HomeMy WebLinkAbout20-S-02 BMY Construction CCOs 041 - 055.pdfDepartment of Public Works and Planning
Development Services & Capital Projects Division
Steven E. White, Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project:Animal Shelter
Contract No.:20-S-02
Date:7/27/2021
Contractor:BMY Construction Group, Inc.
Architect:Roger Davidson
Change Order No.:CCO # 041
Construction Contract Dollar Amount (as awarded on 10/30/20)$7,405,000.00
Director's Change Order Limit:$210,000.00
Contract Time (Calendar Days):298
Construction Start Date:11/02/20
Original Construction Completion Date:7/16/21
Change Order Scope of Work:
Attachment(s):
PCO estimate, CO Proposal
Net Additive Change Order Dollar Amount:$1,860.70
Net Additive Calendar Days:0
Net Deductive Change Order Dollar Amount:$0.00
Net Deductive Calendar Days:0
Total Change Order Dollar Amount To Date -$117,820.29
Adjusted Contract Dollar Amount:$7,287,179.71
Total Adjusted Calendar Days To Date:0
Director's Change Order Limit Balance:$327,820.29
Adjusted Construction Completion Date:07/16/21
Reviewed:Roger Davidson
Architect
Reviewed:Keith Eckert
Project Manager
Reviewed: Mandeep Sekhon
Construction Manager
Reviewed: Steven E. White
Director
Approved: Jean Rousseau
County Administrative Officer, CAO
Approved: Steve Brandau
Board of Supervisors Chairman
Director Approval Date:
Scan and forward Director Approved Copy to:CAO Greg Reinke
DPH David Luchini
PWP Business Office Lemuel Asprec
Construction Manager Mandeep Sekhon
Staff Analyst Linda Guerra
Architect Roger Davidson
Add hot/cold water supply for added dishwashing - Building 3 Room 9
CHANGE ORDER SUMMARY
Project: Animal Shelter
No. App. Date Add ($) Credit ($) Rejected Pending Adj. Days Description
CCO 001 5/6/2021 -$13,124.00 0 Credit for less over excavation in building areas
CCO 002 5/6/2021 -$32,673.00 0 Deletion of Ext. glass mat. gypsum sheathing
CCO 003 5/6/2021 $1,992.00 0 Install GFCI on Ext. of BLDG 3
CCO 004 5/6/2021 $1,335.00 0 Additional fixture on pole
CCO 005 5/6/2021 $350.00 0 Additional BLDG 1 outlet
CCO 006 5/6/2021 $1,216.00 0 Add conduit stubs for gates
CCO 007 5/6/2021 $1,457.00 0 Install double acting hinges
CCO 008 $42,091.00 0 Door type changes
CCO 009 5/6/2021 -$57,287.00 0 Install insulation at various locations
CCO 010 0 Ceiling tile changes
CCO 011 N/A
CCO 012 5/6/2021 $683.00 0 Door type changes
CCO 013 $129,241.00 Tile base additions
CCO 014 $10,238.00 0 Trail drawing
CCO 015 5/6/2021 $2,653.00 0 Add utility sink BLDG 1
CCO 016 $11,306.00 0 Add trench draings at Ext. kennels
CCO 017 5/6/2021 $18,696.00 0 Add plumbing & utilities
CCO 018 N/A
CCO 019 $27,485.00 Sheet metal additions
CCO 020 5/6/2021 -$43,716.00 0 Credit for grade
CCO 021 5/6/2021 $2,721.00 0 Widen footings
CCO 022 5/6/2021 $860.00 0 Extend pop outs
CCO 023 $3,386.00 0 Additional concrete
CCO 024 N/A
CCO 025 5/6/2021 $21,084.00 0 Additional trench drains
CCO 026 5/19/2021 $2,964.00 Added two canopy footings
CCO 027 -$17,735.00 0 Ext. storefront doors changes
CCO 028 -$626.00 0 Parking lot striping w/curb and gutter painting
CCO 029 $603.91 0 Credit for Demo by Pump station
CCO 030 $1,761.48 0 Added upport posts in 4' Wall
CCO 031 $20,966.00 0 Foundation Changes to Each BLDG
CCO 032 $1,049.56 0 Credit Electrical for Water Heater Elimination
CCO 033 -$17,960.00 0 Rebar Credit due to foundation changes
CCO 034 $10,117.00 0 Guillotine door credit
CCO 035 $108,055.00 Install Site Water and Hose Bibs
CCO 036 -$4,697.00 0 Omit Trench Drain in BLDG 1 RM 1
CCO 037 -$8,002.00 Omit One WH-2 in Building-2
CCO 038 $6,638.53 0 Prefrabicated Shower Enclosures BLDG 2
Totals $76,139.01 -$195,820.00 $267,745.00 $85,065.47 Totals 0
CHANGE ORDER SUMMARY
Project: Animal Shelter
No. App. Date Add ($) Credit ($) Rejected Pending Adj. Days Description
CCO 039 $5,013.61 0 Added water supply for clothes washer
CCO 040 $15,106.23 0 Install 3 compartment sink RM #9 - BLDG 3
CCO 041 $1,860.70 0 Add hot/cold water supply for added dishwashing
Totals $77,999.71 -$195,820.00 $267,745.00 $105,185.31 Totals 0
Department of Public Works and Planning
Development Services & Capital Projects Division
Steven E. White, Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project:Animal Shelter
Contract No.:20-S-02
Date:7/27/2021
Contractor:BMY Construction Group, Inc.
