PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project: Animal Services
Contract No.: 20-S-02
Date: 2/24/2022
Contractor: BMY Construction Group, Inc.
Architect: Roger Davidson
Change Order No.: CCO#111
Construction Contract Dollar Amount(as awarded on 10/30/20) $7,405,000.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 298
Construction Start Date: 12/08/20
Original Construction Completion Date: 10/2/21
Change Order Scope of Work:
Add concrete splash blocks under all downpouts to prevent erosion.
Attachment(s):
PCO Proposal,Reference Does,Cover Sheet
Net Additive Change Order Dollar Amount: $1,638.94
Net Additive Calendar Days:
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days:
Total Change Order Dollar Amount To Date $473,594.83
Adjusted Contract Dollar Amount: $7,878,594.83
Total Adjusted Calendar Days To Date: 47
Director's Change Order Limit Balance: -$263,594.83
Adjusted Construction Completion Date: 11/18/21
Reviewed: Roger Davidson ���mh
Architect
Reviewed: Keith Eckert &t. eft
,h M
Project Manager
Reviewed: Mandeep Sekhon 044 -
Construction Manager
Approved: Will Kettler
Division Manager
Approved: Steven E. White ste✓an E white
Director
Approved: Brian Pacheco
Board of Supervisors Chairman
Director Approval Date: Mar 1,2022
Scan and forward Director Approved Copy to: CAO Paul Nerland
DPH David Luchini
PWP Business Office Kay Vang
Staff Analyst Linda Guerra
cot, County of Fresno
19 11P Department of Public Works and Planning
O� 36 O Development Services&Capital Projects Division
FRESH Steven E.White,Director
COUNTY CHANGE ORDER REQUEST
Project: Animal Services
Contract No.: 20-S-02
Date: 2/24/2022
Contractor: BMY Construction Group,Inc.
5485 E.Olive Ave.
Fresno,California 93727
(559)2434200
Change Order No.: CCO#111
Construction Contract Dollar Amount(as awarded on 10/30/20): $7,405,000.00
Original Construction Completion Date: 10102121
CCO#111 is hereby approved by the County.
Scope of Work:
Add concrete splash blocks under all downpouts to prevent erosion.
Attachment:
PCO Proposal,Reference Docs,Cover Sheet
Net Additive Change Order Dollar Amount: $1,638.94
Net Additive Calendar Days: �0
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: 0
Total Change Order Dollar Amount To Date: $473,594.83
Adjusted Contract Dollar Amount: $7,878,594.83
Total Adjusted Calendar Days To Date: 47
Adjusted Construction Completion Date: 11/18/21
Keith Eckert
Project Manager
Date: Feb 24,2022
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised adjusted Contract dollar amount and time extension shown in this Change Order as payment in full.
In the event the Contractor does not sign acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article Vl shall apply.
Accepted By: BMY Construction Group,Inc. IG
Authorized Signatu
Dale:
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
linda}uerra fresnocount rc� a.gov
Fresno County Department of Public Woks and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project: Animal Services
CCO 001 6/30/2021 -$13,124.00 0 Credit for less over excavation in building areas
CCO 002 6/30/2021 -$32,673.00 0 Deletion of Ext.glass mat. gypsum sheathing
CCO 003 6/30/2021 $1,992.00 0 Install GFCI on Ext.of BLDG 3
CCO 004 6/30/2021 $1,335.00 0 Additional fixture on pole
