PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno Countv Internal Use Onlv
Project: Animal Services
Contract No.: 20-S-02
Date: 11/29/2021
Contractor: BMY Construction Group, Inc.
Architect: Roqer Davidson
Change Order No.: CCO#096
Construction Contract Dollar Amount(as awarded on 10/30/20) $7,405,000.00
Director's Change Order Limit: $210,000.00
Contract Time(Calendar Days): 298
Construction Start Date: 12/08/20
Original Construction Completion Date: 10/2/21
Change Order Scope of Work:
Door type alteration to 02:S-BLDG 3 door 10b
Attachment(s):
PCO Proposal,Reference Docs,Cover Sheet
Net Additive Change Order Dollar Amount: $1,303.00
Net Additive Calendar Days: DO
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: 00
Total Change Order Dollar Amount To Date $281,627.12
Adjusted Contract Dollar Amount: $7,686,627.12
Total Adjusted Calendar Days To Date: 43
Director's Change Order Limit Balance: -$71,627.12
Adjusted Construction Completion Date: 11/14/21
Reviewed. Roger Davidson AVNk11PfONRMIDSON Pn
Architect
Reviewed: Keith Eckert hM EM F kh ,
a-(J-31, 3—
Project Manager
Reviewed: Mandeep Sekhon
Construction Manager
Reviewed: Will Kettler —
Division Manager
Reviewed: Steven E. White s fP✓wnte(Feb 1,E(
bi4 oe
PST)
Director
Approved. Jean Rousseau
County Administrative Officer,CAD
Approved. Steve Brandau
Board of Supervisors Chairman
Director Approval Date: Feb 1,2022
Scan and forward Director Approved Copy to: CAO Greg Reinke
DPH David Luchini
PWP Business Office Kay Vang
Staff Analyst Linda Guerra
Director Steve White
ti `oL County of Fresno
K E Department of Public Works and Planning
Development Services&Capital Projects Division
FRBS Steven E.White,Director
COUNTY CHANGE ORDER REQUEST_
Project: Animal Services
Contract No.: 20-S-02
Date: 11/29/2021
Contractor: BMY Construction Group,Inc.
5485 E.Olive Ave.
Fresno,California 93727
(559)243-4200
Change Order No.: CCO#096
Construction Contract Dollar Amount(as awarded on 10/30/20): $7,405,000.00
Original Construction Completion Date: 10/02/21
CCO#096 is hereby approved by the County.
Scope of Work:
Door type alteration to 02:S-BLDG 3 door 10b
Attachment:
PCO Proposal,Reference Does,Cover Sheet
Net Additive Change Order Dollar Amount: $1,303.00
Net Additive Calendar Days: t—_J
Net Deductive Change Order Dollar Amount: $0.00
Net Deductive Calendar Days: �]
Total Change Order Dollar Amount To Date: $281,627.12
Adjusted Contract Dollar Amount: $7,686,627.12
Total Adjusted Calendar Days To Date:
Adjusted Construction Completion Date: 11/14/21
Keith Eckert h21?hN lr
s Project Manager
Date: Nov 30,2021
By signing acceptance of this Change Order,the Contractor shall agree to the following:
1.Provide all equipment,material,labor and services required to complete the Scope of Work specified in
this Change Order.
2.The revised Ousted Contract dollar amount and time extension shown in this Change Order as payment in full,
In the event the Contractor does not sbn acceptance of this Change Order,Provisions under the Agreement 16-S-05,
Article V/shell apply.
Accepted By. SMY Construction Group,Inc.
Authorized Signatul
Date: { U
When completed by the Contractor, please scan and return Hard Copies and Color PDF copy to:
Linda Guerra,Staff Analyst
linda uerra-u fresnocountvea.