Architect:Roger Davidson
Change Order No.:CCO # 048
Construction Contract Dollar Amount (as awarded on 10/30/20)$7,405,000.00
Director's Change Order Limit:$210,000.00
Contract Time (Calendar Days):298
Construction Start Date:11/02/20
Original Construction Completion Date:7/16/21
Change Order Scope of Work:
Attachment(s):
PCO estimate, CO Proposal
Net Additive Change Order Dollar Amount:$13,105.44
Net Additive Calendar Days:0
Net Deductive Change Order Dollar Amount:$0.00
Net Deductive Calendar Days:0
Total Change Order Dollar Amount To Date -$104,714.85
Adjusted Contract Dollar Amount:$7,300,285.15
Total Adjusted Calendar Days To Date:0
Director's Change Order Limit Balance:$314,714.85
Adjusted Construction Completion Date:07/16/21
Reviewed:Roger Davidson
Architect
Reviewed:Keith Eckert
Project Manager
Reviewed: Mandeep Sekhon
Construction Manager
Reviewed: Steven E. White
Director
Approved: Jean Rousseau
County Administrative Officer, CAO
Approved: Steve Brandau
Board of Supervisors Chairman
Director Approval Date:
Scan and forward Director Approved Copy to:CAO Greg Reinke
DPH David Luchini
PWP Business Office Lemuel Asprec
Construction Manager Mandeep Sekhon
Staff Analyst Linda Guerra
Architect Roger Davidson
Revised Canopy Footings - Building 3 Sally Port
CHANGE ORDER SUMMARY
Project:Animal Shelter
No. App. Date Add ($) Credit ($) Rejected Pending Adj. Days Description
CCO 001 5/6/2021 -$13,124.00 0 Credit for less over excavation in building areas
CCO 002 5/6/2021 -$32,673.00 0 Deletion of Ext. glass mat. gypsum sheathing
CCO 003 5/6/2021 $1,992.00 0 Install GFCI on Ext. of BLDG 3
CCO 004 5/6/2021 $1,335.00 0 Additional fixture on pole
CCO 005 5/6/2021 $350.00 0 Additional BLDG 1 outlet
CCO 006 5/6/2021 $1,216.00 0 Add conduit stubs for gates
CCO 007 5/6/2021 $1,457.00 0 Install double acting hinges
CCO 008 $42,091.00 0 Door type changes
CCO 009 5/6/2021 -$57,287.00 0 Install insulation at various locations
CCO 010 0 Ceiling tile changes
CCO 011 N/A
CCO 012 5/6/2021 $683.00 0 Door type changes
CCO 013 $129,241.00 Tile base additions
CCO 014 $10,238.00 0 Trail drawing
CCO 015 5/6/2021 $2,653.00 0 Add utility sink BLDG 1
CCO 016 $11,306.00 0 Add trench draings at Ext. kennels
CCO 017 5/6/2021 $18,696.00 0 Add plumbing & utilities
CCO 018 N/A
CCO 019 $27,485.00 Sheet metal additions
CCO 020 5/6/2021 -$43,716.00 0 Credit for grade
CCO 021 5/6/2021 $2,721.00 0 Widen footings
CCO 022 5/6/2021 $860.00 0 Extend pop outs
CCO 023 $3,386.00 0 Additional concrete
CCO 024 N/A
CCO 025 5/6/2021 $21,084.00 0 Additional trench drains
CCO 026 5/19/2021 $2,964.00 Added two canopy footings
CCO 027 -$17,735.00 0 Ext. storefront doors changes
CCO 028 -$626.00 0 Parking lot striping w/curb and gutter painting
CCO 029 $603.91 0 Credit for Demo by Pump station
CCO 030 $1,761.48 0 Added upport posts in 4' Wall
CCO 031 $20,966.00 0 Foundation Changes to Each BLDG
CCO 032 $1,049.56 0 Credit Electrical for Water Heater Elimination