CCO 005 6/30/2021 $350.00 0 Additional BLDG 1 outlet
CCO 006 6/30/2021 $1,216.00 0 Add conduit stubs for gates
CCO 007 6/30/2021 $1,457.00 0 Install double acting hinges
CCO 008 9/2/2021 $42,091.00 0 Door type changes
CCO 009 6/30/2021 -$57,287.00 0 Install insulation at various locations
GGG 010 0 Ceiling tile changes
GGG 011 N/A
CCO 012 6/30/2021 $683.00 0 Door type changes
CCO 013 $129,241.00 Tile base additions
CCO 014 $10,238.00 Trail drawing
CCO 015 6/30/2021 $2,653.00 0 Add utility sink BLDG 1
CCO 016 7/27/2021 $11,306.00 0 Add trench drains at Ext. kennels
CCO 017 7/27/2021 $18,696.00 0 Add plumbing&utilities
GGO M N/A
CCO 019 $27,485.00 Sheet metal additions
CCO 020 6/30/2021 -$43,716.00 0 Credit for grade
CCO 021 6/30/2021 $2,721.00 0 Widen footings
CCO 022 6/30/2021 $860.00 0 Extend pop outs
CCO 023 6/30/2021 $3,386.00 0 Additional concrete
GGO 024 N/A
CCO 025 5/6/2021 $21,084.00 0 Additional trench drains
CCO 026 5/19/2021 $2,964.00 0 Added two canopy footings
CCO 027 8/12/2021 -$17,735.00 0 Ext.storefront doors changes
CCO 028 7/29/2021 -$626.00 0 Parking lot striping w/curb and gutter painting
CCO 029 11/18/2021 -$603.91 0 Credit for Demo by Pump station
Page 1 of 4
No. App. Date Add ($) Credit Rejected Pending Adj. Days Description
CCO 030 7/29/2021 $1,761.48 0 Added support posts in 4'Wall
CCO 031 11/18/2021 -$20,966.00 0 Foundation Changes to Each BLDG
CCO 032 8/30/2021 -$1,049.56 0 Credit Electrical for Water Heater Elimination
CCO 033 7/29/2021 -$17,960.00 0 Rebar Credit due to foundation changes
CCO 034 11/19/2021 -$10,117.00 0 Guillotine door credit
CCO 035 $108,055.00 Install Site Water and Hose Bibs
CCO 036 7/29/2021 -$4,697.00 0 Omit Trench Drain in BLDG 1 RM 1
CCO 037 7/29/2021 -$8,002.00 0 Omit One WH-2 in Building-2
CCO 038 7/29/2021 $6,638.53 0 Prefabricated Shower Enclosures BLDG 2
CCO 039 9/2/2021 $5,013.61 0 Added water supply for clothes washer
CCO 040 $15,106.23 Install 3 compartment sink RM#9-BLDG 3
CCO 041 7/29/2021 $1,860.70 0 Add hot/cold water supply for added dishwashing
CCO 042 $8,369.65 OFCI dog wash tub
CCO 042.2 11/30/2021 $5,307.00 0 Owner furnished tub-Rough in for water and sewer
CCO 043 10/13/2021 $4,578.21 0 Install TD-3 BLDG 3
CCO 044 9/2/2021 $11,279.77 0 Install TD-1 BLDG 3 sallyport
CCO 045 $6,356.03 Add L1 Iav in place of OFCI
CCO 045.2 11/30/2021 $5,306.00 0 Owner furnished sinks,water/sewer rough in provided
CCO 046 8/30/2021 $8,441.51 0 Extended exterior walls-BLDG 2
CCO 047 8/30/2021 -$122,982.00 0 Credit formica in place of INT.wall paneling
CCO 048 7/29/2021 $13,105.44 0 Revised footings for canopy at sally port
CCO 049 9/2/2021 $957.00 0 Additional slab concrete BLDG 3
CCO 050 9/2/2021 $4,634.00 0 EXT. kennel pads outside BLDG 2 originally from PCO#31
CCO 051 9/19/2021 $22,144.00 0 Added dryer and DW hood per mech. Drawing
CCO 052 8/30/2021 $193,529.00 0 Metal wall paneling in BLDG 1 &2
CCO 053 8/30/2021 $5,163.00 0 Standard door frame to alumnatone package
CCO 054 $6,707.00 Light kits package
CCO 055 7/29/2021 $2,657.00 0 Restaking for concrete drive BLDG 3
CCO 056 8/30/2021 $12,475.00 0 Additional concrete for rolling gates&curb at sally port
CCO 057 9/28/2021 -$8,682.00 0 Credit for Transfer Doors at Building 2 Package
CCO 058 $131,363.00 Install rolling gates,visions slats, added fencing/gates, etc.
