HomeMy WebLinkAbout2005C CCO 04.pdfCOUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
LATON PEDESTRIAN AND DRAINAGE IMPROVEMENTS CHANGE ORDER NO. 4
FEDERAL PROJECT NUMBER: ATPL-5942(275) JUNE 24, 2021
CONTRACT NO. 20-05-C PAGE 1 OF 3
__ Contractor
__ Auditor
__ Business Office
__ Board of Supervisors
__ Const. Management
__ RE/Arch
__ Design
We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment
therefor the prices shown above.
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
TO: EMMETT S EXCAVATION INC.:
Make the following changes to the plans and specifications or do work not in the plans and specifications for
the contract. Because of the change(s), EIGHT (8) - WORKING DAYS will be added to the contract time. The
revised completion date is July 14, 2021.
PART I: COMPENSATE THE CONTRACTOR FOR THE CALIFORNIA STATEWIDE CRUDE OIL
PRICE INDEX FLUCTUATION
Compensate the Contractor for fluctuations greater than or less than five percent in the California
statewide crude oil index for the month the material was placed when compared to the index published
on the month of the bid opening. The California statewide crude oil index for bid opening month,
September 2020, was 233.1. The index was 360.0 for the month of April 2021, which applies to the
pay estimate for the quantity of oil (hot mix asphalt) being compensated for the month of April 2021.
The index was 354.4 for the month of May 2021, which applies to the pay estimate for the quantity of oil
(hot mix asphalt) being compensated for the month of May 2021.
The asphalt content in the hot mix asphalt from Calaveras Materials, Inc. was 4.25 percent in the 3/4-
inch mix. These percentages were reduced to 3.48 percent to account for 15 percent Reclaimed
Asphalt Pavement (RAP) in the mix and applies to 550.54 tons of ¾-inch mix placed in April 2021, and
622.65 tons of ¾-inch mix placed in May 2021. The total adjustment for the asphalt in hot mix asphalt
furnished from Calaveras Materials, Inc. plant resulted in an increase of $4,943.63
TOTAL COST PART I: A $4,943.63 INCREASE
TOTAL TIME EXTENSION PART I: ZERO - WORKING DAYS
PART II: UPGRADE AND INSTALL A TRAFFIC RATED ELECTRICAL PULL BOX EXTRA WORK
In accordance with Section 4-Standard Specifications, upgrade and
install a new traffic rated electrical pull box at the base of the power pole located at approximately Sta. 110+50
30 RT (Fowler Avenue) as required by Pacific Gas & Electric Company. The new traffic rated pull box shall be
installed following the details of the Rule 16 and requirements of PG&E. Perform the work according to the
applicable sections of the Standard Specifications and Special Provisions.
Payment for this work will be made as extra work at an agreed lump sum price of $3,410 according to Section
9-1.03, Payment Scope, of the Special Provisions. This price includes compensation of all labor, materials,
equipment, overhead costs, markups, and incidentals for performing the work.
Two days will be added to the contract time for this work.
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
LATON PEDESTRIAN AND DRAINAGE IMPROVEMENTS CHANGE ORDER NO. 4
FEDERAL PROJECT NUMBER: ATPL-5942(275) JUNE 24, 2021
CONTRACT NO. 20-05-C PAGE 2 OF 3
__ Contractor
__ Auditor
__ Business Office
__ Board of Supervisors
__ Const. Management
__ RE/Arch
__ Design
We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment
therefor the prices shown above.
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
TOTAL COST PART II: $3,410 INCREASE
TOTAL TIME EXTENSION PART II: TWO WORKING-DAYS
PART III: REPLACE DAMAGED WATER VALVE AND RESTORE SUBGRADE EXTRA WORK
In accordance with Section 4-o e Standard Specifications, replace the
damaged 10-inch water main with a new 10-inch water valve and all appurtenances necessary to complete the
repair at approximately Sta. 25+50 20 LT (Latonia Avenue). Compensation includes locating of nearest shut
off valves and cleaning water damage to private driveways and regrading and reestablishing areas of work that
were inundated with water. Perform all work according to the applicable sections of the Standard
Specifications and Special Provisions. Payment for this work will be made as extra work at Force Account
according to Section 9-1.03, Payment Scope, of the Special Provisions; total compensation for this work
resulted in $15,614.65.
Four days will be added to the contract time for this work.
