HomeMy WebLinkAboutAnimal Services CCO 098.pdf cot,, County of Fresno
Department of Public Works and Planning
O� SRO Development Services&Capital Projects Division
1�RES Steven E.White,Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno Countv Internal Use Only
Project: Animal Services
Contract No.: 20-S-02
Date: 12/15/2021
Contractor: BMY Construction Group, Inc.
Architect: Roger Davidson
Change Order No.: CCO#098
Construction Contract Dollar Amount(as awarded on 10/30/20) $7,405,000.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 298
Construction Start Date: 12/08/20
Original Construction Completion Date: 10/2/21
Change Order Scope of Work:
Diamond plate cover at sidewalk drain-BLDG 1
Attachment(s):
PCO Proposal,Reference Docs,Cover Sheet
Net Additive Change Order Dollar Amount: $1,284.05
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �0
Total Change Order Dollar Amount To Date $382,626.17
Adjusted Contract Dollar Amount: $7,787,626.17
Total Adjusted Calendar Days To Date: 47
Director's Change Order Limit Balance: -$172,626.17
Adjusted Construction Completion Date: 11/18/21
AVM VID Reviewed: Roger Davidson RDW—N((-27,N 0PST)
Architect
Reviewed: Keith Eckert %rii' M.`em s,
Project Manager
Reviewed: Mandeep Sekhon
Construction Manager
Reviewed: Will Kettler
Division Manager
Reviewed: Steven E. White Sie Een EWh o9 n,ei,a3. oPsn
Director
Approved: Steve Brandau
Board of Supervisors Chairman
Director Approval Date: Jan 3,2022
Scan and forward Director Approved Copy to: CAO Greg Reinke
DPH David Luchini
PWP Business Office Kay Vang
Staff Analyst Linda Guerra
Director Steve White
,q cot, County of Fresno
�y Department of Public Works and Planning
O� �O Development Services 8 Capital Projects Division
FR$S Steven E.White,Director
COUNTY CHANGE ORDER REQUEST
Project: Animal Services
Contract No.: 20-S-02
Date: 12/15/2021
Contractor: BMY Construction Group,Inc.
5485 E.Olive Ave.
Fresno,California 93727
(559)243-4200
Change Order No.: CCo#098
Construction Contract Dollar Amount(as awarded on 10/30/20): $7,405,000.00
Original Construction Completion Date: 10/02121
CCO#098 is hereby approved by the County.
Scope of Work:
Diamond plate cover at sidewalk drain-BLDG 1
Attachment:
PCO Proposal,Reference Docs,Cover Sheet
Net Additive Change Order Dollar Amount: $1,284.05
Net Additive Calendar Days: �p
Net Deductive Change Order Dollar Amount: ;0.00
Net Deductive Calendar Days: �p
Total Change Order Dollar Amount To Date: $382,626.17
Adjusted Contract Dollar Amount: $7,787,626.17
Total Adjusted Calendar Days To Date: q7
Adjusted Construction Completion Date: 11/18121
Keith Eckert /motif�clrcrt//
MxiM1LL[cAenP ottle,3M313>3P
Project Manager
Date: Dec 16,2021
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article VI shall apply.