Fresno CountyDepartment or Public Works and Planning,Development Services&Capital Projects Division
2220 Tulare Street,Eighth Floor
Fresno,CA. 93721
CHANGE ORDER SUMMARY
Project: Animal Services
"II�. �. �. Description
001 6/30/2021 -$13,124.00 0 Credit for less over excavation in building areas
CCO 002 6/30/2021 -$32,673.00 0 Deletion of Ext.glass mat.gypsum sheathing
CCO 003 6/30/2021 $1,992.00 0 Install GFCI on Ext.of BLDG 3
CCO 004 6/30/2021 $1,335.00 0 Additional fixture on pole
CCO 005 6/30/2021 $350.00 0 Additional BLDG 1 outlet
CCO 006 6/30/2021 $1,216.00 0 Add conduit stubs for gates
CCO 007 6/30/2021 $1,457.001 0 Install double acting hinges
CCO 008 9/2/2021 $42,091.00 0 Door type changes
CCO 009 6/30/2021 -$57,287.00 0 Install insulation at various locations
SS9 040 0 Ceiling tile changes
=0 011 N/A
CCO 012 6/30/2021 $683.00 0 Door type changes
CCO 013 $129,241.00 Tile base additions
CCO 014 $10,238.00 Trail drawing
CCO 015 6/30/2021 $2,653.00 0 Add utility sink BLDG 1
CCO 016 7/27/2021 $11,306.00 0 Add trench drains at Ext.kennels
CCO 017 7/27/2021 $18,696.00 0 Add plumbing&utilities
=0 04R N/A
CCO 019 $27,485.00 Sheet metal additions
CCO 020 6/30/2021 -$43,716.00 0 Credit for grade
CCO 021 6/30/2021 $2,721.00 0 Widen footings
CCO 022 6/30/2021 $860.00 0 Extend pop outs
CCO 023 6/30/2021 $3,386.00 0 Additional concrete
GG9 094 N/A
CCO 025 5/6/2021 $21,084.00 0 Additional trench drains
CCO 026 5/19/2021 $2,964.001 0 Added two canopy footings
CCO 027 8/12/2021 -$17,735.00 0 Ext.storefront doors changes
CCO 028 7/29/2021 -$626.00 0 Parking lot striping w/curb and gutter painting
CCO 029 11/18/2021 -$603.91 0 Credit for Demo by Pump station
CCO 030 7/29/2021 $1,761.48 0 Added support posts in 4'Wall
CCO 031 11/18/2021 -$20,966.00 0 Foundation Changes to Each BLDG
CCO 032 8/30/2021 -$1,049.56 0 Credit Electrical for Water Heater Elimination
CCO 033 7/29/2021 -$17,960.00 0 Reber Credit due to foundation changes
CCO 034 11/19/2021 -$10,117.00 0 Guillotine door credit
CCO 035 $108,055.00 Install Site Water and Hose Bibs
CCO 036 1 7/29/2021 -$4,697.00 0 Omit Trench Drain in BLDG 1 RM 1
CCO 037 1 7/29/2021 1 -$8,002.001 0 10mit One WH-2 in Building-2
CCO 038 1 7/29/2021 $6,638.53 0 Prefabricated Shower Enclosures BLDG 2
Page 1 of 3
CHANGE ORDER SUMMARY
Project: Animal Shelter
,No. ���__App. Date Add Credit Rejected Pending Adj.Days Description
CCO 039 9/2/2021 $5,013.61 0 Added water supply for clothes washer
CCO 040 $15,106.23 Install 3 compartment sink RM#9-BLDG 3
CCO 041 7/29/2021 $1,860.70 0 Add hot/cold water supply for added dishwashing
CCO 042 $8,369.65 OFCI dog wash tub
CCO 043 10/13/2021 $4,578.21 0 Install TD-3 BLDG 3
CCO 044 9/2/2021 $11,279.77 0 Install TD-1 BLDG 3 sallyport
CCO 045 1 $6,356.03 Add L1 lav in place of OFCI
CCO 046 8/30/2021 $8,441.51 0 Extended exterior walls-BLDG 2
CCO 047 8/30/2021 -$122,982.00 0 Credit formica in place of INT.wall paneling
CCO 048 7/29/2021 $13,105.44 0 Revised footings for canopy at sally port
CCO 049 9/2/2021 $957.00 0 Additional slab concrete BLDG 3
CCO 050 9/2/2021 $4,634.00 0 EXT.kennel pads outside BLDG 2 originally from PCO#31
CCO 051 9/19/2021 $22,144.00 0 Added dryer and DW hood per mec.Drawing
CCO 052 8/30/2021 $193,529.00 0 Metal wall paneling in BLDG 1&2
CCO 053 8/30/2021 $5,163.00 0 Standard door frame to alumnatone package
CCO 054 $6,707.00 Light kits package
CCO 055 7/29/2021 $2,657.00 0 Restaking for concrete drive BLDG 3
CCO 056 8/30/2021 $12,475.00 0 Additional concrete for rolling gates&curb at sally port
CCO 057 9/28/2021 -$8,682.00 0 Credit for Transfer Doors at Building 2 Package
CCO 058 $131,363.00 Install rolling gates,visions slats,added fencing/gates,etc.
