HomeMy WebLinkAboutCCO 018.pdf o C0U� County of Fresno
Department of Public Works and Planning
t� f RES�O Development Services&Capital Projects Division
Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 2/3/2022
Contractor: Klassen Corporation
Architect: Roger Davidson
Change Order No.: CCO#018
Construction Contract Dollar Amount(as awarded on 08/10/20) $11,364,500.00
Change Order Allowance: $568,225.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 322
Construction Start Date: 11/09/20
Original Construction Completion Date: 9/26/21
Change Order Scope of Work:
Correction to Construction Start Date,Original Construction Completion date,
and Adjusted Construction Completion date on PCOs per contract agreement,
NTP issued to contractor,and approved PCOs 3,4,5,6,7,and 8.
Attachment(s):
NTP and Contractor coversheets for PCOs 3,4,5,6,7,and 8.
Net Additive Change Order Dollar Amount:
Net Additive Calendar Days: DO
Net Deductive Change Order Dollar Amount:
Net Deductive Calendar Days: DO
Total Change Order Dollar Amount To Date -$54,695.32
Adjusted Contract Dollar Amount: $11,309,804.68
Total Adjusted Calendar Days To Date: 30
Director's Change Order Limit Balance: $264,695.32
Adjusted Construction Completion Date: 10/26/21
ya'a�ra'mh
Reviewed: Roger Davidson ,ear,e,o,F.e3,zoz 3,Psn
Architect
41L..a.�
Reviewed: LaRue Goossen .0 Genssen„e,,,,o;,,,,,PST)
1P�ro(j�ecct Manager
Reviewed: Mandeep Sekhon "�"S' ^
Construction Manager
Approved: Will Kettler
Division Manager
Approved: Steven E. White sic a C-whzlo-
White(-4,2022 08 33Psp
Director
Approved: Brian Pacheco Not Applicable
Board of Supervisors Chairman
Approval Date: Feb 4,2022
Scan and forward Director Approved Copy to: CAO Paul Nerland
Sheriffs Office Thomas Trester
PWP Business Office Kay Vang
Staff Analyst Linda Guerra
co��.,� County of Fresno
Department of Public Works and Planning
Development Services&Capital Projects Division
FRES Steven E.White,Director
CONTRACT CHANGE ORDER
Project: Fresno County Sheriff Area 2 Substation
Contract No.: 19-S-04
Date: 9/15/2021
Contractor: Klassen Corporation
2021 Westwind Drive
Bakersfield,California 93301
(661)324-3900
Change Order No.: CCO#018
Construction Contract Dollar Amount(as awarded on 08/10/20): $11,364,500.00
Original Construction Completion Date: 09/26/21
CCO#018 is hereby approved by the County.
Scope of Work:
Correction to Construction Start Date,Original Construction Completion
date,and Adjusted Construction Completion date on PCOs per contract
agreement, NTP issued to contractor,and approved PCOs 3,4,5,6,7,
and 8.
Attachment:
NTP and Contractor coversheets for PCOs 3,4,5,6,7,and 8.
Net Additive Change Order Dollar Amount: $0.00
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date: -$47,131.52
Adjusted Contract Dollar Amount: $11,317,368.48
Total Adjusted Calendar Days To Date: 30
Adjusted Construction Completion Date: 10/26/21
LaRue Goossen
Project Manager Signature
Date: Sep 16,2021
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
Accepted By: Klassen Corporation
Authorized Signature
Date: Feb 3,2022
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
lindaguerra@fresnocountyea.gov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
s
°
c o
o _0
(D N LL 0 m
a) C =
cc 0) U .�. m >,
Q Fu c 3 C .a m m m m o
m E
d
'm o � d t3 n -0 - c m
rn C7 ° " w a°i c U m a°i
E _ N w y �° m o o a m '> ° m r E
°�
00 N m N m m O N — m O °- m m 0 0
9 9 m
O o Co m Co
coom 0 @ U U N U
r
v> O Z m v> w w m Q
ui
N
m
0
rn
vi
Cl! 't
CN N
M
� M
O fl� rl� O O It?