/ C
Accepted By: BMY Construction Group,Inc. f
Authorized Signet
Date:
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
lindat=_uerra fresnocountvca.gov
Fresno County Department of Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project: Animal Services II
No. -404now- Add Credit Rejected Pending t:L escription
CCO 001 6/30/2021 -$13,124.00 0 Credit for less over excavation in building areas
CCO 002 6/30/2021 -$32,673.00 0 Deletion of Ext.glass mat.gypsum sheathing
CCO 003 6/30/2021 $1,992.00 0 Install GFCI on Ext.of BLDG 3
CCO 004 6/30/2021 $1,335.00 0 Additional fixture on pole
CCO 005 6/30/2021 $350.00 0 Additional BLDG 1 outlet
CCO 006 6/30/2021 $1,216.00 0 Add conduit stubs for gates
CCO 007 6/30/2021 $1,457.00 0 Install double acting hinges
CCO 008 9/2/2021 $42,091.00 0 Door type changes
CCO 009 6/30/2021 -$57,287.00 0 Install insulation at various locations
GGO 048 0 Ceiling tile changes
CGO 044 N/A
CCO 012 6/30/2021 $683.00 0 Door type changes
CCO 013 $129,241.00 Tile base additions
CCO 014 $10,238.00 Trail drawing
CCO 015 6/30/2021 $2,653.00 0 Add utility sink BLDG 1
CCO 016 7/27/2021 $11,306.00 0 Add trench drains at Ext.kennels
CCO 017 7/27/2021 $18,696.00 0 Add plumbing&utilities
GGO 0i8 N/A
CCO 019 $27,485.001 Sheet metal additions
CCO 020 6/30/2021 -$43,716.00 0 Credit for grade
CCO 021 6/30/2021 $2,721.00 0 Widen footings
CCO 022 6/30/2021 $860.00 0 Extend pop outs
CCO 023 6/30/2021 $3,386.00 0 Additional concrete
GGO 024 N/A
CCO 025 5/6/2021 $21,084.00 0 Additional trench drains
CCO 026 5/19/2021 $2,964.00 0 Added two canopy footings
CCO 027 8/12/2021 -$17,735.00 0 Ext.storefront doors changes
CCO 028 7/29/2021 -$626.00 0 Parking lot striping w/curb and gutter painting
CCO 029 11/18/2021 -$603.91 0 Credit for Demo by Pump station
CCO 030 7/29/2021 $1,761.48 0 Added support posts in 4'Wall
CCO 031 11/18/2021 -$20,966.00 0 Foundation Changes to Each BLDG
CCO 032 8/30/2021 -$1,049.56 0 Credit Electrical for Water Heater Elimination
CCO 033 7/29/2021 -$17,960.00 0 Rebar Credit due to foundation changes
CCO 034 11/19/2021 -$10,117.00 0 Guillotine door credit
CCO 035 $108,055.00 Install Site Water and Hose Bibs
CCO 036 7/29/2021 -$4,697.00 0 Omit Trench Drain in BLDG 1 RM 1
CCO 037 7/29/2021 -$8,002.00 0 Omit One WH-2 in Building-2
CCO 038 1 7/29/2021 1 1 $6,638.531 1 1 0 Prefabricated Shower Enclosures BLDG 2
Page 1 of 3
CHANGE ORDER SUMMARY
Project: Animal Services
Date s ascription
CCO 039 9/2/2021 $5,013.61 0 Added water supply for clothes washer
CCO 040 $15,106.23 Install 3 compartment sink RM#9-BLDG 3
CCO 041 7/29/2021 $1,860.70 0 Add hot/cold water supply for added dishwashing
CCO 042 $8,369.65 OFCI dog wash tub
CCO 042.2 11/30/2021 $5,307.00 0 Owner furnished tub-Rough in for water and sewer
CCO 043 10/13/2021 $4,578.21 0 Install TD-3 BLDG 3
CCO 044 9/2/2021 $11,279.77 0 Install TD-1 BLDG 3 sallyport
CCO 045 $6,356.03 Add L1 lav in place of OFCI
CCO 045.2 11/30/2021 $5,306.00 0 Owner furnished sinks,water/sewer rough in provided
CCO 046 8/30/2021 $8,441.51 0 Extended exterior walls-BLDG 2
CCO 047 8/30/2021 -$122,982.00 0 Credit formica in place of INT.wall paneling
CCO 048 7/29/2021 $13,105.44 0 Revised footings for canopy at sally port
CCO 049 9/2/2021 $957.00 0 Additional slab concrete BLDG 3
CCO 050 9/2/2021 $4,634.00 0 EXT.kennel pads outside BLDG 2 originally from PCO#31
CCO 051 9/19/2021 $22,144.00 0 Added dryer and DW hood per mech.Drawing
CCO 052 8/30/2021 $193,529.00 0 Metal wall paneling in BLDG 1&2
CCO 053 8/30/2021 $5,163.00 0 Standard door frame to alumnatone package
CCO 054 $6,707.00 Light kits package
CCO 055 7/29/2021 $2,657.00 0 Restaking for concrete drive BLDG 3
CCO 056 8/30/2021 $12,475.00 0 Additional concrete for rolling gates&curb at sally port
CCO 057 9/28/2021 -$8,682.00 0 Credit for Transfer Doors at Building 2 Package
CCO 058 $131,363.00 Install rolling gates,visions slats,added fencing/gates,etc.
CCO 058.1 11/18/2021 $143,904.00 2 Install rolling gates,visions slats,added fencing/gates,etc.
