HomeMy WebLinkAboutCCO 023.pdf cot�,y County of Fresno Department of Public Works and Planning 6 O� 5 Development Services&Capital Projects Division FRES Steven E.White,Director PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST This Document is for Fresno County Internal Use Only Project: Fresno County Sheriff Area 2 Substation Contract No.: 19-S-04 Date: 12/14/2021 Contractor: Klassen Corporation Architect: Roger Davidson Change Order No.: CCO#023 Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00 Change Order Allowance: $568,225.00 Director's Change Order Limit: $210,000.00 Contract Time(Calendar Days): 322 Construction Start Date: 11/09/20 Original Construction Completion Date: 9/26/21 Change Order Scope of Work: Install additional piping,valves,and fittings per ASI 02 sheet P3.1,detail "D".Add waste and water pipe and fittings to the ice maker location as shown on Sheet R-A2.2 from ASI 03 Attachment(s): PCO proposal and support docs Net Additive Change Order Dollar Amount: $3,093.25 Net Additive Calendar Days: DO Net Deductive Change Order Dollar Amount: Net Deductive Calendar Days: �0 Total Change Order Dollar Amount To Date -$34,169.58 Adjusted Contract Dollar Amount: $11,330,330.42 Total Adjusted Calendar Days To Date: 30 Director's Change Order Limit Balance: $244,169.58 Adjusted Construction Completion Date: 10/26/21 Reviewed: Roger Davidson ��4V�—O —PST) Architect n Reviewed: LaRue Goossen Project Manager Reviewed: Mandeep Sekhon Construction Manager Reviewed: Will Kettler 11 4— Division Manager Approved: Steven E. White sty E I &�V- Steven E Wh,te(-22.20213019 PST) Director Approved: Steve Brandau NOT APPLICABLE Board of Supervisors Chairman Approval Date: Dec 22,2021 Scan and forward Director Approved Copy to: CAO Greg Reinke Sheriffs Office Thomas Trester PWP Business Office Kay Vang Construction Manager Mandeep Sekhon Staff Analyst Linda Guerra Architect Roger Davidson cot, County of Fresno 119 , Department of Public Works and Planning p 1856 O Development Services&Capital Projects Division Steven E.White,Director CONTRACT CHANGE ORDER Project: Fresno County Sheriff Area 2 Substation Contract No.: 19-S-04 Date: 12/14/2021 Contractor: Klassen Corporation 2021 Westwind Drive Bakersfield,California 93301 (661)324-3900 Change Order No.: CCO#023 Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00 Original Construction Completion Date: 09/26/21 CCO#023 is hereby approved by the County. Scope of Work: Install additional piping,valves,and fittings per ASI 02 sheet P3.1,detail "D".Add waste and water pipe and fittings to the ice maker location as shown on Sheet R-A2.2 from ASI 03 Attachment: PCO proposal and support docs Net Additive Change Order Dollar Amount: $3,093.25 Net Additive Calendar Days: �0 Net Deductive Change Order Dollar Amount: $0.00 Net Deductive Calendar Days: �0 Total Change Order Dollar Amount To Date: -$34,169.58 Adjusted Contract Dollar Amount: $11,330,330.42 Total Adjusted Calendar Days To Date: 30 Adjusted Construction Completion Date: 10/26/21 LaRue Goossen LARue Goossen 1Dec 14,301111:o PST) Project Manager Signature Date: Dec 14,2021 By signing acceptance of this Change Order,the Contractor shall agree to the following., 1.Provide all equipment material,labor and services required to complete the Scope of Work specified in this Change Order. 