TOTAL COST PART III: $15,614.65 INCREASE
TOTAL TIME EXTENSION PART III: FOUR (4) WORKING-DAYS
PART IV: POTHOLE TO LOCATE THE SHALLOW WATER MAIN AND TRENCH TO PROVIDE A
PROTECTIVE COVER OF CONCRETE SLURRY ABOVE THE WATER MAIN LESS THAN 2.5
FEET BELOW FINISHED GRADE EXTRA WORK
In accordance with Section 4-Standard Specifications, provide
necessary labor, equipment, and materials to locate the shallow 10-inch water main on the north side of
Latonia Avenue, approximately between Sta. 21+00 to Sta. 26+50. Once the depth of the top of pipe has been
established, excavate over the top of the water main to approximately 1-foot above pipe and continue
trenching until the top of pipe is at least 2 ½-foot below finished grade. The excavated trench shall be
backfilled with red dyed concrete slurry approximately 1-foot thick and extend beyond each edge of the pipe by
6 inches. Caution tape listed as Water Main shall be placed above the existing water main within the
excavated trench. Perform all work according to the applicable sections of the Standard Specifications and
Special Provisions. Payment for this work will be made as extra work at Force Account according to Section 9-
1.03, Payment Scope, of the Special Provisions; total compensation for this work resulted in $5,125.96.
Two days will be added to the contract time for this work.
TOTAL COST PART IV: $5,125.96 INCREASE
TOTAL TIME EXTENSION PART IV: TWO (2) WORKING-DAYS
COUNTY OF FRESNO
CONSTRUCTION MANAGEMENT
CONTRACT CHANGE ORDER
LATON PEDESTRIAN AND DRAINAGE IMPROVEMENTS CHANGE ORDER NO. 4
FEDERAL PROJECT NUMBER: ATPL-5942(275) JUNE 24, 2021
CONTRACT NO. 20-05-C PAGE 3 OF 3
__ Contractor
__ Auditor
__ Business Office
__ Board of Supervisors
__ Const. Management
__ RE/Arch
__ Design
We, the above signed contractor, have given careful consideration to the change proposed and hereby agree, if
this proposal is approved, that we will provide all equipment, furnish all materials, except as may otherwise be
noted above, and perform all services necessary for the work above specified, and will accept as full payment
therefor the prices shown above.
If the Contractor does not sign acceptance of this order, his attention is directed to the requirements of the
specifications as to proceeding with the ordered work and filing a written protest within the time therein
specified.
NET COSTS THIS CHANGE ORDER: A $29,094.24 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: EIGHT (8) WORKING-DAYS
JAMES DREWS, Resident Engineer
APPROVAL RECOMMENDED:
EMMETT S EXCAVATION INC.,
Contractor
MANDEEP SEKHON, Construction Engineer
By:
STEVEN E. WHITE, Director of Public Works
Title: and Planning
Accepted Date: Date:
LETTER OF TRANSMITTAL - C.C.O. NO. 4 JUNE 24, 2021
TO: STEVEN E. WHITE, DIRECTOR LATON PEDESTRIAN AND DRAINAGE
PUBLIC WORKS AND PLANNING IMPROVEMENTS
FEDERAL PROJECT NO.: ATPL-5942(275)
CONTRACT NO. 20-05-C
ATTN: MANDEEP SEKHON
CONSTRUCTION ENGINEER
FROM:
JAMES DREWS, Resident Engineer
STATUS OF FUNDS:
Contract Items $ 2,295,015.05 Original Allotment $ 2,422,265.80
Dept. Furnished Materials $ 0.00 Supplemental. Allotment $ 0.00
Previous CCO's $ 17,927.02 Total Allotment $ 2,422,265.80
This CCO $ 29,094.24 Obligated Funds $ 2,342,036.31
Total Obligated Funds $ 2,342,036.31 Unobligated Balance $ 80,299.49
DIRECTOR'S LIMIT to sign change orders is: $ 127,250.75
PART I - DESCRIPTION:
Compensate the Contractor for the California Statewide Crude Oil Price Index Fluctuation.
WHY:
As per Section 9-1.07 Payment Adjustments for Price Index Fluctuations, of the Standard
Specifications, adjustments are to be made for the California Statewide Crude Oil Price Index
fluctuations exceeding five percent of the price index for the month of the bid opening. The California
Statewide Crude Oil Price for bid opening month, September 2020, was 233.1. The index was 360.0
for the month of April 2021, and the index was 354.4 for the month of May 2021 which applies to the
quantity of oil being used for hot mix asphalt for the paving operations. The California Statewide
Crude Oil Price Index fluctuations exceeded five percent during the above-mentioned month when
paving with hot mix asphalt took place, resulting in a $4,943.63 increase.