CCO 059 8/30/2021 $4,265.78 1 Provide electrical for rolling gates
CCO 060 10/22/2021 -$29,050.00 0 Gypsum deduct for installation of metal paneling
CCO 061 10/28/2021 $6,989.00 0 Fabrication,Install,Backfill 15'rebar at canopy footings
CCO 062 9/28/2021 $1,738.00 1 Added electrical BLDG 3
CCO 063 $14,086.00 Extended performance staff change
CCO 063.1 11/19/2021 $14,086.00 15 Extended performance staff change
CCO 064 $14,086.00 Extended GC and time concrete revisions
CCO 064.1 11/19/2021 $14,086.00 15 Extended GC and time concrete revisions
CCO 065 8/30/2021 $2,817.00 3 Extended GC and time due to BLDG 3 mech revisions
CCO 066 8/30/2021 $2,817.00 3 Extended GC and Time Due to Guillotine Door Changes
CCO 067 10/22/2021 $7,062.00 0 Guillotine door frame material change-BLDG 2
CCO 067.1 $6,332.00 PCO#67 Additional cost for remaining doors
CCO 068 9/21/2021 $1,717.00 0 Ext.light changes-BLDG 1
CCO 069 9/21/2021 $605.00 0 Add.Concrete west side of BLDG 3
CCO 070 9/7/2021 $6,875.00 0 Extended GC and time revisions for Guillotine door changes
CCO 071 $7,225.00 0 Install added site hose bibs
CCO 072 10/28/2021 $1,041.00 0 Door type alterations from 01:S to 05:5-BLDG 3
CCO 073 9/17/2021 $0.00 0 Date Adjustments
CCO 074 10/28/2021 $6,396.00 0 Revised concrete slab detail at Sally&food prep drive
CCO 075 1 10/28/2021 $704.001 0 JAdditional Outlets BLDG 1 RM 4
CCO 076 1 10/28/2021 $691.00 0 1 Re-Frame roll-up door-BLDG 3
Page 2 of 3
CHANGE ORDER SUMMARY
Project: Animal Services
Date Add Credit Rejected Pending R
CCO 077 10/28/2021 $584.00 0 Additional concrete per ASI&mechanical pad-BLDG 1
CCO 078 10/13/2021 $6,442.00 0 Re-frame Guillotine Door ROs
CCO 079 10/13/2021 $61,416.00 0 Add sidewalk&mow strips
CCO 079.1 $20,761.00 Add sidewalk
CCO 080 10/13/2021 $6,561.00 2 Add hat track for kennel backing
CCO 081 11/2/2021 -$1,066.44 0 Omit plants/irrigation-BLDG 1
CCO 082
CCO 083 11/19/2021 $3,085.00 1 Paint louvers to match windows
CCO 084 11/9/2021 $6,583.00 0 Hose bib relocation due to change in original location-BLDG 3
CCO 085 11/19/2021 $10,047.00 0 Add water lines to make-up air units-BLDG 2
CCO 086 11/30/2021 $4,904.00 0 Add 4 hose bibs to BLDG 2&3,cap hot lines to BLDG 3
CCO 087 11/30/2021 $2,596.00 0 Relocation of Lay.brackets in restrooms-BLDG 2
CCO 088
CCO 089 11/30/2021 $889.00 0 Additional Demo for sewer line-BLDG 2
CCO 090 12/2/2021 $6,332.00 0 Correction to PCO#067
CCO 091 12/2/2021 -$40,655.00 0 Credit for PCO#79 removing cost of mow strips
CCO 092
CCO 093 12/15/2021 $53,620.00 4 Add electricl per revised drawings mark"D"-BLDG 3
CCO 094 11/19/2021 $7,308.00 0 Add 5'extension on all four kennel locations-BLDG 2
CCO 095
CCO 096 11/19/2021 $1,303.00 0 Door type alteration to 02:S-BLDG 3 door 10b
CCO 097
CCO 098 12/15/2021 $1,284.05 0 Diamond plate cover at sidewalk drain-BLDG 1
Totals $813,618.08 -$430,991.91 $498,185.91 $0.00 Totals 47 Page 3 of 3
.rN.
■rr
CONSTRUCTION
GROUP INCORPORATED
December 1, 2021
County of Fresno
Construction Division
Attn: Keith Eckert
2220 Tulare Street, 711 Floor
Fresno, CA 93721
Re: Animal Control Center
BMY JOB NO. 20015
Subject: PCO 998—Diamond Plated Cover at Sidewalk Drain
Mr. Eckert,
BMY Construction Group, Inc. (BMY) is providing the following PCO for the costs and time associated with the
changes made to added sidewalk per ASI north of building 1, by the switchgear. BMY to provide diamond plated
cover with L Angles to allow diamond cover sit flush with concrete.