CCO 058.1 11/18/2021 $143,904.00 2 Install rolling gates,visions slats, added fencing/gates, etc.
Page 2 of 4
No. App. Date Add ($) Credit Rejected Pending Adj. Days Description
CCO 059 8/30/2021 $4,265.78 1 Provide electrical for rolling gates
CCO 060 10/22/2021 -$29,050.00 0 Gypsum deduct for installation of metal paneling
CCO 061 10/28/2021 $6,989.00 0 Fabrication, Install, Backfill 15'rebar at canopy footings
CCO 062 9/28/2021 $1,738.00 1 Added electrical BLDG 3
CCO 063 $14,086.00 Extended performance staff change
CCO 063.1 11/19/2021 $14,086.00 15 Extended performance staff change
CCO 064 $14,086.00 Extended GC and time concrete revisions
CCO 064.1 11/19/2021 $14,086.00 15 Extended GC and time concrete revisions
CCO 065 8/30/2021 $2,817.00 3 Extended GC and time due to BLDG 3 mech revisions
CCO 066 8/30/2021 $2,817.00 3 Extended GC and Time Due to Guillotine Door Changes
CCO 067 10/22/2021 $7,062.00 0 Guillotine door frame material change-BLDG 2
CCO 067.1 $6,332.00 PCO#67 Additional cost for remaining doors
CCO 068 9/21/2021 $1,717.00 0 Ext. light changes-BLDG 1
CCO 069 9/21/2021 $605.00 0 Add. Concrete west side of BLDG 3
CCO 070 9/7/2021 $6,875.00 0 Extended GC and time revisions for Guillotine door changes
CCO 071 $7,225.00 0 Install added site hose bibs
CCO 072 10/28/2021 $1,041.00 0 Door type alterations from 01:S to 05:S-BLDG 3
CCO 073 9/17/2021 $0.00 0 Date Adjustments
CCO 074 10/28/2021 $6,396.00 0 Revised concrete slab detail at Sally&food prep drive
CCO 075 10/28/2021 $704.00 0 Additional Outlets BLDG 1 RM 4
CCO 076 10/28/2021 $691.00 0 Re-Frame roll-up door-BLDG 3
CCO 077 10/28/2021 $584.00 0 Additional concrete per ASI &mechanical pad-BLDG 1
CCO 078 10/13/2021 $6,442.00 0 Re-frame Guillotine Door ROs
CCO 079 10/13/2021 $61,416.00 0 Add sidewalk&mow strips
CCO 079.1 $20,761.00 Add sidewalk
CCO 080 10/13/2021 $6,561.00 2 Add hat track for kennel backing
CCO 081 11/2/2021 -$1,066.44 0 Omit plants/irrigation-BLDG 1
CCO 082
CCO 083 11/19/2021 $3,085.00 1 Paint louvers to match windows
CCO 084 11/9/2021 $6,583.00 0 Hose bib relocation due to change in original location-BLDG 3
CCO 085 11/19/2021 $10,047.00 0 Add water lines to make-up air units-BLDG 2
CCO 086 11/30/2021 $4,904.00 0 Add 4 hose bibs to BLDG 2&3,cap hot lines to BLDG 3
CCO 087 11/30/2021 $2,596.001 1 1 0 1 Relocation of Lay. brackets in restrooms-BLDG 2
CCO 088
Page 3 of 4
No. App. Date Add ($) Credit Rejected Pending Adj. Days Description
CCO 089 11/30/2021 $889.00 0 Additional Demo for sewer line-BLDG 2
CCO 090 12/2/2021 $6,332.00 0 Correction to PCO#067
CCO 091 12/2/2021 -$40,655.00 0 Credit for PCO#79 removing cost of mow strips
CCO 092 1/19/2022 $7,549.00 0 Relocation of plumbing and adding S-2 in BLDG 2
CCO 093 12/15/2021 $53,620.00 4 Add electrical per revised drawings mark"D"-BLDG 3
CCO 094 11/19/2021 $7,308.00 0 Add 5'extension on all four kennel locations-BLDG 2
CCO 095 12/30/2021 $28,533.76 0 Sally port fencing-BLDG 3
CCO 096 11/19/2021 $1,303.00 0 Door type alteration to 02:S-BLDG 3 door 10b
CCO 097 1/19/2022 $5,185.31 0 Add curb&gutter work north of site
CCO 098 12/15/2021 $1,284.05 0 Diamond plate cover at sidewalk drain-BLDG 1