2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full. In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05, Article VI shall apply. ,dad pia/Ng Accepted By: Klassen Corporation Roa--(e«0,20 PST) Authorized Signature Date: Dec 20,2021 When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to: Linda Guerra,StaffAnalyst lindaeuerraWre snocountvea.Gov Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division 2220 Tulare Street,Eighth Floor Fresno,CA. 93721 CHANGE ORDER SUMMARY Project Sheriff Substation r App.Date Add Credit Rejected Pending Adj. Days Description CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee CCO 002 - $16,857.00 Revised site grades CCO 003 8/30/2021 $0.00 2 Rain delays CCO 004 8/30/2021 $0.00 2 Rain delays CCO 005 8/30/2021 $0.00 13 Rain delays CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG GGO 009 N/A CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing CCO 011 - $572,775.76 Storage Bldg.electric CCO 012 $32,245.91 Substation electrical CCO 013 $112,372.79 Electrical plan update CCO 014 $7,444.00 Blockout revised data room CCO 015 - $14,657.00 Additional work in large data room CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy CCO 017 - $7,563.80 0 Mechanical hangers CCO 018 9/16/2021 $0.00 0 Date adjustments CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions CCO 020 12/14/2021 $2,794.26 0 Install metal sill flashings CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall CCO 022 CCO 023 12/14/2021 $3,093.25 0 Install additional piping,valves,and fittings CCO 024 $795.79 I Revised Architectural CCO 025 11/22/2021 $8,355.00 CCO 026 $0.00 Metal Building Delay#1 Totals $127,330.42 -$161,500.001 $731,670.351 $33,041.701 Totals 30 K PCCO #023 Klassen corporation Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub 2021 Westwind Dr 1129 North Armstrong Avenue Bakersfield,California 93301 Fresno,California 93727 Phone:(661)324-3000 Phone: Fax:(661)324-3900 Fax: Prime Contract Change Order #023: Plumbing - ASI 02 & ASI 03 CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime 2220 Tulare Street,8th FI Contract Fresno,California 93721 DATE CREATED: 11/02/2021 CREATED BY: Emma Smith(KLASSEN CORPORATION) CONTRACT STATUS: Pending-In Review REVISION: 0 CHANGE REASON: SCHEDULE IMPACT: TOTAL AMOUNT: $ 3,093.25 DESCRIPTION: CE#030-ASI 03-Add Waste&Water Pipe-Ice Maker Add waste and water pipe and fittings to the Ice Maker location as shown on Sheet R-A2.2 from ASI03. LaRue approved. CE#032-ASI 02-Install Addit. Piping Valves &Fittings Install additional piping,valves,and fittings per ASI02,sheet P3.1, Detail D. ATTACHMENTS: #4.FS at IM.pdf #2.WH