BMY is requesting the County to issue a Change Order adding $1,284.05 to the contract price. In order to
perform the work BMY is requiring a time extension of 0 calendar days.
This PCO is valid for 30 days. Due to unprecedent times in our industry, with volatile material pricing and
delivery, it is of the utmost importance that this PCO be processed quickly. Our industry is currently having
supply issues. The cost of material is on a consistent rise and it is not as readily available, with lead times getting
longer. This may directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down and get material and
products, At this time we need your assistance with timely approvals so we can minimize project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further information,
please do not hesitate to contact me.
Respectfully,
Dylan Medeiros
Project Engineer
Page 1 of 1
5485 East Olive Avenue • Fresno, CA 93727 - Phone (559) 243-4200 - Fax (559) 222-2380
Lic No. 686178
PCO #098
CONSTRUCTION
GROUPINCORPORATFO
BMY Construction Group Incorporated Project: 20015-Animal Control Center
5485 East Olive Avenue 190 West Dan Ronquillo Drive
Fresno, California 93727-2541 Fresno, California 93706
Phone: (559)243-4200
Fax: null
Prime Contract Potential Change Order #098: CE #107 - Diamond Plated
Cover at Sidewalk Drain
TO: The County of Fresno. Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street.8th Floor Fresno,California 93727
Fresno, California 93721
PCO NUMBER/REVISION: 098,10 CONTRACT: 20015-Animal Control Center Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Dylan Medeiros(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 12/1/2021
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $1,284.05
POTENTIAL CHANGE ORDER TITLE: CE#107-Diamond Plated Cover at Sidewalk Drain
CHANGE REASON: Design Development
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract is Changed As Follows)
CE#107-Diamond Plated Cover at Sidewalk Drain
ASI added drain at sidewalk by switchgear.Diamond plate cover will be installed on L angles to allow flush with concrete sidewalk
ATTACHMENTS:
PCO#98-Proposal.Ddf
# I Budget Code Description Amount
1 01-8550.0 BMY Contingency.Other $1.150.00
Subtotal; $1,150.00
Project Manager(2.90%Applies to all lire item types.). $33.35
General Liabil ty (0.10%Applies to all line item types.): $1,15
Superintendent(2.00%Applies to all line item types.): $23.00
Project Engineer(1.50%Applies to all line item types.). $17.25
Overhead and Profit(3.5090 Applies to all line item types.): S40.25
Health Insurance(0.75%Applies to all line item types.): $9.49
Bond(0.75°'o Applies to all line item types.): $9.56
Grand Total: $1,284.05
BMY Construction Group Incorporated Page 1 of 2 Printed On: 12/1/2021 02:26 PM
Moren Industrial Metals Inc.
2597 N Fordham Fresno, CA 93727 Lic 11699872 559-285-9028 Fax 559-291-6950
Quote # 21-3408 Date: 1 1/19/2021
Attention: Ray Coulter
BMY Construction
Project Name: Fresno County Animal Control
We are pleased to provide cost for the following:
• Provide Only (1) 3/16" Mild Steel Diamond Plate Cover at Side Walk drain
Opening per job walk with Ray, to include (2) 1.5" X 2" X 60" L-Angle
supports.
TotalPrice ........................................................................$1,150.00
Additional Pricing
Submittals or shop drawing...................................................$ 680.00 each
This Quote is Only Good for 30 Days from Date of Quote
Excluded from estimate are the following items:
❑ Shop Drawing,Submittals, TPO Metal Scuppers,TPO Clad Metal, &Pas-through
❑ Electrical, Plumbing,Condensate Drains Storefront flashings,Paint
• Conduits,Wiring,Piping,Mechanical flashings, Holiday Pay
❑ Material Price Changes do to Tariffs, Anything not listed above.
❑ Door Handles,Door Locking Mechanisms, Door Closing Mechanisms.
U Finish hardware, Engineered changes to the above scope of work.
❑ Submittals, Permit fees, soil testing/sampling, if needed.
The terms quoted are all- inclusive and COT(all services) we anticipate our firm would
need to complete the entire development process. We do not agree with the practice of
providing a test-only-type quote and then invoicing for additional unstated services. We
think it is only fair to provide you with quotes and terms that are complete, easy to read
and with all the costs included, with no complicated mathematical formulations,
calculations, hidden fees or surprises