CCO 099
CCO 100
CCO 101 12/30/2021 $757.08 0 Add. (5)vision glass-BLDG 3
CCO 102 12/30/2021 $7,950.28 0 Fab. &Install signage-BLDG 1 Exterior
CCO 103
CCO 104 1/19/2022 $1,149.95 0 Push plate mounting post-BLDG 1
CCO 105 1/19/2022 $3,286.05 0 Paint interior side of sally port-BLDG 3
CCO 106 1/19/2022 $989.27 0 Add power for irrigation controller
CCO 107
CCO 108 2/22/2022 $1,506.56 0 Added power for In-Door unit-BLDG 1
CCO 109 2/22/2022 $419.57 0 Cellular Alarm Communicator
CCO 110 2/4/2022 $32,002.89 0 Add FRP-BLDG 2&3
CCO 110.1 $30,886.00 0 Add FRP-BLDG 2&3
CCO 111 2/22/2022 $1,638.941 0 Add splash blocks under all downspouts
Totals $904,586.74 -$430,991.911 $529,071.911 $0.00 47 Page 4 of 4
CONSTRUCTION
GROUP INCORPORATED
February 9,2021
County of Fresno
Construction Division
Attn: Keith Eckert
2220 Tulare Street,711 Floor
Fresno,CA 93721
Re: Animal Control Center
BMY JOB NO.20015
Subject: PCO#111—Splash Blocks
Mr. Eckert,
BMY Construction Group, Inc.(BMY)is providing the following PCO for the costs and time associated with the changes made
to all building downspouts.Concrete splash blocks were requested under all downspouts.
BMY is requesting the County to issue a Change Order adding $1,638.94 to the contract price. In order to perform the work
BMY is requiring a time extension of 0 calendar days.
This PCO is valid for 30 days. Due to unprecedent times in our industry,with volatile material pricing and delivery, it is of the
utmost importance that this PCO be processed quickly. Our industry is currently having supply issues.The cost of material is
on a consistent rise and it is not as readily available,with lead times getting longer. This may directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down and get material and products.
At this time we need your assistance with timely approvals so we can minimize project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further information, please do not
hesitate to contact me.
Respectfully,
Dylan Medeiros
Project Engineer
Page 1 of 1
5485 East Olive Avenue • Fresno, CA 93727 • Phone (559)243-4200 • Fax(559)222-2380
Lic No. 686178
= PCO #111
CONSTRUCTION
GROUP INCORPORATED
BMY Construction Group Incorporated Project:20015-Animal Control Center
5485 East Olive Avenue 190 West Dan Ronquillo Drive
Fresno,California 93727-2541 Fresno,California 93706
Phone:(559)243-4200
Fax:null
Prime Contract Potential Change Order #111 : CE #125 - Install Splash
Blocks
TO: The County of Fresno, Department of Public FROM: BMY Construction Group, Inc.
Works and Planning 5485 E.Olive Ave
2220 Tulare Street,8th Floor Fresno,California 93727
Fresno,California 93721
PCO NUMBER/REVISION: 111 /0 CONTRACT: 20015-Animal Control Center Prime
Contract
REQUEST RECEIVED FROM: CREATED BY: Dylan Medeiros(BMY Construction
Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 2/9/2022
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: $1,638.94
POTENTIAL CHANGE ORDER TITLE: CE#125-Install Splash Blocks
CHANGE REASON:Client Request
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract Is Changed As Follows)
CE#125-Install Splash Blocks
Splash blocks installed under all downspouts to prevent erosion.