CCO 058.1 11/18/2021 $143,904.00 2 Install rolling gates,visions slats,added fencing/gates,etc.
CCO 059 8/30/2021 $4,265.78 1 Provide electrical for rolling gates
CCO 060 10/22/2021 -$29,050.00 0 Gypsum deduct for installation of metal paneling
CCO 061 10/28/2021 $6,989.00 0 Fabrication,Install,Backfill 15'rebar at canopy footings
CCO 062 9/28/2021 $1,738.00 1 Added electrical BLDG 3
CCO 063 $14,086.00 Extended performance staff change
CCO 063.1 11/19/2021 $14,086.00 15 Extended performance staff change
CCO 064 $14,086.00 Extended GC and time concrete revisions
CCO 064.1 11/19/2021 $14,086.00 15 Extended GC and time concrete revisions
CCO 065 8/30/2021 $2,817.00 3 Extended GC and time due to BLDG 3 mech revisions
CCO 066 8/30/2021 $2,817.00 3 Extended GC and Time Due to Guillotine Door Changes
CCO 067 10/22/2021 $7,062.001 0 Guillotine door frame material change-BLDG 2
CCO 068 9/21/2021 $1,717.00 0 Ext.light changes-BLDG 1
CCO 069 9/21/2021 $605.00 0 Add.Concrete west side of BLDG 3
CCO 070 9/7/2021 $6,875.00 0 Extended GC and time revisions for Guillotine door changes
CCO 071 $7,225.00 0 Install added site hose bibs
CCO 072 10/28/2021 $1,041.00 0 Door type alterations from 01:S to 05:S-BLDG 3
CCO 073 9/17/2021 $0.00 0 Date Adjustments
CCO 074 10/28/2021 $6,396.00 0 Revised concrete slab detail at Sally&food prep drive
CCO 075 10/28/2021 $704.00 0 Additional Outlets BLDG 1 RM 4
CCO 076 1 10/28/2021 1 $691.00 1 1 0 1 Re-Frame roll-up door-BLDG 3
Page 2 of 3
CHANGE ORDER SUMMARY
Project: Animal Shelter
-AppDate Add Credit Rejected Pending Adj.Days Description
CCO 077 10/28/2021 $584.00 0 Additional concrete per ASI&mechanical pad-BLDG 1
CCO 078 10/13/2021 $6,442.00 0 Re-frame Guillotine Door ROs
CCO 079 10/13/2021 $61,416.00 0 Add sidewalk&mow strips
CCO 079.1 $20,761.00 Add sidewalk
CCO 080 10/13/2021 $6,561.00 2 Add hat track for kennel backing
CCO 081 11/2/2021 -$1,066.44 0 Omit plants/irrigation-BLDG 1
CCO 082
CCO 083 11/19/2021 $3,085.00 1 Paint louvers to match windows
CCO 084 11/9/2021 $6,583.00 0 Hose bib relocation due to change in original location-BLDG 3
CCO 085 11/19/2021 $10,047.00 0 Add water lines to make-up air units-BLDG 2
CCO 086
CCO 087
CCO 088
CCO 089
CCO 090
CCO 091
CCO 092
CCO 093
CCO 094 11/19/2021 $7,308.00 0 Add 5'extension on all four kennel locations-BLDG 2
CCO 095 _
CCO 096 11/19/2021 $1,303.00 0 Door type alteration to 02:S-BLDG 3 door 10b�
Totals $671,964.03 -$390,336.91 $525,801.91 $27,468.00 Totals 43 Page 3 of 3
CONSTRUCTION
GROUP INCORPORATED
November 29, 2021
County of Fresno
Construction Division
Attn: Keith Eckert
2220 Tulare Street,711 Floor
Fresno,CA 93721
Re: Animal Control Center
BMY JOB NO.20015
Subject: PCO#96--Added Light Cut Outs and Kits Building 3
Mr. Eckert,
BMY Construction Group, Inc. (BMY) is providing the following PCO for the costs and time associated with the
changes made to Building 3 door 10b.County requested the door type change to 02:S.
BMY is requesting the County to issue a Change Order adding $1,303 to the contract price. In order to perform
the work BMY is requiring a time extension of 0 calendar days.
This PCO is valid for 30 days. Due to unprecedent times in our industry, with volatile material pricing and
delivery, it is of the utmost importance that this PCO be processed quickly. Our industry is currently having
supply issues, The cost of material is on a consistent rise and it is not as readily available,with lead times getting
longer. This may directly impact your project.