Pipingpdf POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER: PCO# I Title Schedule Impact Amount 023 1 Plumbing-ASI 02&ASI 03 3,093.25 TOTAL: $3,093.25 CHANGE ORDER LINE ITEMS: PCO#023:Plumbing-ASI 02&ASI 03 # Cost Code Description Type Amount 1 15-400-Plumbing Fixtures Add Water Pipe&Fittings Subcontractor $2,457.00 2 15-400-Plumbing Fixtures Piping,Valves,&Fittings Subcontractor $295.00 Subtotal: $2,752.00 Fee:10.00%Applies to all line item types. 275.20 Insurance:1.40%Applies to all line item types. 38.53 Bond:1.00%Applies to all line item types. 27.52 Grand Total: $3,093.25 The original(Contract Sum) $ 11,364,500.00 Net change by previously authorized PCCO $ 106,804.68 The contract sum prior to this PCCO was $ 11,471,304.68 The contract sum would be changed by this PCCO in the amount of $ 3,093.25 The new contract sum including this PCCO will be $ 11,474,397.93 The contract time will not be changed by this PCCO Klassen Corporation page 1 of 2 Printed On: 12/10/2021 08:19 AM T.P. Thomas Plumbing, Inc. License# 613719 CP# 4 P.O. Box 835 Phone 559-591-6499 Dinuba, California 93618 Fax 559-802-3306 Project: Sheriff's Substation Gen.Cont. Klassen Corp. Date: 4/14/2021 Attention: Rod I Jeremy Ref: Floor Sink at Ice Maker Cost Proposal 1 Scope of Work 2 3 Add waste and water pipe and fittings to the Ice Maker location as shown on Sheet R-A2.2 4 from AS103. (Data Center) 5 6 Provide and install a Floor Sink. 8 9 Costs Description Extension Units Notes $per unit 10 MATERIAL 11 4"CAST IRON PIPE $ 74.50 10 $ 7.45 12 4 X 4 CAST IRON WYE $ 27.09 1 $ 27.09 13 4"C.I. 1/8 BEND $ 9.27 1 $ 9.27 14 4"C.I. P-TRAP $ 40.46 1 $ 40.46 15 4"NO HUB COUPLINGS $ 67.80 10 $ 6.78 16 SEE ATTACHED SHEET $ 718.57 (BALANCE OF MATERIAL) 17 SUBTOTAL MATERIAL $ 937.69 18 SALES TAX @ 8.25% $ 77.36 19 OVERHEAD&PROFIT @ 15% $ 152.26 20 TOTAL MATERIAL COST $ 1,167.31 21 EQUIPMENT 22 BOBCAT $ - 0 HRS-BOBCAT $ 30.00 PER HOUR 23 MINI EXCAVATOR $ 0 HRS-MINI EXCAVATOR $ 35.00 PER HOUR 24 BACKHOE $ 0 HRS-BACKHOE $ 40.00 PER HOUR 25 GENIE LIFT $ 0 HRS-GENIE LIFT $ 25.00 PER HOUR 26 OTHER: PICKUP/DELIVERY OF MATERIAL $ 0 27 MOBILIZATION $ 0 28 SUBTOTAL EQUIPMENT $ 29 OVERHEAD&PROFIT @ 15% $ - 30 TOTAL EQUIPMENT COST $ - 31 LABOR 32 PLUMBER-JOURNEYMAN $ 981.72 12 'HRS-JOURNEYMAN PLMB 81.81 PER HOUR 33 PLUMBER-APPRENTICE $ - 0 'HRS-APPRENTICE 59.60 PER HOUR 34 UTILITY-Pipefitter $ 0 'HRS-UTILITY PIPEFITTER 47.00 PER HOUR 35 PLUMBER-PIPETRADES $ 0 'HRS-PIPETRADES 29.12 PER HOUR 36 ADMINISTRATIVE $ - 0 'HRS-ADMINISTRATIVE 45.00 PER HOUR 37 LABOR BURDEN ' Includes Benefits 38 JOURNEYMAN PLUMBER $ 119.87 12.21% EA.TAXES, INSURANCE 39 APPRENTICE $ - 12.92% EA.TAXES, INSURANCE 40 UTILITY-Pipefitter $ 15.73% EA.TAXES, INSURANCE 41 PIPETRADES $ 13.95% EA.TAXES, INSURANCE 42 ADMINISTRATIVE $ 13.95% EA.TAXES, INSURANCE 43 SUBTOTAL LABOR&LABOR BURDEN $ 1,101.59 44 OVERHEAD&PROFIT @ 15% $ 165.24 45 TOTAL LABOR&LABOR BURDEN $ 1,266.83 46 47 BOND COST? ® $ 23.12 48 49 TOTAL COST PROPOSAL $ 2,457 By: Mike