AMENDMENT NUMBER THREE (3)
Agreement Number: P -20-225
May 18, 2021
Master Agreement
Contract Number P -20-225 covering the purchase of Asphalt and Various Aggregates is amended as
follows:
The County of Fresno hereby accepts your price increase notice dated April 15, 2021 to be effective May
15, 2021 in accordance with the terms and conditions of our Contract Number P-20-225 and Revised
Attachment. All orders placed prior to May 15, 2021 will be priced in accordance with current
contract pricing.
Maximum: In no event shall services performed and/or fees paid under this Agreement be in excess of
thirty-five million dollars, ($35,000,000.00).
Please acknowledge your acceptance by returning all pages of this letter to my office via email or USPS.
If you have any questions, please contact Debbie Scharnick, Purchase Technician II , at (559) 600-7110
or email dscharnick@fresnocountyca.gov.
FOR THE COUNTY OF FRESNO
Gary E. Cornuelle
Purchasing Manager
333 W. Pontiac Way
Clovis, CA 93612
GEC:DS
CONTRACT NO. P-20-225 Page 2
Master Agreement
May 18, 2021
G:\PUBLIC\CONTRACTS & EXTRACTS\2020 CONTRACTS\20-225 ASPHALT CONCRETE MASTER\CONTRACT
AND AMENDMENTS\20-225 AMEND 3.DOC
CONTRACTOR TO COMPLETE:
Company: Vulcan Construction
Type of Entity:
Individual Limited Liability Company
Sole Proprietorship Limited Liability Partnership
Corporation General Partnership
Signature
Print Name and Title Date
Signature
Print Name and Title Date
Address City State Zip
TELEPHONE NUMBER FAX NUMBER E-MAIL ADDRESS
ACCOUNTING USE ONLY
ORG No.:
Account No.:
Requisition No.:
(1/2020)
CONTRACT NO. P-20-225 Page 3
Master Agreement
May 18, 2021
G:\PUBLIC\CONTRACTS & EXTRACTS\2020 CONTRACTS\20-225 ASPHALT CONCRETE MASTER\CONTRACT
AND AMENDMENTS\20-225 AMEND 3.DOC
Revised Attachment “A”
Part A: Slow Cure (SC) Asphalt Concrete
For each of the specified material below, please list cost per ton for plant pick-up rate. Please
itemize any additional materials you are able to provide, not listed below. Quoted prices shall
include all labor, materials, taxes, insurance, and miscellaneous fees per ton. Sales tax shall be
excluded from the prices quoted.
Item Description Yearly use Unit Price Plant Location
1 3/8” SC - 800
700 tons $69.00 per ton Sanger/Madera
2 3/8” SC - 3000
250 tons $69.00 per ton Sanger/Madera
3 $________.__ per ton
4 $________.__ per ton
5 $________.__ per ton
6 $________.__ per ton
7 Environmental Fee $5.00 per load
Part B: Performance Graded (PG) Asphalt Concrete
For the specified material below, please list cost per ton for plant pick-up rate Please itemize
any additional materials you are able to provide, not listed below. Quoted prices shall include
all labor, materials, taxes, insurance, and miscellaneous fees per ton. Sales tax shall be
excluded from the prices quoted.
Item Description Yearly use Unit Price Plant Location
1 PG 64-10, ¾” Max
25,000 tons $54.00 per ton Ashlan/Sanger/Madera
2 PG 64-10, ½” Max
80,000 tons $54.00 per ton Ashlan/Sanger/Madera
3 PG 64-10, 3/8” Max
20,000 tons $56.00 ton Ashlan/Sanger/Madera
4 PG 64-10, ST 1/2" Max
Medium
150 tons $54.00 per ton Ashlan/Sanger/Madera
5 PG 64-10, ST 3/8" Max 150 tons $56.00 per ton Ashlan/Sanger/Madera
CONTRACT NO. P-20-225 Page 4
Master Agreement
May 18, 2021
G:\PUBLIC\CONTRACTS & EXTRACTS\2020 CONTRACTS\20-225 ASPHALT CONCRETE MASTER\CONTRACT
AND AMENDMENTS\20-225 AMEND 3.DOC
6 PG64-10, Sheet Mix 150 tons $62.00 per ton Ashlan/Sanger/Madera
7 PG 70-10, ¾” Max
10,000 tons $55.00 per ton Ashlan/Sanger/Madera
8 PG 70-10, ½” Max
15,000 tons $55.00 per ton Ashlan/Sanger/Madera
9 PG 70-10, 3/8” Max
10,000 tons $62.00 per ton Ashlan/Sanger/Madera
10 PG 64-28, 3/4” Max 4,000 tons $69.00 per ton Ashlan/Sanger/Madera
