PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 12/14/2021
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#023
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Install additional piping,valves,and fittings per ASI 02 sheet P3.1,detail
"D".Add waste and water pipe and fittings to the ice maker location as
shown on Sheet R-A2.2 from ASI 03
Attachment(s):
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $3,093.25
Net Additive Calendar Days: DO
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date -$34,169.58
Adjusted Contract Dollar Amount: $11,330,330.42
Total Adjusted Calendar Days To Date: 30
Director's Change Order Limit Balance: $244,169.58
Adjusted Construction Completion Date: 10/26/21
Reviewed: Roger Davidson ��4V�—O —PST)
Architect
n
Reviewed: LaRue Goossen
Project Manager
Reviewed: Mandeep Sekhon
Construction Manager
Reviewed: Will Kettler 11 4—
Division Manager
Approved: Steven E. White sty E I &�V-
Steven E Wh,te(-22.20213019 PST)
Director
Approved: Steve Brandau NOT APPLICABLE
Board of Supervisors Chairman
Approval Date: Dec 22,2021
Scan and forward Director Approved Copy to: CAO Greg Reinke
Sheriffs Office Thomas Trester
PWP Business Office Kay Vang
Construction Manager Mandeep Sekhon
Staff Analyst Linda Guerra
Architect Roger Davidson
cot, County of Fresno
119 , Department of Public Works and Planning
p 1856 O Development Services&Capital Projects Division
Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 12/14/2021
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#023
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#023 is hereby approved by the County.
Scope of Work:
Install additional piping,valves,and fittings per ASI 02 sheet P3.1,detail
"D".Add waste and water pipe and fittings to the ice maker location as
shown on Sheet R-A2.2 from ASI 03
Attachment:
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $3,093.25
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: -$34,169.58
Adjusted Contract Dollar Amount: $11,330,330.42
Total Adjusted Calendar Days To Date: 30
Adjusted Construction Completion Date: 10/26/21
LaRue Goossen
LARue Goossen 1Dec 14,301111:o PST)
Project Manager Signature
Date: Dec 14,2021
By signing acceptance of this Change Order,the Contractor shall agree to the following.,
1.Provide all equipment material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
,dad pia/Ng
Accepted By: Klassen Corporation Roa--(e«0,20 PST)
Authorized Signature
Date: Dec 20,2021
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,StaffAnalyst
lindaeuerraWre snocountvea.Gov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
r App.Date Add Credit Rejected Pending Adj. Days Description
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 - $16,857.00 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
GGO 009 N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 - $572,775.76 Storage Bldg.electric
CCO 012 $32,245.91 Substation electrical
CCO 013 $112,372.79 Electrical plan update
CCO 014 $7,444.00 Blockout revised data room
CCO 015 - $14,657.00 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 - $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020 12/14/2021 $2,794.26 0 Install metal sill flashings
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
CCO 022
CCO 023 12/14/2021 $3,093.25 0 Install additional piping,valves,and fittings
CCO 024 $795.79 I Revised Architectural
CCO 025 11/22/2021 $8,355.00
CCO 026 $0.00 Metal Building Delay#1
Totals $127,330.42 -$161,500.001 $731,670.351 $33,041.701 Totals 30
K PCCO #023
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #023: Plumbing - ASI 02 & ASI 03
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 11/02/2021 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $ 3,093.25
DESCRIPTION:
CE#030-ASI 03-Add Waste&Water Pipe-Ice Maker
Add waste and water pipe and fittings to the Ice Maker location as shown on Sheet R-A2.2 from ASI03.
LaRue approved.
CE#032-ASI 02-Install Addit. Piping Valves &Fittings
Install additional piping,valves,and fittings per ASI02,sheet P3.1, Detail D.