ATTACHMENTS:
PCO#111 -Proposal.pdf
# Budget Code Description Amount
1 32-9000.S Landscaping&Irrigation/ALL Build/Install splash blocks $1,467.84
COMMERCIAL.Subcontract
Subtotal: $1,467.84
Project Manager(2.90%Applies to all line item types.): $42.57
General Liability(0.10%Applies to all line item types.): $1.47
Superintendent(2.00%Applies to all line item types.): $29.36
Project Engineer(1.50%Applies to all line item types.): $22.02
Overhead and Profit(3.50%Applies to all line item types.): $51.37
Health Insurance(0.75%Applies to all line item types.): $12.11
Bond(0.75%Applies to all line item types.): $12.20
Grand Total: $1,638.94
BMY Construction Group Incorporated Page 1 of 2 Printed On:2/9/2022 08:18 AM
PCO #111
CONSTRUCTION
GROUPINCORPORATED
Noel Roger Davidson II(The County of The County of Fresno,Department of BMY Construction Group,Inc.
Fresno,Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street,8th Floor 2220 Tulare Street,8th Floor 5485 E.Olive Ave
Fresno,California 93721 Fresno,California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 2 of 2 Printed On:2/9/2022 08:18 AM
February 04,2022
BrightView Page 1 of 3
Landscape Services
Proposal for Extra Work at
Animal Control Center
Property Name Animal Control Center Contact Dylan Mederios
Property Address 190 West Dan Ronquillo Dr To BMY Construction Group Incorporated
Fresno, CA 93706 Billing Address 5485 East Olive Ave
Fresno, CA 93727-2541
Project Name RFQ#16 Animal Control
Project Description Install Additional Splash Blocks under gutters per plan
Scope of Work
QTY UoM/Size Material/Description Unit Price Total
.....................................................................................................................................................................................................................................................................................................................................................................................................
12.00 EACH Build&Install Concrete Splash blocks under rain gutters $122.32 $1,467.84
to divert water away from building as requested by builder
For internal use only
SO# 7728281
JOB# 311800130
Service Line 150 Total Price $1,467.84
THIS IS NOT AN INVOICE
This proposal is valid for 60 days unless otherwise approved by BrightView Landscape Services,Inc.
5213 E Pine Ave,Fresno,CA 93727 ph.(559)453-1670 fax(925)734-0769
February 04,2022
Page 2 of 3
TERMS & CONDITIONS 14. Cancellation: Notice of Cancellation of work must be received in writing
before the crew is dispatched to their location or Client/Owner will be liable for
1. The Contractor shall recognize and perform in accordance with written terms, a minimum travel charge of$150.00 and billed to Client/Owner.
written specifications and drawings only, contained or referred to herein. Al
materials shall conform to bid specifications.
The following sections shall apply where Contractor provides Customer with tree
2. Work Force: Contractor shall designate a qualified representative with care services:
experience in landscape maintenance/construction upgrades or when
applicable in tree management.The workforce shall be competent and qualified, 15. Tree&Stump Removal:Trees removed will be cut as dose to the ground as
and shall be legally authorized to work in the U.S. possible based on conditions to or next to the bottom of the tree trunk.Additional
charges will be levied for unseen hazards such as, but not limited to concrete
3. License and Permits:Contractor shall maintain a Landscape Contractor's brick filled trunks,metal rods,etc.If requested mechanical grinding of visible tree
license, if required by State or local law, and will comply with all other license stump will be done to a defined width and depth below ground level at an
and permit requirements of the City,State and Federal Governments, as well additional charge to the ClienUOwner. Defined backfill and landscape material
as all other requirements of law. may be specified. Client/Owner shall be responsible for contacting Underground
Service Alert to locate underground utility lines prior to start of work.Contractor is
4. Taxes: Contractor agrees to pay all applicable taxes,including sales tax where not responsible damage done to underground utilities such as but not limited to,
applicable on material supplied. cables,wires,pipes,and irrigation parts.Contractor will repair damaged irrigation
lines at the Client/Owners expense.
