HomeMy WebLinkAboutCCO 021.pdf CO, County of Fresno
Department of Public Works and Planning
� 6
Development Services&Capital Projects Division
Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 11/16/2021
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#021
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Install 1/2"wedge anchors at exterior wall
Attachment(s):
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $3,399.23
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: 00
Total Change Order Dollar Amount To Date -$48,412.09
Adjusted Contract Dollar Amount: $11,316,087.91
Total Adjusted Calendar Days To Date: 30
Director's Change Order Limit Balance: $258,412.09
Adjusted Construction Completion Date: 10/26/21
MAIMZfON
Reviewed: Roger Davidson R-IDSON(-22,2021 0 32 PST)
Architect
VR ^—=•-
Reviewed: LaRue Goossen 7-G..-(-22,20211000 PST)
Project Manager
Reviewed: Mandeep Sekhon
Construction Manager
Reviewed: Will Kettler �
Division Manager
Approved: Steven E. White Sf�E Wlute-
s1—Ew„,1¢(-22,20211018 PST)
Director
Approved: Steve Brandau NOTAPPLICABLE
Board of Supervisors Chairman
Approval Date: Dec 22,2021
Scan and forward Director Approved Copy to: CAD Greg Reinke
Sheriff's Office Thomas Trester
PWP Business Office Kay Vanq
Construction Manager Mandeep Sekhon
Staff Analyst Linda Guerra
Architect Roger Davidson
coU,� County of Fresno
Department of Public Works and Planning
O� s Development Services&Capital Projects Division
Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 11/16/2021
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#021
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#021 is hereby approved by the County.
Scope of Work:
Install 1/2"wedge anchors at exterior wall
Attachment:
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $3,399.23
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: -$48,412.09
Adjusted Contract Dollar Amount: $11,316,087.91
Total Adjusted Calendar Days To Date: 30
Adjusted Construction Completion Date: 10/26/21
LaRue Goossen t� --
L as,
Project Manager Signature
Date: Nov 22,2021
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
Accepted B : Klassen Cor oration Rost'palk9
p Y p odP—(—20.202 PST)
Authorized Signature
Date: Dec 20,2021
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
lindaauerra@fresnocountvca.eov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
-,N App. Date Add Credit Rejected Pending Adj. Days Description
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 - $16,857.00 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
GGO 009 N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 - $572,775.76 Storage Bldg electric
CCO 012 $32,245.91 Substation electrical
CCO 013 $112,372.79 Electrical plan update
CCO 014 $7,444.00 Blockout revised data room
CCO 015 - $14,657.00 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 - $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
Totals $113,087.91 -$161,500.001 $731,670.351 $32,245.911 Totals 30
K PCCO #021
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #021 : Install Wedge Anchors at Exterior
Wa I I
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 10/27/2021 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $ 3,399.23
DESCRIPTION:
CE#026-Install Wedge Anchors at Exterior Wall
1)Add labor and materials to install'/2'wedge anchors at exterior wall.
2)Torque test inspection by others.
Materials Metal Studs
Add'/i'anchor bolts 302 x$2.72=$821.44
Material Tax 7.975%_$65.51
Labor
Carpenter 48 hours 48 x$81.08=$3,891.84
Labor Burden
48hrs @ 81.08 x 36%_$1,401.62
Total Materials$886.95
Total Labor$3,891.84
Total Burden$ 1,401.62
5%Over Head$309.02
5%Profit$309.02
Total$6,798.45
Klassen&Fresno to split total:
ATTACHMENTS:
Change Order#4 Sheriff Area 2 Substation.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
022 1 CE#026-Install Wedge Anchor 3,399.23
TOTAL: $3,399.23
CHANGE ORDER LINE ITEMS:
PCO#022:CE#026-Install Wedge Anchor
# I Cost Code Description Type Amount
1 1 09-250-Gypsum Board Labor and Materials(Owner Half) Subcontractor $3,399.23
Subtotal: $3,399.23
Grand Total: $3,399.23
Klassen Corporation page 1 of 2 Printed On: 11/12/2021 07:58 AM
K PCCO #021
Klassen
corporation
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 106,804.68
The contract sum prior to this PCCO was $ 11,471,304.68
The contract sum would be changed by this PCCO in the amount of $ 3,399.23
The new contract sum including this PCCO will be $ 11,474,703.91
The contract time will not be changed by this PCCO
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE