Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 12/14/2021
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#024
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Revised Architectural,wall type 1.3 requiring R-19 and now RM#
SS113B requiring R-19 FSK(Foil Scrim Kraft)faced fiberglass at ceiling
Attachment(s):
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $795.79
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0,00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date -$33,373.79
Adjusted Contract Dollar Amount: $11,331,126,21
Total Adjusted Calendar Days To Date: 30
Director's Change Order Limit Balance: $243,373.79
Adjusted Construction Completion Date: 10/26/21
Reviewed: Roger Davidson A014VIP ON
Architect
Reviewed: LaRue Goossen
Project Manager
Reviewed: Mandeep Sekhon
Construction Manager
Reviewed: Will Kettler
Division Manager
Approved: Steven E. White PST,
Director
Approved: Steve Brandau NOT APPLICABLE
Board of Supervisors Chairman
Approval Date: Dec 22,2021
Scan and forward Director Approved Copy to: CAO Greg Reinke
Sheriffs Office Thomas Trester
PWP Business Office Kay Vang
Construction Manager Mandeep Sekhon
Staff Analyst Linda Guerra
Architect Roger Davidson
cot, County of Fresno
119 , Department of Public Works and Planning
p 1856 O Development Services&Capital Projects Division
Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 12/14/2021
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#024
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#024 is hereby approved by the County.
Scope of Work:
Revised Architectural,wall type 1.3 requiring R-19 and now RM#
SS113B requiring R-19 FSK(Foil Scrim Kraft)faced fiberglass at ceiling
Attachment:
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $795.79
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: -$33,373.79
Adjusted Contract Dollar Amount: $11,331,126.21
Total Adjusted Calendar Days To Date: 30
Adjusted Construction Completion Date: 10/26/21
LaRue Goossen
Project Manager
Date: Dec 14,2021
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
AcceAccepted 8 : Klassen Corporation Ad�a%!18
/� Y p aoeczioe(oxxo,zouss:wPST)
Authorized Signature
Date: Dec 20,2021
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,StaffAnalyst
lindaeuerraWre snocountvea.Gov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
r App.Date Add Credit Rejected Pending Adj. Days Description
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 - $16,857.00 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
GGO 009 N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 - $572,775.76 Storage Bldg.electric
CCO 012 $32,245.91 Substation electrical
CCO 013 $112,372.79 Electrical plan update
CCO 014 $7,444.00 Blockout revised data room
CCO 015 - $14,657.00 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 - $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020 12/14/2021 $2,794.26 0 Install metal sill flashings
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
CCO 022
CCO 023 12/14/2021 $3,093.25 0 Install additional piping,valves,and fittings
CCO 024 12/14/2021 $795.79 0 I Revised Architectural
CCO 025 11/22/2021 $8,355.00
CCO 026 $0.00 Metal Building Delay#1
Totals $128,126.21 -$161,500.001 $731,670.351 $32,245.911 Totals 30
K PCCO #024
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #024: ASI 7 - Revised Architecturals -
Substation Insulation at Data Room
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 11/03/2021 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $795.79
DESCRIPTION:
CE#029-ASI 7-Revised Architecturals
REVISIONS IN DRAWINGS-Wall Type 1.3 requiring R-19 and now Rm#SS113B requiring R-19 FSK(Foil Scrim Kraft)faced fiberglass at ceiling.
ATTACHMENTS:
Coast Building Products-CO.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
024 ASI 7-Revised Architecturals 795.79
TOTAL: $795.79
CHANGE ORDER LINE ITEMS:
PCO#024:ASI 7-Revised Architecturals
# Cost Code Description Type Amount
1 07-210-Building Insulation Add Insulation for Wall Type 1.3-Delta#8 Subcontractor $303.17
2 07-210-Building Insulation Add Ceiling Insulation for Room SS113B-Delta#8 Subcontractor $312.08
3 07-210-Building Insulation Coast Building OH&P Subcontractor $92.75
Subtotal: $708.00
Fee:10.00%Applies to all line item types. 70.80
Bond:1.00%Applies to all line item types. 7.08
Insurance:1.40%Applies to all line item types. 9.91
Grand Total: $795.79
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 106,804.68
The contract sum prior to this PCCO was $ 11,471,304.68
The contract sum would be changed by this PCCO in the amount of $ 795.79
The new contract sum including this PCCO will be $ 11,472,100.47
The contract time will not be changed by this PCCO
Klassen Corporation page 1 of 2 Printed On: 12/13/2021 11 :19 AM
K PCCO #024
Klassen
corporation
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 2 of 2 Printed On: 12/13/2021 11 :19 AM
PSACRAMENTO COAST BUILDING PRODUCTS
• Fresno A TopBuild Company
731 North Market Blvd.,Sacramento CA 95874
P(916)440-8761-F(916)448-2931-CA#202026C2
CHANGE ORDER REQUEST
Date: 11/1/2021
Contractor Name: KLASSEN CORPORATION Project Name: FRESNO COUNTY SHERIFF AREA:
Address: 2021 WESTWIND DR Project Address:
City/State/Zip: BAKERSFIELD,CA.93301 City/State/Zip:
Phone Number: 661-324-3000 COR#:
Fax Number: 661-324-3900
Attention: ROD PAINE
DESCRIPTION REVISIONS IN DRAWINGS-Wall Type 1.3 requiring R-19 and now Rm#SS113B requiring R-19
FSK(Foil Scrim Kraft)faced fiberglass at ceiling
Breakout
--------------
Materials Quantity UOM Unit Cost Material
Wall Type 1.3=R-19 24"un 424 sq ft $ 0.56 $ 237.44
Ceiling Rm#SS113B=R-19 24"FSK(Foil Scrim Kraft) 263 sq ft $ 1.02 $ 268.26
$
$
Subtotal 5
Labor Quantity UOM Unit Cost Labor
WALL TYPE 1.3-JOURNEYMAN 0.75 HOUR $ 87.64 $ 65.73
CEILING RM#SS113B 0.5 HOUR $ 87.64 $ 43.82
Subtotal
Cost: $ 615
ACCEPTED BY: DATE:
OH&P 15% $ 92
TITLE:
Total: $ 708