ATTACHMENTS:
#4.FS at IM.pdf #2.WH Pipingpdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
023 1 Plumbing-ASI 02&ASI 03 3,093.25
TOTAL: $3,093.25
CHANGE ORDER LINE ITEMS:
PCO#023:Plumbing-ASI 02&ASI 03
# Cost Code Description Type Amount
1 15-400-Plumbing Fixtures Add Water Pipe&Fittings Subcontractor $2,457.00
2 15-400-Plumbing Fixtures Piping,Valves,&Fittings Subcontractor $295.00
Subtotal: $2,752.00
Fee:10.00%Applies to all line item types. 275.20
Insurance:1.40%Applies to all line item types. 38.53
Bond:1.00%Applies to all line item types. 27.52
Grand Total: $3,093.25
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 106,804.68
The contract sum prior to this PCCO was $ 11,471,304.68
The contract sum would be changed by this PCCO in the amount of $ 3,093.25
The new contract sum including this PCCO will be $ 11,474,397.93
The contract time will not be changed by this PCCO
Klassen Corporation page 1 of 2 Printed On: 12/10/2021 08:19 AM
T.P. Thomas Plumbing, Inc. License# 613719 CP# 4
P.O. Box 835 Phone 559-591-6499
Dinuba, California 93618 Fax 559-802-3306
Project: Sheriff's Substation Gen.Cont. Klassen Corp. Date: 4/14/2021
Attention: Rod I Jeremy
Ref: Floor Sink at Ice Maker Cost Proposal
1 Scope of Work
2
3 Add waste and water pipe and fittings to the Ice Maker location as shown on Sheet R-A2.2
4 from AS103. (Data Center)