cc M 7 0 O
rr
t4
0 o p
0 o p
0
u�
e9 p
�s
O O O O um7. O M W O co
LO O O O O 0 V m Cl) O �
(0 v> E» cs� c n_ m c L �' cOD
ss EH 00 fA
V3
N
m
O
F
C
O
N
7
Q N
cn
W
0
O
W
CD N M -e LO O H O
Z 5 O O O O O O O O
a) O O O O O O O O O O O O O O O O O
_ 'p O O O O O O O O O O O O O O O O O
U a U U U U U U U U U U U U U U U U U
K
PCCO #003
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax: (661)324-3900 Fax:
Prime Contract Change Order #003: CE #003 - Rain Delays
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 12/15/2020 CREATED BY: Tayler Wells(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT: 2 days
TOTAL AMOUNT: $ 0.00
DESCRIPTION:
CE#003-Rain Delays
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
003 1 CE#003-Rain Delays 0.00
TOTAL: $0.00
CHANGE ORDER LINE ITEMS:
PCO#003:CE#003-Rain Delays
# Cost Code Description Type Amount
1 11/18/20 $0.00
2 12/14/20 $0.00
Subtotal: $0.00
Grand Total: $0.00
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 0.00
The contract sum prior to this PCCO was $ 11,364,500.00
The contract sum would be changed by this PCCO in the amount of $ 0.00
The new contract sum including this PCCO will be $ 11,364,500.00
The contract time will be increased by this PCCO by 2 days
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On: 12/15/2020 09:41 AM
K PCCO #004
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #004: CE #003 - Rain Delays
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 12/28/2020 CREATED BY: Tayler Wells(KLASSEN CORPORATION)
CONTRACT STATUS: Approved REVISION: 0
CHANGE REASON: SCHEDULE IMPACT: 2 days
TOTAL AMOUNT: $0.00
DESCRIPTION:
CE#003-Rain Delays
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
004 1 CE#003-Rain Delays 0.00
TOTAL: $0.00
CHANGE ORDER LINE ITEMS:
PCO#004:CE#003-Rain Delays
# Cost Code Description Type Amount
1 12/15120 $0.00
2 12/16120 $0.00
Subtotal: $0.00
Grand Total: $0.00
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 105,059.68
The contract sum prior to this PCCO was $ 11,469,569.68
The contract sum will not be changed by this PCCO in the amount of $0.00
The new contract sum including this PCCO will be $ 11,469,559.68
The contract time will be increased by this PCCO by 2 days
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On:9/7/2021 08:17 AM
K
PCCO #005
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax: (661)324-3900 Fax:
Prime Contract Change Order #005: CE #003 - Rain Delays 3
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 2/08/2021 CREATED BY: Tayler Wells(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT:
TOTAL AMOUNT: $ 0.00
DESCRIPTION:
CE#003-Rain Delays
ATTACHMENTS:
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
005 1 CE#003-Rain Delays 3 0.00
TOTAL: $0.00
CHANGE ORDER LINE ITEMS:
PCO#005:CE#003-Rain Delays 3
# Cost Code Description Type Amount
1 1/26/21 $0.00
2 1/27/21 $0.00
3 1/28/21 $0.00
4 1/29/21 $0.00
5 2/1/21 $0.00
6 2/2/21 $0.00
7 2/3/21 $0.00
8 12/17/20 $0.00
9 12/18/20 $0.00
10 12/28/20 $0.00
11 12/29/20 $0.00
12 12/30/20 $0.00
13 1/25/21 $0.00
Subtotal: $0.00
Grand Total: $0.00
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 0.00
The contract sum prior to this PCCO was $ 11,364,500.00
The contract sum would be changed by this PCCO in the amount of $ 0.00
The new contract sum including this PCCO will be $ 11,364,500.00
The contract time will not be changed by this PCCO
Klassen Corporation page 1 of 2 Printed On:2/8/2021 11 :56 AM
K
PCCO #005
Klassen
corporation
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 2 of 2 Printed On:2/8/2021 11 :56 AM
K
PCCO #006
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax: (661)324-3900 Fax:
Prime Contract Change Order #006: Storage Bid Floor Drain Elevations
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 2/18/2021 CREATED BY: Rod Paine(KLASSEN CORPORATION)
CONTRACT STATUS: Draft REVISION: 0
CHANGE REASON: SCHEDULE IMPACT: 5 days
TOTAL AMOUNT: $6,870.55
DESCRIPTION:
CE#004-Storage Bld Floor Drain Elevations
Provide pricing for drainage slopes to floor drains per attached response and drawing.
