PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 12/14/2021
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#020
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Fabricate and install new metal sill flashing at window of tower per the
provided detail
Attachment(s):
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $2,794.26
Net Additive Calendar Days: DO
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date -$37,262.83
Adjusted Contract Dollar Amount: $11,327,237.17
Total Adjusted Calendar Days To Date: 30
Director's Change Order Limit Balance: $247,262.83
Adjusted Construction Completion Date: 10/26/21
Reviewed: Roger Davidson PLaVIDON
Architect
Reviewed: LaRue Goossen „e,De u.zo=logs Ps„
Pro'ect Manager
Reviewed: Mandeep Sekhon S-"C
Construction Manager
Reviewed: Will Kettler
Division Manager
Approved: Steven E. White sty is w!�
Steven E WhRe(Dec 22,202]3018 P81)
Director
Approved: Steve Brandau NOT APPLICABLE
Board of Supervisors Chairman
Approval Date: Dec 22,2021
Scan and forward Director Approved Copy to: CAO Greg Reinke
Sheriffs Office Thomas Trester
PWP Business Office Kay Vang
Construction Manager Mandeep Sekhon
Staff Analyst Linda Guerra
Architect Roger Davidson
cot, County of Fresno
119 , Department of Public Works and Planning
p 1856 O Development Services&Capital Projects Division
Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 12/14/2021
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#020
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#020 is hereby approved by the County.
Scope of Work:
Fabricate and install new metal sill flashing at window of tower per the
provided detail
Attachment:
PCO proposal and support docs
Net Additive Change Order Dollar Amount: $2,794.26
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: -$37,262.83
Adjusted Contract Dollar Amount: $11,327,237.17
Total Adjusted Calendar Days To Date: 30
Adjusted Construction Completion Date: 10/26/21
LaRue Goossen
RProject Manager Signature
Date: Dec 14,2021
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
Accepted 8 : Klassen Corporation AVOW�Q�H202115 Acce
p Y p rsoa as�e me<aa, ae asn
Authorized Signature
Date: Dec 20,2021
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,StaffAnalyst
lindaeuerraWre snocountvea.Gov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project Sheriff Substation
r App.Date Add Credit Rejected Pending Adj. Days Description
CCO 001 8/30/2021 $685.00 0 Water board-SMARTS fee
CCO 002 - $16,857.00 Revised site grades
CCO 003 8/30/2021 $0.00 2 Rain delays
CCO 004 8/30/2021 $0.00 2 Rain delays
CCO 005 8/30/2021 $0.00 13 Rain delays
CCO 006 8/30/2021 $6,870.55 5 Storage BLDG drain elevation
CCO 007 8/30/2021 $1,745.00 3 Substation floor sink install
CCO 008 8/30/2021 $7,614.33 5 Operable partition wall FTG
GGO 009 N/A
CCO 010 8/30/2021 $89,889.80 0 Block wall for fencing
CCO 011 - $572,775.76 Storage Bldg.electric
CCO 012 $32,245.91 Substation electrical
CCO 013 $112,372.79 Electrical plan update
CCO 014 $7,444.00 Blockout revised data room
CCO 015 - $14,657.00 Additional work in large data room
CCO 016 8/30/2021 -$161,500.00 0 Delete Large Canopy
CCO 017 - $7,563.80 0 Mechanical hangers
CCO 018 9/16/2021 $0.00 0 Date adjustments
CCO 019 9/21/2021 $2,884.00 0 Folding Wall Revisions
CCO 020 12/14/2021 $2,794.26 0 Install metal sill flashings
CCO 021 11/16/2021 $3,399.23 0 Install Wedge Anchors at Exterior Wall
CCO 022
CCO 023
CCO 024 $795.79 Revised Architectural
CCO 025 11/22/2021 $8,355.00
CCO 026 $0.00 Metal Building Delay#1
Totals $124,237.17 -$161,500.001 $731,670.351 $33,041.701 Totals 30
K PCCO #020
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #020: Fabricate & Install Metal Sill
Flashings
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 10/25/2021 CREATED BY: Emma Smith(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $2,794.26
DESCRIPTION:
CE#024-Fabricate&Install Metal Sill Flashings
Fabricate and install new metal sill flashing at window of tower per the provided detail.