HOW:
Utilize formula established in Section 9-1.07 of the State Standard Specifications.
COST:
$4,943.63 Increase
LETTER OF TRANSMITTAL - C.C.O. NO. 4 JUNE 24, 2021
PART II - DESCRIPTION:
Upgrade and Install a Traffic Rated Electrical Pull Box Extra Work
WHY:
The project Plans and Special Provisions noted to install a regular fiberglass electrical pull box at the
base of the power pole (Rule 16) that will provide the electrical point of service for the Flashing
Pedestrian Crossing Sign. Upon inspection by the Pacific Gas & Electric inspector, it was noted that
the area could be driven over by vehicles and PG&E required the installation of a traffic rated
electrical pull box.
HOW:
The Contractor was directed to install the necessary traffic rated electrical pull box as required by
PG&E. Compensation for this work will be made at an agreed lump sum price of $3,410, in
accordance with Section 9-1.03 Payment Scope of the Special Provisions. Two working days will be
added to the contract for this work.
COST:
$3,410 Increase
PART III DESCRIPTION:
Replace Damaged Water Valve and Restore Subgrade Extra Work.
WHY:
While removing the existing asphalt concrete surfacing with the use of a milling machine in
an area designated to be drainage ditch on the shoulder area along the north side of Latonia
Avenue, a water valve, which was buried in the asphalt concrete surfacing, was damaged.
The Underground Service Alert (USA) did not mark the valve in the shoulder area. The
milling machine that was removing the existing asphalt concrete hit the top of the water valve
in an area where the existing water main was only 1 ½ feet below the surface. The water
valve broke and discharged a very large amount of water. Other water valves to shut down
and isolate the ruptured water main had to be located and exposed from underneath existing
asphalt concrete. The Contractor was able to replace and restore water service before the
end of the day. The water saturated the subgrade for driveways and HMA walkway. The
subgrade had to be worked and replaced to restore to conditions prior to the damaged water
valve. It was necessary to the replaced the damaged water main, water vales, and to restore
subgrade as extra work.
HOW:
The Contractor was directed to replace the damaged water valve and repair the water main.
Several days were needed to move and dry the saturated native subgrade for use within the
project site. Compensation for this work will be made at Forced Account, in accordance with
Section 9-1.03 Payment Scope of the Special Provision. The Contractor provided invoice billing
for the extra work. The invoices were reviewed and verified for accuracy. The payment was
calculated using appropriate markups and surcharges according to Section 9-
n; the total compensation resulted in $15,614.65.
Four working days will be added to the contract for this work.
LETTER OF TRANSMITTAL - C.C.O. NO. 4 JUNE 24, 2021
COST:
A $15,614.65 Increase
PART IV DESCRIPTION:
Protective Cover of Concrete
Slurry above the Water Main less than 2.5 feet below Finished Grade Extra Work.
WHY:
After repairing the water main and water valve at Sta. 25+50 on Latonia Avenue, previous
as-built plans were provided that showed the water main was installed less than 2 feet below
finished grade. The concern was that the removal of the asphalt concrete surfacing on the
shoulder would expose the existing water main to potential damages. The depth of the
existing water main was potholed in several locations until the water main was verified to be
at least 2.5 feet below finished grade. Any areas where the water main was verified to have
less than 2.5 feet of cover, the Contractor was directed to excavate above the water main
and provide a concrete slurry backfill to protect the shallow water main.
HOW:
The Contractor was directed to pothole and locate the depth of the existing shallow water main.
Once located, the Contractor excavated, and slurry backfilled over any section of the water
main that has less than 2.5 feet of native cover material. Compensation for this work will be
made at Forced Account, in accordance with Section 9-1.03 Payment Scope of the State
Standard Specifications. The Contractor provided invoice billing for the extra work. The
invoices were reviewed and verified for accuracy. The payment was calculated using
appropriate markups and surcharges according to Section 9-
Standard Specification; the total compensation resulted in $5,125.96.
Two working days will be added to the contract for this work.
COST:
A $5,125.96 Increase
NET COST THIS CHANGE ORDER: $29,094.24 INCREASE
NET TIME EXTENSION THIS CHANGE ORDER: EIGHT (8) WORKING-DAYS