ATTACHMENTS:
RFI 19 Response(1-12-2021).pdf RFQ Response.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
006 1 Storage Bid Floor Drain Elevations 5 days 6,870.55
TOTAL: $6,870.55
CHANGE ORDER LINE ITEMS:
PCO#006:Storage Bid Floor Drain Elevations
# Cost Code Description Type Amount
1 03-300-Cast-in-Place Concrete Storage Bld Floor Drain Slopes Subcontractor $5,851.55
2 20-600-Financials,Bonds Bond 1% Other $59.00
3 20-800-Financials,Builder's Risk Insurance 1.4% Other $82.00
4 20-500-Financials,Construction Profit Fee 10% Other $878.00
Subtotal: $6,870.55
Grand Total: $6,870.55
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 0.00
The contract sum prior to this PCCO was $ 11,364,500.00
The contract sum would be changed by this PCCO in the amount of $ 6,870.55
The new contract sum including this PCCO will be $ 11,371,370.55
The contract time will be increased by this PCCO by 5 days
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On:2/18/2021 08:46 AM
PCCO #007
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax:(661)324-3900 Fax:
Prime Contract Change Order #007: ASI 06 Substation Floor Sink
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035:Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 2/2412021 CREATED BY: Rod Paine(KLASSEN CORPORATION)
CONTRACT STATUS: Pending-In Review REVISION: 0
CHANGE REASON: SCHEDULE IMPACT: 3 days
TOTAL AMOUNT: $1,745.00
DESCRIPTION:
CE#008-ASI 06 Substation Floor Sink
Provide and install floor sink,countersink and water filtration.per attached ASI#06 Drawings
ATTACHMENTS:
#3 d Plumbing Plan-P2.3.pdf P3.1R-Schedules and Details
Revised P3 1 R SCHEDULES AND DETAILS PDF P2 2R-Enlarged Plumbing Plan-P2 2 pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# Title Schedule impact Amount
007 1 ASI 06 Substation Floor Sink t 3 days 1,745.00
TOTAL: $1,745.00
CHANGE ORDER LINE ITEMS:
PCO#007:ASI 06 Substation Floor Sink!Water Filter i Faucet
# Cost Code Description Type Amount
1 15-400-Plumbing Fixtures ASI 06 Substation Floor Sink Subcontractor $1,553.00
2 2M00-Financials,Bonds Bond 1% Other $15.00
3 20-800-Financials,Builder's Risk Insurance 1.4% Other $22.00
4 20-500-Financials,Construction Profit Fee 10% Other $155.00
Subtotal: $1,745.00
Grand Total: jl� 745.00
The original(Contract Sum) $11,364,500.00
Net change by previously authorized PCCO $0.00
The contract sum prior to this PCCO was $ 11,364,500.00
The contract sum would be changed by this PCCO in the amount of $ 1,745.00
The new contract sum includinq this PCCO will be $ 11,366,245.00
f hontract time will be increased by this PCCO by 3 days
Klassen Corporation Fresno Co.Dept of Public Works
2220 Tulare Street,8th FI
Fresno California 93721
SIGNATURE DATE SIGNATURE DATE
Klassen Corporation page 1 of 1 Printed On:3/9/2021 04:07 PM
K PCCO #008
Klassen
corporation
Klassen Corporation Project:05-3-20035-Fresno County Sheriff Sub
2021 Westwind Dr 1129 North Armstrong Avenue
Bakersfield,California 93301 Fresno,California 93727
Phone:(661)324-3000 Phone:
Fax: (661)324-3900 Fax:
Prime Contract Change Order #008: Operable Wall Footing
CONTRACT COMPANY: Fresno Co.Dept of Public Works CONTRACT FOR: 05-3-20035 :Fresno County Sheriff Sub Prime
2220 Tulare Street,8th FI Contract
Fresno,California 93721
DATE CREATED: 3/08/2021 CREATED BY: Rod Paine(KLASSEN CORPORATION)
CONTRACT STATUS: Draft REVISION: 0
CHANGE REASON: SCHEDULE IMPACT: 5 days
TOTAL AMOUNT: $7,614.33
DESCRIPTION:
CE#011 -Operable Wall Footing
Provide footing per Drawings dated 1-30-19
ATTACHMENTS:
COR 2 Partition Wall Footings-Google Docs.pdf Folding Partition Footing Layout(02-24-2021.pdf
POTENTIAL CHANGE ORDERS IN THIS CHANGE ORDER:
PCO# I Title Schedule Impact Amount
008 1 Operable Wall Footing 5 days 7,614.33
TOTAL: $7,614.33
CHANGE ORDER LINE ITEMS:
PCO#008:Operable Wall Footing
# Cost Code Description Type Amount
1 03-300-Cast-in-Place Concrete Operable Wall Footing Subcontractor $6,774.33
2 20-600-Financials,Bonds Bond 1% Other $68.00
3 20-800-Financials,Builder's Risk Insurance 1.4% Other $95.00
4 20-500-Financials,Construction Profit Fee 10% Other $677.00
Subtotal: $7,614.33
Grand Total: $7,614.33
The original(Contract Sum) $ 11,364,500.00
Net change by previously authorized PCCO $ 0.00
The contract sum prior to this PCCO was $ 11,364,500.00
The contract sum would be changed by this PCCO in the amount of $ 7,614.33
The new contract sum including this PCCO will be $ 11,372,114.33
The contract time will be increased by this PCCO by 5 days
Klassen Corporation Fresno Co.Dept of Public Works