ATTACHMENTS:
Graham Prewett-JP02.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
021 1 CE#024-Fabricate&Install 2,794.26
TOTAL: $2,794.26
CHANGE ORDER LINE ITEMS:
PCO#021 :CE#024-Fabricate 8r Install
# Cost Code Description Type Amount
1 07-500-Membrane Roofing Subcontractor $2,486.00
Subtotal: $2,486.00
Klassen OH&P:10.00%Applies to all line item types. 248.60
Bond:1.00%Applies to all line item types. 24.86
Insurance:1.40%Applies to all line item types. 34.80
Grand Total: $2,794.26
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 106,804.68
The contract sum prior to this PCCO was $ 11,471,304.68
The contract sum would be changed by this PCCO in the amount of $ 2,794.26
The new contract sum including this PCCO will be $ 11,474,098.94
The contract time will not be changed by this PCCO
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On: 12/13/2021 11 :15 AM
559Q91-3741
fax 5591291-5082
&P 2773 North Business Park Avenue#102
Fresno,Caldonnta 93727
GRAMAMPAfJd!►t71,Mr, License u 793065
CHANGE ORDER
To: Klassen Corp Date: lo/18/2021
Project Name:
Fresno Sheriff Substation
Attention: Curtis Gardner Project Reference No:
GPI Job No: 1626
Change Order No: 1Po?
Original Contract Amount ....................................................$
Previous Change Order Amount(s) .......................................$
This Change Order...............................................................$ 2,486.00
Revised Contract Amount ................................................... $
Description:
Fabricate and install new metal sill flashings at window of tower per the provided detail.
Material-$670.00
Labor- ....$1,492.00
P/0..........$324.00
Total . ..$2,486.00
Graham Prewett, Inc.
John Powers / Project Manager
Print Name/Title Print Name/Title
�o>�in J"osYers
Signature Signature
10/18/2021
Date Date
30'-0"
PLAN DIMENSION PLAN
SEE POOR PIMEN
01 SCHEDULE 01
AlJS Al
O
'N
T poop 7
Mf OPENING
FIN FIN At
FLR FLR
ff]ALUMINUM FRAME [K]ALUMINUM FRAME [E]ALUMiNum FRAME ALUMINUM FRAME QALUMINUM FRAME
104INvon vill,lpor4 Y(114001`4 MIND01"l WINDOW
PLAN
DIMEN
Ala
DOOR
.50_O'�Al 5014ev 6`0"(2 EO SPCS)
Is
A M4
Nil
ALUMINUM FRAME
126-�,
1 SIM Nil
Al qe U, �4 ill 1/2*&LA59
SIM
WINDOWWINDOWa /150OR NOT USED A44 M/21 MIL
ALUMINUM FRAME U, gpN.& SIM SECURITY
WINDOWU,In FILM
FIN E14 FIN FIN
A44
FL5
[DINTERIOR ALUMINUM [E]INTERIOR ALUMINUM BINTERIOR ALUMINUM
DOOR FRAME FRAME V41NOOH FRAME TRANSACTION
J"111,1001"l
WINDOW AND FRAME ELEVATIONS 0 6" 4- 11, 12'
A42 SCALE:1/4"-1'-O"
.0.
REVISION
/10\ 06-17.2021
CUSTOM SUNSHADE Y41 3'SQUARE
N FASCIA,SQUARE OUTRI66EK
6"Aluminum 11 ALUMINUM r
N AND UNIVERSAL CURTAIN WALL
F
BRACKET
rame
q, 1.,
TFO ROOFING 0/TAPERED
15/32 Ply INSULATION
12 11/4
0 L--------------------------------------------------------------------------------------------------------------
------------------------ -------------------------------------------------------------
- ---------------------------------------------------------------------------4------------
PREFINISWED
METAL FASCIA 0/
OFOAM SHAPE
--------------------------------------------------------------------------------------------------------------
z. 4'-0' 2-
\-PREFINISNED METAL Sheet No.
SOFFIT PANEL
ALMXMW CURTAIN WALL
F MrN6 SYSTEM
XNSULATCO GLASSA7 . 2
A72qVERTICAL DETAIL
SCALE:9"-1'4r