11 PG 64-28, 1/2” Max 4,000 tons $69.00 per ton Ashlan/Sanger/Madera
12 PG 64-28, 3/8” Max 4,000 tons $69.00 per ton Ashlan/Sanger/Madera
13 PG 64-16, 3/4” Max 4,000 tons $58.00 per ton Ashlan/Sanger/Madera
14 PG 64-16, 1/2” Max 4,000 tons $58.00 per ton Ashlan/Sanger/Madera
15 PG 64-16, 3/8” Max 4,000 tons $59.00 per ton Ashlan/Sanger/Madera
16 ST 1/2" HMA Type A 6,000 tons $54.00 per ton Ashlan/Sanger/Madera
17 ½” HMA Commercial 30 tons $53.00 per ton Ashlan/Sanger/Madera
18 1/2" HMA 64-10R15 20,000 tons $54.00 per ton Ashlan/Sanger/Madera
19 ¾” HMA 64-10R15LAS B 5 tons $69.00 per ton Ashlan/Sanger/Madera
20 ST ½ HMA 64-10 with Warm Mix $64.00per ton
Ashlan/Sanger/Madera
21 ST ¾ 64-10 with Warm Mix $64.00 per ton
Ashlan/Sanger/Madera
22 $________.__ per ton
23 $________.__ per ton
24 $________.__ per ton
25 Environmental Fee $5.00 per load
Part C: Aggregates
For the specified material below, please list cost per ton for plant pick-up rate. Please itemize
any additional materials you are able to provide, not listed below. Quoted prices shall include
all labor, materials, taxes, insurance, and miscellaneous fees per ton. Sales tax shall be
excluded from the prices quoted.
Item Description Yearly use Unit Price Plant Location
1 ¾” Max Aggregate Base, Class 2
65,000 tons $12.00 per ton Sanger
2 Permeable Material Class I, Type 5,000 tons $________.__ per ton
CONTRACT NO. P-20-225 Page 5
Master Agreement
May 18, 2021
G:\PUBLIC\CONTRACTS & EXTRACTS\2020 CONTRACTS\20-225 ASPHALT CONCRETE MASTER\CONTRACT
AND AMENDMENTS\20-225 AMEND 3.DOC
B
3 Permeable Material Class 2
5,000 tons $22.00 per ton Sanger
4 Concrete Sand
5,000 ton $10.00 per ton Sanger
5 Skid Sand (50% ¼” Crushed
Rock, 50% Concrete Sand)
5,000 tons $20.00 per ton Sanger
6 Plaster Sand
5,000 tons $21.00 per ton sanger
7 Pit Surge
1,000 tons $________.__ per ton
8 Crushed Rock
1,000 tons $22.00 per ton Sanger
9 Cobble Stone, 6” Max/Cobble
Stone, 4”-6”
5,000 tons $________.__ per ton
10 Cobble Stone, 12” Max, Cobble
Stone 6”-12”
5,000 tons $________.__ per ton
12 Snow Sand 707 tons $15.00 per ton Sanger
13 Rock Dust 76 tons $9.00 per ton sanger
15 ¾” Caltrans Class 2 AB 5,000 tons $12.00 per ton Sanger
16 $________.__ per ton
17 $________.__ per ton
18 $________.__ per ton
19 $________.__ per ton
20 $________.__ per ton
21 $________.__ per ton
22 $________.__ per ton
23 $________.__ per ton
24 Environmental Fee $5.00 per load
CONTRACT NO. P-20-225 Page 6
Master Agreement
May 18, 2021
G:\PUBLIC\CONTRACTS & EXTRACTS\2020 CONTRACTS\20-225 ASPHALT CONCRETE MASTER\CONTRACT
AND AMENDMENTS\20-225 AMEND 3.DOC
Equipment Type (please list, if
applicable)
Zone Hourly Rate for 1-8-
hour work day
Hourly Rate
exceeding 8-hour
workday (includes
weekday hours,
weekends, holidays,
etc.)
1 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour
2 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour
3 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour
4 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour
5 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour
6 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour
7 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour
8 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour
9 Zone A $________.__ per
hour
$________.__ per
hour
CONTRACT NO. P-20-225 Page 7
Master Agreement
May 18, 2021
G:\PUBLIC\CONTRACTS & EXTRACTS\2020 CONTRACTS\20-225 ASPHALT CONCRETE MASTER\CONTRACT
AND AMENDMENTS\20-225 AMEND 3.DOC
Zone B $________.__ per
hour
$________.__ per
hour
10 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour
11 Zone A $________.__ per
hour
$________.__ per
hour
Zone B $________.__ per
hour
$________.__ per
hour