5
6 Provide and install a Floor Sink.
8
9 Costs Description Extension Units Notes $per unit
10 MATERIAL
11 4"CAST IRON PIPE $ 74.50 10 $ 7.45
12 4 X 4 CAST IRON WYE $ 27.09 1 $ 27.09
13 4"C.I. 1/8 BEND $ 9.27 1 $ 9.27
14 4"C.I. P-TRAP $ 40.46 1 $ 40.46
15 4"NO HUB COUPLINGS $ 67.80 10 $ 6.78
16 SEE ATTACHED SHEET $ 718.57 (BALANCE OF MATERIAL)
17 SUBTOTAL MATERIAL $ 937.69
18 SALES TAX @ 8.25% $ 77.36
19 OVERHEAD&PROFIT @ 15% $ 152.26
20 TOTAL MATERIAL COST $ 1,167.31
21 EQUIPMENT
22 BOBCAT $ - 0 HRS-BOBCAT $ 30.00 PER HOUR
23 MINI EXCAVATOR $ 0 HRS-MINI EXCAVATOR $ 35.00 PER HOUR
24 BACKHOE $ 0 HRS-BACKHOE $ 40.00 PER HOUR
25 GENIE LIFT $ 0 HRS-GENIE LIFT $ 25.00 PER HOUR
26 OTHER: PICKUP/DELIVERY OF MATERIAL $ 0
27 MOBILIZATION $ 0
28 SUBTOTAL EQUIPMENT $
29 OVERHEAD&PROFIT @ 15% $ -
30 TOTAL EQUIPMENT COST $ -
31 LABOR
32 PLUMBER-JOURNEYMAN $ 981.72 12 'HRS-JOURNEYMAN PLMB 81.81 PER HOUR
33 PLUMBER-APPRENTICE $ - 0 'HRS-APPRENTICE 59.60 PER HOUR
34 UTILITY-Pipefitter $ 0 'HRS-UTILITY PIPEFITTER 47.00 PER HOUR
35 PLUMBER-PIPETRADES $ 0 'HRS-PIPETRADES 29.12 PER HOUR
36 ADMINISTRATIVE $ - 0 'HRS-ADMINISTRATIVE 45.00 PER HOUR
37 LABOR BURDEN ' Includes Benefits
38 JOURNEYMAN PLUMBER $ 119.87 12.21% EA.TAXES, INSURANCE
39 APPRENTICE $ - 12.92% EA.TAXES, INSURANCE
40 UTILITY-Pipefitter $ 15.73% EA.TAXES, INSURANCE
41 PIPETRADES $ 13.95% EA.TAXES, INSURANCE
42 ADMINISTRATIVE $ 13.95% EA.TAXES, INSURANCE
43 SUBTOTAL LABOR&LABOR BURDEN $ 1,101.59
44 OVERHEAD&PROFIT @ 15% $ 165.24
45 TOTAL LABOR&LABOR BURDEN $ 1,266.83
46
47 BOND COST? ® $ 23.12
48
49 TOTAL COST PROPOSAL $ 2,457 By: Mike Lansford, Mgr.
T.P. Thomas Plumbing, Inc. License# 613719 CP# 4 Page 2
P.O. Box 835 Phone 559-591-6499
Dinuba, California 93618 Fax 559-802-3306
Project: Sheriff's Substation Contractor: Klassen Corp. Date: 4/14/2021
Additional Material
48 Qtv Description Unit Cost Extended
49 1 COPPER PIPE,FITTINGS&VALVE $ 100.00 $ 100.00
50 1 FLOOR SINK $ 618.57 $ 618.57
51 $ - $ -
52 $ $
53 $ $
54 $ $
55 $ $
56 $ $
57 $ $
58 $ $
59 $ $ -
60 $ $ -
61 $ $ -
62 $ $ -
63 $ $ -
64 $ $
65 $ $
66 $ $
67 $ $
68 $ $
69 $ $
70 $ $
71 $ $
72 $ $
73 $ $
74 $ - $
75 $ - $
76 $ - $
77 $ - $
78 $ - $
79 $ - $
80 $ - $
81 $ - $
82 $ - $
83 $ - $
84 $ - $
85 $ - $
86 $ - $
87 $ - $
88 $ - $ -
89 $ - $ -
90 $ - $ -
91 $ - $ -
92 $ - $ -
93 $ - $
94 $ - $
95 Total Material to Line 16 $ 719
T.P. Thomas Plumbing, Inc. License# 613719 CP# 2
P.O. Box 835 Phone 559-591-6499
Dinuba, California 93618 Fax 559-802-3306
Project: Sheriff's Substation Gen.Cont. KLASSEN CORP Date: 2/2/2021
Attention: ROD
Ref: AS1002 Cost Proposal
1 Scope of Work
2
3 Install additional piping, valves and fittings per AS102, sheet P3.1, Detail D.
4
5
6 Costs Description Extension Units Notes $per unit
8 MATERIAL
9 3/4"COPPER PIE $ 24.30 10 LF $ 2.43
10 3/4"PROPRESS MALE ADAPTERS $ 15.24 4 EA $ 3.81
11 3/4"x 1/2"PROPRESS TEE $ 25.50 6 EA $ 4.25
12 3/4"PROPRESS 90 ELBOW $ 14.75 5 EA $ 2.95
13 PETE'S PLUG $ 10.88 1 EA $ 10.88
14 3/4"CHECK VALVE $ 41.08 2 EA $ 20.54
15 1/2"PROPRESS FEMALE ADAPTER $ 2.52 1 EA $ 2.52
16 3/4"WATTS BALL VALVE $ 15.36 1 EA $ 15.36
17 SUBTOTAL MATERIAL $ 110.09
18 SALES TAX @ 8.25% $ 9.08
19 OVERHEAD&PROFIT @ 15% $ 17.88
20 TOTAL MATERIAL COST $ 137.05
21 EQUIPMENT
22 BOBCAT $ - 0 HRS-BOBCAT $ 30.00 PER HOUR
23 MINI EXCAVATOR $ 0 HRS-MINI EXCAVATOR $ 35.00 PER HOUR
24 BACKHOE $ 0 HRS-BACKHOE $ 40.00 PER HOUR
25 GENIE LIFT $ 0 HRS-GENIE LIFT $ 25.00 PER HOUR
26 OTHER: PICKUP/DELIVERY OF MATERIAL $ 0
27 MOBILIZATION $ 0
28 SUBTOTAL EQUIPMENT $
29 OVERHEAD&PROFIT @ 15% $ -
30 TOTAL EQUIPMENT COST $ -
31 LABOR
32 PLUMBER-JOURNEYMAN $ 122.72 1.5 'HRS-JOURNEYMAN PLMB 81.81 PER HOUR
33 PLUMBER-APPRENTICE $ - 0 'HRS-APPRENTICE 64.25 PER HOUR
34 UTILITY-Pipefitter $ 0 'HRS-UTILITY PIPEFITTER 47.00 PER HOUR
35 PLUMBER-PIPETRADES $ 0 'HRS-PIPETRADES 29.12 PER HOUR
36 ADMINISTRATIVE $ - 0 'HRS-ADMINISTRATIVE 45.00 PER HOUR
37 LABOR BURDEN ' Includes Benefits
38 JOURNEYMAN PLUMBER $ 14.98 12.21% EA.TAXES, INSURANCE
39 APPRENTICE $ - 12.92% EA.TAXES, INSURANCE
40 UTILITY-Pipefitter $ 15.73% EA.TAXES, INSURANCE
41 PIPETRADES $ 13.95% EA.TAXES, INSURANCE
42 ADMINISTRATIVE $ 13.95% EA.TAXES, INSURANCE
43 SUBTOTAL LABOR&LABOR BURDEN $ 137.70
44 OVERHEAD&PROFIT @ 15% $ 20.65
45 TOTAL LABOR&LABOR BURDEN $ 158.35
46
47 BOND COST? $ 0
48
49 TOTAL COST PROPOSAL $ 295 By: Mike Lansford, Mgr.
K PCCO #023
Klassen
corporation
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 2 of 2 Printed On: 12/10/2021 08:19 AM