk9
p Y p .dP—(J..11, z 07:51 PSI
Authorized Signature
Date: Jan 11,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
lindaauerra@fresnocountvca.eov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 - $16,857.00 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
GSO 009 N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 - $572,775.76 Storage Bldg.electric
CCO 012 $32,245.91 Substation electrical
CCO 013 - $112,372.79 Electrical plan update
CCO 014 - $7,444.00 Blockout revised data room
CCO 015 - $14,657.00 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 - $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020 12/14/2021 $2,794.26 0 Fab.&Install metal sill flashing
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
CCO 022 NOT USED
CCO 023 12/14/2021 $3,093.25 0 Plumbing alterations per ASI 2&3
CCO 024 12/14/2021 $795.79 0 Revised Architecturals
CCO 025 11/22/2021 $8,355.00 0 Install Overflow pipe minus penetration of gutter
CCO 026 $0.00 Metal Building Delay#1
CCO 027 12/29/2021 $4,486.63 0 Fur out West Exterior Wall
CCO 028 12/29/2021 $2,097.75 0 Hardware changes from rev.in dwgs.ASI 7
CCO 031 12/29/2021 $10,008.101 0 Ceramic tile alterations
Totals $144,718.69 -$161,500.001 $731,670.351 $32,245.91 Totals 30
K
PCCO #031
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax: (661)324-3900 Fax:
Prime Contract Change Order #031 : ASI 07 - Ceramic Tile Change
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 12/10/2021 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $ 10,008.10
DESCRIPTION:
CE#046-ASI 07-Ceramic Tile Change
ATTACHMENTS:
BULLETIN 13 ASI 07-CERAMIC TILE CHANGE.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
031 ASI 07-Ceramic Tile Change 10,008.10
TOTAL: $10,008.10
CHANGE ORDER LINE ITEMS:
PCO#031 :ASI 07-Ceramic Tile Change
# Cost Code Description Type Amount
1 09-300-Tle Change PFT-1,PFT-2,&PTB-1 Subcontractor $8,904.00
Subtotal: $8,904.00
Fee:10.00%Applies to all line item types. 890.40
Insurance:1.40%Applies to all line item types. 124.66
Bond:1.00%Applies to all line item types. 89.04
Grand Total: $10,008.10
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 106,804.68
The contract sum prior to this PCCO was $ 11,471,304.68
The contract sum would be changed by this PCCO in the amount of $ 10,008.10
The new contract sum including this PCCO will be $ 11,481,312.78
The contract time will not be changed by this PCCO
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On: 12/10/2021 08:35 AM
J. DEAN BALLARD AND SONS TILE AND MARBLE CO.
► ,' 3141 N.ARGYLE
FRESNO,CA 93727
PHONE: (559)291-9408
FAX: (559) 291-6946
LICENSE #297024 CA
UNION AFFILIATED/BAC LOCAL 3 CA
SBE CERTIFICATION #32824
DATE: 10/19/2021 DIR PUBLIC WORKS REG.#1000002729
TO: KLASSEN CORPORATION
ATTN.: ROD PAINE
REGARDING: FRESNO COUNTY SHERIFF AREA 2 SUBSTATION
LOCATION: FRESNO, CA
SPECIFICATION: 093000 TILE
SUBJECT: BULLETIN #13 ASI 07 REVISED ARCHITECTURAL
SUMMARY: CHANGE PFT-1, PFT-2 & PTB-1
BID MATERIAL
#VR-022 24X24" UNPOLISHED 1615 $4.41 $7,122.15
#VR-022 12X24" UNPOLISHED 1659 $3.24 $5,375.16
#VR-022 S43C9 3X12 BULNOSE UNPOLISHED 388 $3.61 $1,400.68
SUBTOTAL $13,897.99
TAX $1,108.3 6
TOTAL $15,006.35
REVISED MATERIAL
#DR-08 24X24" UNPOLISHED 1615 $6.20 $10,013.00
#DR-08 12X24" UNPOLISHED 1659 $5.51 $9,141.09
#DR-08 P43F9 3X24" BULNOSE UNPOLISHED 194 $7.96 $1,544.24
SUBTOTAL $20,698.33
'FAX $1,728.31
TOTAL $22,426.64
DIFFERENCE $7,420.29
MARKUP $0.20 $1,484.06
TOTAL ADD ASI 07 $8,904
IF YOU HAVE ANY QUESTIONS PLEASE CONTACT SANDRA LEE OR JIM BALLARD.
SINCERELY,
J. DEAN BALLARD AND SONS TILE AND MARBLE CO.
JIM BALLARD
ESTIMATOR