Lansford, Mgr. T.P. Thomas Plumbing, Inc. License# 613719 CP# 4 Page 2 P.O. Box 835 Phone 559-591-6499 Dinuba, California 93618 Fax 559-802-3306 Project: Sheriff's Substation Contractor: Klassen Corp. Date: 4/14/2021 Additional Material 48 Qtv Description Unit Cost Extended 49 1 COPPER PIPE,FITTINGS&VALVE $ 100.00 $ 100.00 50 1 FLOOR SINK $ 618.57 $ 618.57 51 $ - $ - 52 $ $ 53 $ $ 54 $ $ 55 $ $ 56 $ $ 57 $ $ 58 $ $ 59 $ $ - 60 $ $ - 61 $ $ - 62 $ $ - 63 $ $ - 64 $ $ 65 $ $ 66 $ $ 67 $ $ 68 $ $ 69 $ $ 70 $ $ 71 $ $ 72 $ $ 73 $ $ 74 $ - $ 75 $ - $ 76 $ - $ 77 $ - $ 78 $ - $ 79 $ - $ 80 $ - $ 81 $ - $ 82 $ - $ 83 $ - $ 84 $ - $ 85 $ - $ 86 $ - $ 87 $ - $ 88 $ - $ - 89 $ - $ - 90 $ - $ - 91 $ - $ - 92 $ - $ - 93 $ - $ 94 $ - $ 95 Total Material to Line 16 $ 719 T.P. Thomas Plumbing, Inc. License# 613719 CP# 2 P.O. Box 835 Phone 559-591-6499 Dinuba, California 93618 Fax 559-802-3306 Project: Sheriff's Substation Gen.Cont. KLASSEN CORP Date: 2/2/2021 Attention: ROD Ref: AS1002 Cost Proposal 1 Scope of Work 2 3 Install additional piping, valves and fittings per AS102, sheet P3.1, Detail D. 4 5 6 Costs Description Extension Units Notes $per unit 8 MATERIAL 9 3/4"COPPER PIE $ 24.30 10 LF $ 2.43 10 3/4"PROPRESS MALE ADAPTERS $ 15.24 4 EA $ 3.81 11 3/4"x 1/2"PROPRESS TEE $ 25.50 6 EA $ 4.25 12 3/4"PROPRESS 90 ELBOW $ 14.75 5 EA $ 2.95 13 PETE'S PLUG $ 10.88 1 EA $ 10.88 14 3/4"CHECK VALVE $ 41.08 2 EA $ 20.54 15 1/2"PROPRESS FEMALE ADAPTER $ 2.52 1 EA $ 2.52 16 3/4"WATTS BALL VALVE $ 15.36 1 EA $ 15.36 17 SUBTOTAL MATERIAL $ 110.09 18 SALES TAX @ 8.25% $ 9.08 19 OVERHEAD&PROFIT @ 15% $ 17.88 20 TOTAL MATERIAL COST $ 137.05 21 EQUIPMENT 22 BOBCAT $ - 0 HRS-BOBCAT $ 30.00 PER HOUR 23 MINI EXCAVATOR $ 0 HRS-MINI EXCAVATOR $ 35.00 PER HOUR 24 BACKHOE $ 0 HRS-BACKHOE $ 40.00 PER HOUR 25 GENIE LIFT $ 0 HRS-GENIE LIFT $ 25.00 PER HOUR 26 OTHER: PICKUP/DELIVERY OF MATERIAL $ 0 27 MOBILIZATION $ 0 28 SUBTOTAL EQUIPMENT $ 29 OVERHEAD&PROFIT @ 15% $ - 30 TOTAL EQUIPMENT COST $ - 31 LABOR 32 PLUMBER-JOURNEYMAN $ 122.72 1.5 'HRS-JOURNEYMAN PLMB 81.81 PER HOUR 33 PLUMBER-APPRENTICE $ - 0 'HRS-APPRENTICE 64.25 PER HOUR 34 UTILITY-Pipefitter $ 0 'HRS-UTILITY PIPEFITTER 47.00 PER HOUR 35 PLUMBER-PIPETRADES $ 0 'HRS-PIPETRADES 29.12 PER HOUR 36 ADMINISTRATIVE $ - 0 'HRS-ADMINISTRATIVE 45.00 PER HOUR 37 LABOR BURDEN ' Includes Benefits 38 JOURNEYMAN PLUMBER $ 14.98 12.21% EA.TAXES, INSURANCE 39 APPRENTICE $ - 12.92% EA.TAXES, INSURANCE 40 UTILITY-Pipefitter $ 15.73% EA.TAXES, INSURANCE 41 PIPETRADES $ 13.95% EA.TAXES, INSURANCE 42 ADMINISTRATIVE $ 13.95% EA.TAXES, INSURANCE 43 SUBTOTAL LABOR&LABOR BURDEN $ 137.70 44 OVERHEAD&PROFIT @ 15% $ 20.65 45 TOTAL LABOR&LABOR BURDEN $ 158.35 46 47 BOND COST? $ 0 48 49 TOTAL COST PROPOSAL $ 295 By: Mike Lansford, Mgr. K PCCO #023 Klassen corporation Klassen Corporation Fresno Co.Dept of Public Works 2220 Tulare Street,8th FI Fresno California 93721 SIGNATURE DATE SIGNATURE DATE Klassen Corporation page 2 of 2 Printed On: 12/10/2021 08:19 AM