CCO 033 -$17,960.00 0 Rebar Credit due to foundation changes
CCO 034 $10,117.00 0 Guillotine door credit
CCO 035 $108,055.00 Install Site Water and Hose Bibs
CCO 036 -$4,697.00 0 Omit Trench Drain in BLDG 1 RM 1
CCO 037 -$8,002.00 Omit One WH-2 in Building-2
CCO 038 $6,638.53 0 Prefrabicated Shower Enclosures BLDG 2
Totals $76,139.01 -$195,820.00 $267,745.00 $85,065.47 Totals 0
CHANGE ORDER SUMMARY
Project: Animal Shelter
No. App. Date Add ($) Credit ($) Rejected Pending Adj. Days Description
CCO 039 $5,013.61 0 Added water supply for clothes washer
CCO 040 $15,106.23 0 Install 3 compartment sink RM #9 - BLDG 3
CCO 041 $1,860.70 0 Add hot/cold water supply for added dishwashing
CCO 042 $8,369.65 0 OFCI dog wash tub
CCO 043 $4,578.21 0 Install TD-3 BLDG 3
CCO 044 $11,279.77 0 Install TD-1 BLDG 3 sallyport
CCO 045 $6,356.03 0 Add L1 lav in place of OFCI
CCO 046 $8,441.51 0 Extended exterior walls - BLDG 2
CCO 047 -$79,448.00 0 Credit formica in place of INT. wall paneling
CCO 048 $13,105.44 0 Revised footings for canopy at sally port
Totals $91,105.15 -$195,820.00 $267,745.00 $64,762.48 Totals 0
Department of Public Works and Planning
Development Services & Capital Projects Division
Steven E. White, Director
PROJECT MANAGEMENT CONSTRUCTION CHANGE ORDER REQUEST
This Document is for Fresno County Internal Use Only
Project:Animal Shelter
Contract No.:20-S-02
Date:7/27/2021
Contractor:BMY Construction Group, Inc.
Architect:Roger Davidson
Change Order No.:CCO # 055
Construction Contract Dollar Amount (as awarded on 10/30/20)$7,405,000.00
Director's Change Order Limit:$210,000.00
Contract Time (Calendar Days):298
Construction Start Date:11/02/20
Original Construction Completion Date:7/16/21
Change Order Scope of Work:
Attachment(s):
PCO estimate, CO Proposal
Net Additive Change Order Dollar Amount:$2,657.00
Net Additive Calendar Days:0
Net Deductive Change Order Dollar Amount:$0.00
Net Deductive Calendar Days:0
Total Change Order Dollar Amount To Date -$102,057.85
Adjusted Contract Dollar Amount:$7,302,942.15
Total Adjusted Calendar Days To Date:0
Director's Change Order Limit Balance:$312,057.85
Adjusted Construction Completion Date:07/16/21
Reviewed:Roger Davidson
Architect
Reviewed:Keith Eckert
Project Manager
Reviewed: Mandeep Sekhon
Construction Manager
Reviewed: Steven E. White
Director
Approved: Jean Rousseau
County Administrative Officer, CAO
Approved: Steve Brandau
Board of Supervisors Chairman
Director Approval Date:
Scan and forward Director Approved Copy to:CAO Greg Reinke
DPH David Luchini
PWP Business Office Lemuel Asprec
Construction Manager Mandeep Sekhon
Staff Analyst Linda Guerra
Architect Roger Davidson
Re-staking due to Structural & Archtiectural discrepency
CHANGE ORDER SUMMARY
Project:Animal Shelter
No. App. Date Add ($) Credit ($) Rejected Pending Adj. Days Description
CCO 001 5/6/2021 -$13,124.00 0 Credit for less over excavation in building areas
CCO 002 5/6/2021 -$32,673.00 0 Deletion of Ext. glass mat. gypsum sheathing