BMY is working diligently to process requested changes quickly, keep material pricing down and get material and
products. At this time we need your assistance with timely approvals so we can minimize project impacts.
We appreciate your assistance with this matter. If you have any questions or need any further information,
please do not hesitate to contact me.
Respectfully,
Dylan Medeiros
Project Engineer
Page 1 of 1
5485 East Olive Avenue • Fresno, CA 93727 • Phone (559) 243-4200 • Fax(559) 222-2380
Lic No, 686178
1 =uFAM PCO #096
CONSTRUCTION
GROUP INCnnPORATCD
BMY Construction Group Incorporated Project:20015-Animal Control Center
5485 East Olive Avenue 190 West Dan Ronquillo Drive
Fresno.Califomia 93727-2541 Fresno, California 93706
Phone: (559)243-4200
Fax null
Prime Contract Potential Change Order #096: CE #104 - Add Light Cut Outs
to Double Acting Door Building 3
TO: The County of Fresno, Department of Public FROM: BMY Construction Group. Inc.
Works and Planning 5485 E. Olive Ave
2220 Tulare Street.8th Floor Fresno, California 93727
Fresno.California 93721
PCO NUMBER/REVISION: 096 10 CONTRACT: 20015-Animal Control Center Prime
Contract
REQUEST RECEIVED FROM: Keith Eckert(The County of Fresno, CREATED BY: Dylan Medeiros(BMY Construction
Department of Public Works and Pla) Group,Inc.)
STATUS: Pending-In Review CREATED DATE: 11i29/2021
REFERENCE: PRIME CONTRACT None
CHANGE ORDER:
FIELD CHANGE: No
LOCATION: ACCOUNTING METHOD: Amount Based
SCHEDULE IMPACT: PAID IN FULL: No
EXECUTED: No SIGNED CHANGE ORDER
RECEIVED DATE:
TOTAL AMOUNT: S1.303.44
POTENTIAL CHANGE ORDER TITLE: CE#104-Add Light Cut Outs to Double Acting Door Building 3
CHANGE REASON: Client Request
POTENTIAL CHANGE ORDER DESCRIPTION: (The Contract is Changed As Follows)
CE#104-Add Light Cut Outs to Double Acting Door Building 3
County requested door 10b in Building 3 change to 02:S. Contractor will field cut to allow the 6"x 68"cut out.
ATTACHMENTS:
FIN Building 3 Double Doors_ into Food Storage_msg , _PCO#96-_Proposal.p_df
Noel Roger Davidson II(The County of The County of Fresno, Department of BMY Construction Group, Inc.
Fresno, Department of Public Works and Public Works and Planning
Planning)
2220 Tulare Street, 8th Floor 2220 Tulare Street.8th Floor 5485 E. Olive Ave
Fresno, California 93721 Fresno. California 93721 Fresno,California 93727
SIGNATURE DATE SIGNATURE DATE SIGNATURE DATE
BMY Construction Group Incorporated Page 1 of 1 Printed On: 11/29/2021 12:45 PM
14989 Carnage Ave
Sonora, CA 95370 SIERRA
(209) 532-1801
HARDWARE
Name/Address
BMY Construction Group, Inc. Date Change Order#
5485 East Olive Avenue 11/29/2021 35935
Fresno CA
93727-2541
Animal Control Center -
CHANGE ORDER REQUEST: PO: BMY-4493 Fresno
Description Total
Add full light cut outs to location 3-10b
Add 2 full frames for cut outs
PO: BMY-4493.11024
Please sign and email back to confirm acceptance of above Total pricing. T $1 ,167.37
Phone#
209-532-1801 Signature
Sierra Architectural Products COR 34503
Item Qty. Price Total
LT-B1 Light kit 6x68 2 $102.50 $205.00
0 $0.00 $0.00
0 $0.00 $0.00
$0.00 $0.00
60.00 $0.00
$0.00 $0.00
$0.00 $0.00
Maternal Subtotal $205. 00
Deducts
0 S0.00 $0.00
0 S0.00 $0.00
0 $0.00 $0.00
Deduct Total $0.00
Labor
Labor per hour 4 $85.00 $340.00
Trip Charge 1 $500.00 $500.00
Shipping 0 $0.00 $0.00
Materaall Subtotal: $205.00
Tax @ 7.925% $16.25
Material Total $221.25
Labor $840.00
Shipping $0.00
Labor and Shipping Total $840.00
Subtotal $1.061.25
Profit and overhead 010% $106.12
Total $1,167.37
Total Deducts W 00
Total Due $1,167.37
2