5. Insurance: Contractor agrees to provide General Liability Insurance,
Automotive Liability Insurance, Worker's Compensation Insurance, and any 16. Waiver of Liability:Requests for crown thinning in excess of twenty-five percent
other insurance required by law or Client/Owner,as specified in writing prior to (25%)or work not in accordance with ISA(international Society of Arboricultural)
commencement of work.If not specified, Contractor will furnish insurance with standards will require a signed waiver of liability.
$1,000,000limit of liability.
Acceptance of this Contract
6. Liability: Contractor shall indemnify the Client/Owner and its agents and Contractor is authorized to perform the work stated on the face of this Contract.
employees from and against any third party liabilities that arise out of Payment will be 100% due at time of billing. If payment has not been received by
Contractor's work to the extent such liabilities are adjudicated to have been BrightView within fifteen(15)days after billing, BrightView shall be entitled to all costs
caused by Contractor's negligence or willful misconduct. Contractor shall not of collection, including reasonable attorneys' fees and it shall be relieved of any
be liable for any damage that occurs from Acts of God are defined as those obligation to continue performance under this or any other Contract with Client/Owner.
caused by windstorm, hail,fire,flood,earthquake, hurricane and freezing,etc. Interest at a per annum rate of 1.5%per month (18% per year), or the highest rate
Under these circumstances, Contractor shall have the right to renegotiate the permitted by law,may be charged on unpaid balance 30 days after billing.
terms and prices of this agreement within sixty(60)days.Any illegal trespass,
claims and/or damages resulting from work requested that is not on property NOTICE: FAILURE TO MAKE PAYMENT WHEN DUE FOR COMPLETED WORK ON
owned by Client/Owner or not under Client/Owner management and control CONSTRUCTION JOBS, MAY RESULT IN A MECHANIC'S LIEN ON THE TITLE TO
shall be the sole responsibility of the Client/Owner. YOUR PROPERTY
7. Subcontractors: Contractor reserves the right to hire qualified Customer
subcontractors to perform specialized functions or work requiring specialized
equipment. Project engineer
8. Additional Services: Any additional work not shown in the above Sgnature Tdle
specifications involving extra costs will be executed only upon signed written
orders,and will become an extra charge over and above the estimate. Dylan Mederios February 04, 2022
Prmted Name Date
9. Access to Jobsite: Client/Owner shall provide all utilities to perform the
work.Client/Owner shall furnish access to all parts ofjobsite where Contractor BrightView Landscape Services, Inc. "BrightView"
is to perform work as required by the Contract or other functions related
thereto, during normal business hours and other reasonable periods of time.
Contractor will perform the work as reasonably practical after the owner makes Enhancement Manager
the site available for performance of the work. signature Tine
10. Invoicing:Client/Owner shall make payment to Contractor within fifteen(15)
days upon receipt of invoice. In the event the schedule for the completion of Jannell Jean Branch February 04, 2022
the work shall require more than thirty (30) days, a progress bill will be Pnmed Name r.:,r,•
presented by month end and shall be paid within fifteen(15)days upon receipt
of invoice.
11. Termination:This Work Order may be terminated by the either party with or Job #: 311800130 Proposed Price: $1,467.84
without cause,upon seven(7)work days advance written notice. Client/Owner
will be required to pay for all materials purchased and work completed to the SO # 7728281
date of termination and reasonable charges incurred in demobilizing. O O
12. Assignment: The Owner/Client and the Contractor respectively, bind
themselves, their partners, successors, assignees and legal representative to
the other party with respect to all covenants of this Agreement. Neither the
Owner/Client nor the Contractor shall assign or transfer any interest in this
Agreement without the written consent of the other provided, however, that
consent shall not be required to assign this Agreement to any company which
controls, is controlled by,or is under common control with Contractor or in
connection with assignment to an affiliate or pursuant to a merger,sale of all or
substantially all of its assets or equity securities, consolidation, change of
control or corporate reorganization.