CCO 003 5/6/2021 $1,992.00 0 Install GFCI on Ext. of BLDG 3
CCO 004 5/6/2021 $1,335.00 0 Additional fixture on pole
CCO 005 5/6/2021 $350.00 0 Additional BLDG 1 outlet
CCO 006 5/6/2021 $1,216.00 0 Add conduit stubs for gates
CCO 007 5/6/2021 $1,457.00 0 Install double acting hinges
CCO 008 $42,091.00 0 Door type changes
CCO 009 5/6/2021 -$57,287.00 0 Install insulation at various locations
CCO 010 0 Ceiling tile changes
CCO 011 N/A
CCO 012 5/6/2021 $683.00 0 Door type changes
CCO 013 $129,241.00 Tile base additions
CCO 014 $10,238.00 0 Trail drawing
CCO 015 5/6/2021 $2,653.00 0 Add utility sink BLDG 1
CCO 016 $11,306.00 0 Add trench draings at Ext. kennels
CCO 017 5/6/2021 $18,696.00 0 Add plumbing & utilities
CCO 018 N/A
CCO 019 $27,485.00 Sheet metal additions
CCO 020 5/6/2021 -$43,716.00 0 Credit for grade
CCO 021 5/6/2021 $2,721.00 0 Widen footings
CCO 022 5/6/2021 $860.00 0 Extend pop outs
CCO 023 $3,386.00 0 Additional concrete
CCO 024 N/A
CCO 025 5/6/2021 $21,084.00 0 Additional trench drains
CCO 026 5/19/2021 $2,964.00 Added two canopy footings
CCO 027 -$17,735.00 0 Ext. storefront doors changes
CCO 028 -$626.00 0 Parking lot striping w/curb and gutter painting
CCO 029 $603.91 0 Credit for Demo by Pump station
CCO 030 $1,761.48 0 Added upport posts in 4' Wall
CCO 031 $20,966.00 0 Foundation Changes to Each BLDG
CCO 032 $1,049.56 0 Credit Electrical for Water Heater Elimination
CCO 033 -$17,960.00 0 Rebar Credit due to foundation changes
CCO 034 $10,117.00 0 Guillotine door credit
CCO 035 $108,055.00 Install Site Water and Hose Bibs
CCO 036 -$4,697.00 0 Omit Trench Drain in BLDG 1 RM 1
CCO 037 -$8,002.00 Omit One WH-2 in Building-2
CCO 038 $6,638.53 0 Prefrabicated Shower Enclosures BLDG 2
Totals $76,139.01 -$195,820.00 $267,745.00 $85,065.47 Totals 0
CHANGE ORDER SUMMARY
Project: Animal Shelter
No. App. Date Add ($) Credit ($) Rejected Pending Adj. Days Description
CCO 039 $5,013.61 0 Added water supply for clothes washer
CCO 040 $15,106.23 0 Install 3 compartment sink RM #9 - BLDG 3
CCO 041 $1,860.70 0 Add hot/cold water supply for added dishwashing
CCO 042 $8,369.65 0 OFCI dog wash tub
CCO 043 $4,578.21 0 Install TD-3 BLDG 3
CCO 044 $11,279.77 0 Install TD-1 BLDG 3 sallyport
CCO 045 $6,356.03 0 Add L1 lav in place of OFCI
CCO 046 $8,441.51 0 Extended exterior walls - BLDG 2
CCO 047 -$79,448.00 0 Credit formica in place of INT. wall paneling
CCO 048 $13,105.44 0 Revised footings for canopy at sally port
CCO 049 $957.00 0 Additional slab concrete BLDG 3
CCO 050 $4,634.00 0 EXT. kennel pads outside BLDG 2 originally from PCO#31
CCO 051 $24,253.00 0 Added dryer and DW hood per mec. Drawing
CCO 052 $135,575.00 0 Metall wall paneling in BLDG 1 & 2
CCO 053 $5,163.00 0 Standard door frame to alumnatone package
CCO 054 $6,707.00 0 Light kits package
CCO 055 $2,657.00 0 Restaking for concrete drive BLDG 3
Totals $93,762.15 -$195,820.00 $267,745.00 $242,051.48 Totals 0