HomeMy WebLinkAboutCCO 019.pdf cotr County of Fresno
19 R' Department of Public Works and Planning
Eli) Development Services&Capital Projects Division
Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 2/2/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#019
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Folding Wall Revisions
Attachment(s):
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $2,884.00
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date -$51,811.32
Adjusted Contract Dollar Amount: $11,312,688.68
Total Adjusted Calendar Days To Date: 30
Director's Change Order Limit Balance: $261,811.32
Adjusted Construction Completion Date: 10/26/21
`6lG[y/AfOf1
Reviewed: Roger Davidson zoz-
Architect
Reviewed: LaRue GoossenL,RG '
Project Manager
Reviewed: Mandeep Sekhon
Construction Manager
Approved: Will Kettler
Division Manager
Approved: Steven E. White s` E �"�
Niiic;Fcb 3.202213 D4STD
Director
Approved: Brian Pacheco NOT APPLICABLE
Board of Supervisors Chairman
Approval Date: Feb 3,2022
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriff's Office Thomas Trester
PWP Business Office Kay Vang
Staff Analyst Linda Guerra
Director Steve White
co��.,� County of Fresno
Department of Public Works and Planning
Development Services&Capital Projects Division
FRES Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 9/21/2021
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#019
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#019 is hereby approved by the County.
Scope of Work:
Folding Wall Revisions
Attachment:
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $2,884.00
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: -$51,811.32
Adjusted Contract Dollar Amount: $11,312,688.68
Total Adjusted Calendar Days To Date: 30
Adjusted Construction Completion Date: 10/26/21
LaRue Goossen
Project o^ Manager
er Signature
Date: Sep 28,2021
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
Accepted By: Klassen Corporation
Authorized Signature
Date: Feb 1,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
lindaguerra@fresnocountyea.gov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
-,N App. Date Add Credit Rejected Pending Adj. Days Description
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 - $16,857.00 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
GGO 009 N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 - $572,775.76 Storage Bldg electric
CCO 012 $32,245.91 Substation electrical
CCO 013 $112,372.79 Electrical plan update
CCO 014 $7,444.00 Blockout revised data room
CCO 015 - $14,657.00 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 - $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 $0.001 0 Date adjustments
CCO 019 9/21/2021 1 $2,884.00 1 0 ITolding Wall Revisions
Totals $109,688.68 -$161,500.001 $731,670.351 $32,245.911 Totals 30
K PCCO #019
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #019: RFI #53 Folding Wall Revisions
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 9/20/2021 CREATED BY: Rod Paine(KLASSEN CORPORATION)
CONTRACT STATUS: Draft REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $2,884.00
DESCRIPTION:
CE#022-RFI#53 Folding Wall Revision
Provide material and labor to resolve folding wall revisions.
ATTACHMENTS:
Sheriff Substation Folding Partition Anchorage Repair.pdf Partition Wall Beam Crane.pdf Anchor Bolts at Partition Wall Breakout.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
020 1 CE#022-RFI#53 Folding Wall 2,884.00
TOTAL: $2,884.00
CHANGE ORDER LINE ITEMS:
PCO#020:CE#022-RFI#53 Folding Wall
# Cost Code Description Type Amount
1 05-120-Structural Steel RFI#53 Folding Wall Revision Subcontractor $1,745.00
2 01-566-GC-Misc.Equipment Crane Service Other $820.00
3 20-500-Financials,Construction Profit Fee 10% Other $257.00
4 20-800-Financials,Builder's Risk Insurance 1.4% Other $36.00
5 20-600-Financials,Bonds Bond Other $26.00
Subtotal: $2,884.00
Grand Total: $2,884.00
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 106,804.68
The contract sum prior to this PCCO was $ 11,471,304.68
The contract sum would be changed by this PCCO in the amount of $ 2,884.00
The new contract sum including this PCCO will be $ 11,474,188.68
The contract time will not be changed by this PCCO
Klassen Corporation page 1 of 2 Printed On:9/20/2021 05:08 PM
K PCCO #019
Klassen
corporation
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 2 of 2 Printed On:9/20/2021 05:08 PM
Reception
From: Curtis Gardner <curtisg@klassencorp.com>
Sent: Thursday, September 9, 2021 12:33 PM
To: Reception; Rod Paine
Subject: RE: RFI - Sheriff Sub
Thank kyou for sending this change order so quickly Kim, but I am sure the county is going to want to see cost
brokendown a little further. Possibly material/ labor/markup. My goal is to push this threw and get installation
scheudled as quick as possible, hoping to save a step of them sending this back.
Curtis Gardner
Construction Superintendent
661-477-3232 cell
KK lassen
corporation
Curtisg@klassencorp.com I www.klassencorp.com
"A tradition of excellence in design and construction"
a lm a
From: Reception <reception@kascofab.com>
Sent: Thursday, September 9, 2021 9:24 AM
To: Rod Paine <rodp@klassencorp.com>; Curtis Gardner<curtisg@klassencorp.com>
Subject: RFI - Sheriff Sub
From Kim @ Kasco Fab Inc
Thank you
'mac. Z 0 ,�
e ! L� d
MIDNIGHT CRANE SERVICE, INC. Emergency Service Available N° 4 4 6 5 0
2561 N. Purdue Ave • Fresno, CA 93727
P 7 Cranes Available
Ph. (559) 790-2578
15 ton • 22 ton • 28 ton
CUSTOMER r 40 ton with 120' reach
ADDRESS 75 ton with 160' reach
PHONE S FAx33
Cl 3R
110-120 ton with 200' reach
C AMOUNT
TOTAL
Customer is solely rasponsible for rigging the load.Midnight Crane employees may assist Customer in rigging the load,but neither Midnight Crane nor it's employees shall be held liable or assume any responsibility
for the riggings or any damage incurred as result of improper rigging.Slings and fittings are loaned to the Customer by Midnight Crane for the Customer's convenience,whatsoever concerning the conditlon of such
loaned equipment or it's fitness for the Customer's specific application.Customer will provide competent personnel,when needed.to direct of Flag,the operation of Midnight Crane.Accordance with American Standard
B30.2.1943 to direct of Flag Midnight Crane Equipment.Customer assumes all responsibility and liability or the adoquacy of design or strength of a lifting lugs or device,embedded in or attached to the load.Customer
responsible for any damage done to the load or crane while equipment is being operated under the work order.Any cable,sling or other equipment used where no rent is charged,are being used at Customers own risk.
Customer agrees to indemnify And defend Midnight Crane and holds it harmless for any loss or claim by other parties arising from the use of equipment.Customer hereby acknowledges that all driveways,
parking lots and all other surfaces over which the equipment is to be operated are sufficient stength to withstand the weight of this equipment and agrees to be solely responsible for any damage thereto.
CUSTOMER SIGNATURE DATE C.7O I