13. Disclaimer:This proposal was estimated and priced based upon a site visit
and visual inspection from ground level using ordinary means, at or about the
time this proposal was prepared. The price quoted in this proposal for the
work described, is the result of that ground level visual inspection and therefore
our company will not be liable for any additional costs or damages for
additional work not described herein, or liable for any incidents/accidents
resulting from conditions, that were not ascertainable by said ground level
visual inspection by ordinary means at the time said inspection was performed.
Contractor cannot be held responsible for unknown or otherwise hidden
defects. Any corrective work proposed herein cannot guarantee exact results.
Professional engineering, architectural, and/or landscape design services
("Design Services") are not included in this Agreement and shall not be
provided by the Contractor. Any design defects in the Contract Documents are
the sole responsibility of the Owner. If the Client/Owner must engage a
licensed engineer, architect and/or landscape design professional, any costs
concerning these Design Services are to be paid by the ClientfOwner directly
to the designer involved.
Exclusions And Qualifications
Personnel/Working Hours
• This Proposal is based upon personnel working normal daytime hours,8 hour work day,40 hour work week.Proposal excludes working in an ineffective manner(rain,
unsafe working conditions,etc.)
• BrightView is an open shop contractor,non-signatory to any labor agreements.
• This Proposal is based on non-prevailing wage and non-union labor rates.
This proposal is based on performing the work in one continuous operation and includes one mobilization of equipment,tools and resources to and from site.
Utilities,Traffic Control,and Permitting
• BrightView excludes any permits or applicable fees in this proposal.Permits and fees,if required,are to be supplied and paid for by others including street closure
and traffic control plans.
• Permanent or temporary Water meter fees,permits,installation and cost for water not included in proposal.
• BrightView Landscape Maintenance,Inc.is not responsible for underground or overhead utilities or their re-routing.
• BrightView is not responsible for unmarked private utilities.
• A minimum of(48)hour notice prior to mobilization must be provided for proper underground utility marking,etc.in public areas.
• The owner shall be responsible for identifying and marking all underground utilities within in the work site.
BrightView shall accept no responsibility for damage to any unmarked underground utilities.
Scope of Work/Project Specifications
• No import or export soils are provided for in this proposal except as noted in the scope of work.All planting spoils to be used on-site.
• Equipment access roads and level crane pads are to be provided at the time of installation and approved by BrightView prior to mobilization.
• Any and all concrete or asphalt cutting,demolition,removal and replacement to be performed by others.
• Hardscape,electrical,surveying,metal work or waterproofing or any other scope not specified in this proposal are excluded.
• No demolition work is provided for in this proposal except as noted in the scope of work.
• BrightView will receive the site clean and free of weeds and construction debris and in finish graded condition(plus or minus 1/10th foot)
• Site is to be readily accessible by smooth bucket skip loader,forklift,and workmen with hand tools,semi-truck and trailer.
• Cutting,patching or penetration of planter walls is excluded.Coring of structures has not been included.All necessary penetrations into existing planters,sealing of
these penetrations,etc.to be by others.
• Waterproofing,protection boards,and topping slabs shall be completed,in place and tested by others prior to mobilization.
• Specified plant materials are subject to availability at the time of construction.
Irrigation
• BrightView shall be given sufficient notice to place irrigation sleeves prior to paving,curbing or wall footings being poured.
• No hardscape(asphalt,concrete,etc.)cutting for purposes of installing irrigation piping,wires,etc.is provided in this proposal.
• Irrigation to be taken from provided point of connection.Water meter installation excluded.
• Irrigation to be installed per plan.Any necessary irrigation modifications to be billed at time and materials.
• Power(110v)P.O.C.for irrigation controller will be provided by the others.
• BrightView will warranty the irrigation system,with regards to material and workmanship for(90)days post-installation.
Warranty
• BrightView shall Warranty all shrubs,ground cover and vines for a period of(90)days.Specimen trees for a period of one(1)year.
• Warranty does not extend beyond the natural life cycle of the plant material.(E.G.annual color,perennials,biennials,etc.)